IRO-014/017 Coordination Among RCs / Outages Flashcards
IRO-014 If two RC’s do not agree on whether emergency conditions exist, what happens?
Both RC’s will act as if an emergency exists.
THe RC declaring an emergency must work on a plan for mitigating it.
Each impacted RC must implement the plan, unless such actions would violate safety / equipment / regulatory requirements.
What is the time frame for reviewing and updating RC operating procedures / processes / plans as identified in IRO-014 R1 ?
Annually, with no more than 15 months between reviews.
What approval is needed on RC operating procedures / processes / plans as identified in IRO-014 R1?
Written agreement must be obtained from all RC’s required to take indicated actions, for each update.
What are the distribution requirements for RC operating procedures / processes / plans as identified in IRO-014 R1?
Distribute to all RC’s required to take indicated actions within 30 days of an update.
IRO-014 R1
What is included in OP’s for activities that require notification or coordination of actions involving neighboring RC’s?
- criteria, process for notifications
- energy and capacity shortages
- voltage control / coord. of reactive resources
- exchange of outage information
- provisions for periodic communications
IRO-017 R1
What are the RC requirements for outage coordination?
Must maintain an Outage Coordination Process
for: Generation and Transmission outages.
IRO-017 R2
Which entities are required to comply with the RC’s outage coordination process?
Transmission Operators and Balancing Authorities
IRO-017 R3
Who must provide Planning Assessments to impacted RC’s?
Planning Coordinator and Transmission Planner
IRO-017 R4
What must happen with identified issues / conflicts with planned outages in near-term transmission planning horizon?
Each Planning Coordinator / Transmission planner must jointly develop solutions with respective RC’s .
IRO-17 R1 cont. what is in the outage coordination process:
- identify roles and reporting responsibilities
- outage submission timing req’s
- define process to evaluate impact
- define process to coordinate resolution of conflicts with TOps / BA;s, other RCs