LOT 202.02 Main Steam Flashcards
- LOT 202.02 Main Steam*
- *
Which steam lines go to which steam chest?
“A” / “D” connect to West steam chest
“B” / “C” connect to East steam chest
Connect to equalizing header before going to main turbine.
- LOT 202.02 Main Steam*
- *
Where does AFW #14 tap off the Main Steam system?
SG “D” PORV line
- LOT 202.02 Main Steam*
- *
What are the design operating parameters of the Main steam system?
- Pressure:*
- *1285 psig**
- 1185 psig - 1050 psig (0% - 100%)*
- Temperature:*
- *600 ˚F**
- Saturated System (Dependent on pressure)*
- Flow:*
- *17,431,819 lbm/hr**
- LOT 202.02 Main Steam*
- *
What is steam line equalizing pressure (PT-557) used for?
SGFPT control
- *Steam Dumps**
- When in pressure control mode*
Located on CP007
- LOT 202.02 Main Steam*
- *
What loads are supplied from the MS header?
MSRs (2)
Steam Dumps (12)
SGFPTs (3)
Gland Seal
Aux Steam
- LOT 202.02 Main Steam*
- *
A loss of power to what components will cause the SG PORVs to close?
Hydraulic Pump:
ESF MCCs
Train A: SG “A” and SG “D” / Train B: SG “B” / Train C: SG “C”
Can be bypassed using station blackout switches
Once bypassed, can operate PORVs with accumulator pressure (1.5 strokes)
- Servo Motors:*
- *PORV “A”: DP1201**
PORV “B”: DP1203
PORV “C”: DP1204
PORV “D”: DP1202
- LOT 202.02 Main Steam*
- *
How is the MSIVs operated?
Air Open / Spring Close
- Closes in ≤ 5 sec upon receipt of close signal
- Both MSIVs and MSIBs fail closed on loss of air
- MSIVs stay open on loss of power
- Note:*
- Physically located on IVC 58’
- Controlled from CP006