Earned Value Calculations Flashcards

1
Q

Planned Value

PV

A

The Authorised budget assigned to Project Work

The value of the work planned to be completed to a point in time, usually the data date, or project completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Earned Value

EV

A

The measure of work performed expressed in terms of the budget authorized for that work.

The planned value of all the work completed (earned) to a point in time, usually the data date, without reference to actual costs.

EV = sum of the planned value of completed work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Actual Cost

AC

A

The realized cost incurred for the work performed on an activity during a specific time period.

The actual cost of all the work completed to a point in time, usually the data date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Budget at Completion

BAC

A

The sum of all budgets established for the work to be performed

The value of total planned work, the project cost baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Variance

CV

A

The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost

The difference between the value of work completed to a point in time, usually the data date, and the actual costs to the same point in time.
CV = EV - AC

Positive = Under planned cost

Neutral = On planned cost

Negative - Over planned cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Variance

SV

A

The amount by which the project is ahead or behind the planned delivery date, at a given point in time, expressed as the difference between the earned value and the planned value.

The difference between the work completed to a point in time, usually the data date, and the work planned to be completed to the same point in time.

SV = EV - PV

Positive - Ahead of Schedule

Neutral - On schedule

Negative - Behind Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Variance at Completion

VAC

A

A projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at
completion.

The estimated difference in cost at the completion of the project

VAC = BAC - EAC

Positive - Under planned cost
. Neutral - On planned cost
Negative - Over planned cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost Performance Index

CPI

A

A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost

A CPI of 1.0 means the project is exactly on budget, that the work actually done so far is exactly the same as the cost so far. Other values show the percentage of how much costs are over or under the budgeted I amount for work accomplished.

CPI = EV/AC

> 1.0 = Under planned cost

exactly 1.0 = On planned cost

<1.0 = Over planned cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Schedule Performance Index

SPI

A

A measure of schedule efficiency expressed as the ratio of earned value to planned value.

An SPI of 1.0 means that the project is exactly on schedule, that the work actually done so far is exactly the same as the work planned to be done so far. Other values show the percentage of how much costs are over or under the budgeted amount for work planned.

SPI = PV/EV

> 1.0 = Ahead of Schedule

exactly 1.0 = On Schedule

<1.0 = Behind Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate at Completion

EAC

A

The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.

If the CPI is expected to be the same for the remainder of the project, EAC can be calculated using:

EAC = BAC/CPI
If future work will be accomplished at the planned rate, use:

EAC = AC + BAC - EV

If the initial plan is no longer valid, use:

EAC = AC + Btm up ETC

If both the CPI and SPI influence the remaining work, use:

EAC = AC + ((BAC - EV)/(CPIxSPI))

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Estimate to Completion

ETC

A

The expected cost to finish all the remaining project work.

Assuming work is proceeding on plan, the cost of completing the remaining authorized work can be calculated using:

ETC = EAC - AC

Reestimate the remaining work from the bottom up.

ETC = Re-estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

To Complete Performance Index

TCPI

A

A measure of the cost performance that must be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding worfc to the budget available.

The efficiency that must be maintained in order to complete on plan.

TCPI = (BAC - EV)/(BAC - AC)

The efficiency that must be maintained in order to complete the current EAC.

TCPI = (BAC-EV)/(EAC-AC)

Greater than 1.0 - Harder to complete

Exactly 1.0 - Same to complete

Less than 1.0 - Easier to complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly