IRO-014/017 Coordination Among RCs / Outages Flashcards

1
Q

IRO-014 If two RC’s do not agree on whether emergency conditions exist, what happens?

A

Both RC’s will act as if an emergency exists.
THe RC declaring an emergency must work on a plan for mitigating it.
Each impacted RC must implement the plan, unless such actions would violate safety / equipment / regulatory requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the time frame for reviewing and updating RC operating procedures / processes / plans as identified in IRO-014 R1 ?

A

Annually, with no more than 15 months between reviews.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What approval is needed on RC operating procedures / processes / plans as identified in IRO-014 R1?

A

Written agreement must be obtained from all RC’s required to take indicated actions, for each update.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the distribution requirements for RC operating procedures / processes / plans as identified in IRO-014 R1?

A

Distribute to all RC’s required to take indicated actions within 30 days of an update.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

IRO-014 R1

What is included in OP’s for activities that require notification or coordination of actions involving neighboring RC’s?

A
  • criteria, process for notifications
  • energy and capacity shortages
  • voltage control / coord. of reactive resources
  • exchange of outage information
  • provisions for periodic communications
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

IRO-017 R1

What are the RC requirements for outage coordination?

A

Must maintain an Outage Coordination Process

for: Generation and Transmission outages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

IRO-017 R2

Which entities are required to comply with the RC’s outage coordination process?

A

Transmission Operators and Balancing Authorities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

IRO-017 R3

Who must provide Planning Assessments to impacted RC’s?

A

Planning Coordinator and Transmission Planner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

IRO-017 R4

What must happen with identified issues / conflicts with planned outages in near-term transmission planning horizon?

A

Each Planning Coordinator / Transmission planner must jointly develop solutions with respective RC’s .

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

IRO-17 R1 cont. what is in the outage coordination process:

A
  • identify roles and reporting responsibilities
  • outage submission timing req’s
  • define process to evaluate impact
  • define process to coordinate resolution of conflicts with TOps / BA;s, other RCs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly