Design and spec Flashcards

1
Q

Tell me about your preperation of the design and specification of a building project from outline proposals to compeltion of the design and specficiation process.

A

I have recently been involved with the specification design and delivery of a cyclical redeocration project. The outline proposal was developed from a detail condition survey of the scheme, which reommendations were then included within a report. A significant item was to replace the timber walkway balustrades. However, due to budget constraints and leaseholder S20, the client requested their repair rather than replacement. I completed a detailed survey of all balustrades and quantified the different repairs required. I then specified the type of materials, treated softwood, fixings and decoration requirments.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Talk me through your experience of the specification process, including detailed knowledge of the main methods of specification.

A

I have been involved with different projects through the entire design and specification process. The process can be intitated at RIBA Stages 0 and continues at 5. For example, in my case study intital design requirements were determined at the strip out stage where a descrptive specifcation of elements meeting building regulations were discussed. For example the requirement of fire compartmentation to the hall and acoustic requirements to the party wall. I would then develop a performance specification that could be issued to the contractor outlining exact materials, methods and standards to be completed. During the project I was completed a prescriptive specifiction of the fire curtain for the contractor to implement that would meet the requirements of buildng regulations part B.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How have you dealt with the design and specifiction process, and its relevance and importance to the procurement and execution of the contract selected for the building works?

A

I have been involved with projects that have been procured through different contracts. I have developed specifications for fire door sets that are descriptive so that the works can procured through a JCT MW with contractors design to allow for the specialsied contractor to procure materails that met performance requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How have you managed the design process to incorporate design works by other in the specification?

A

With reference to Hillcrest, the project involved elements of asbestos removal and replacement of meters and electrical services. At my appointment, I informed the client that specialist consultants should be appointed to design the areas around these elements. I appointed an M&E and Asbestos consultant from our internal approved consultant list. I communicated with them and met them onsite to ensure that the objectives/brief was understood. A plan of work and M&E spec was developed that I included within my overall specification.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Hillcrest Fire Remedial Works
What materials did you specifiy for the compartmentation to the gas services in the duct?

A

I specified a gyproc shaft system that would meet the 30 minute fire resistance requirement. I also included a FD30s intumescent grills and mainteance hatches.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Hillcrest Fire Remedial Works
How did you deal with the ventilation and what guidance a part from the building regulations did you follow?

A

To address the ventilation within the riser we introduced an intumescent grill at the top of the riser and at the bottom of the riser. We then allowed for the floor slab to core drilled to allow for natural ventilation. I referred to BS 6891 table 6 which outlined a requirement for the grills to be 0.05m2.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Hillcrest Fire Remedial Works
How did you design access into the duct for mainteance purposes?

A

To ensure that mainteance access was available to to all of the risers, I specified that a FD30 maintence hatch was installed at high and low levels.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Hillcrest Fire Remedial Works
Did you check the duct where the pipework went into individual flats or other areas?

A

The view of the gas services were obstructed by the asbestos insulation board within the cupboard. As I was unable to prescribe firestopping works to be priced exactly, I included a schedule of rates within the specification for a range of firestopping works for the contractor to price. I also included within the specification an item for the CA to inspect all areas once asbestos had been removed and new services had been installed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Hillcrest Fire Remedial Works
What building regulations did you comply with?

A

All works related to firestopping and the new riser fire doors were compliant with building regulations. Riser doors to FD30 and firestopping to maintaint the 60min compartment line. The electrical components of the project would all be self certified. Approved document B.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Wigston Close, Structural works
How did you incorporate the structural engineers’ requirements into your specification?

A

I included the structural eningeers requirements as an appendix to my specification document. I then ensured that all prescriptive standards for materials and workmanship were included in my document.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Wigston Close, Structural works
What if any immediate work did you specify?

A

Due to the wall being deemed as a dangerous structure, immediate works involved decanting residents, proping the walls with accrow props and steel beams and hording the external wall to secure the property.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Wigston Close, Structural works
What were the additional items that you added to the specification?

A

Additional items included adding decorations and floor covering to the specifiction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the difference between a performance and a prescription specification?

A

Performance specifcation - also known as open
Prescriptive specification - also known as closed
Performance provides more freedom to contractor to achieve the desired end goal, therefore potentailly finding best value for money. Typically used on straight forward projects.
Prescriptive specification sets out exactly what will be expected from the contractor at the end of the project. This enables the client to be sure of what they will get for their investement. Often used in projects where specialist systems are requried.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What type of specifcation did you use in your case study?

A

The specification used for St Francis house was a mixture of performance and prescriptive. I used presriptive methods for elements that required building regulation control i.e. inuslation, acoutsic plaster board and structure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the defintion of an adaptable dwelling under building regulations part M?

A

Dwellings that have some features of a fully accessible dwelling such as wider doors but with some omissions. Allowing for the property to be adapated to meet the requirments of the occupants over time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the purpose of Adaptable dwellings?

A

Occupants who do not require accesible apartments are relcuctant to live in them, this allows for the property to be used and adapted easily.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Warley Hill
How did you apply building regulations to the design of the entrance?

A

External landing with a minimum width of 1200mm
Light outside entrance with motion detecotr
Minimum clear width opening of 850mm
Accesible threshold - level threshold

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Warley Hill
How did you apply the building regulations to the circulation areas and the door widths?

A

All doors had a clear opening of 900mm
Clear width of hall or landing 900mm
Localised obstructions (radiators) not in front of door ways

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Warley Hill
How did you apply building regulations to the design of the habitable areas

A

Minimum clear space in front of kithcen appliances of 1200mm
Opener in living room 1200mm above floor level
750mm free space to either side of bed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Warley Hill
How did you apply building regulations to the design of the bathroom

A

Door opened outward into the hallway
Shower had potentaial for level access adaptation
Access zones for basin and WC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Warley Hill
How did you apply building regulations to the desing of the services?

A

All sockets, stopcocks, controls between 450 and 1200mm above floor level and 300mm away for wall
Consumer switches mounted between 1300a nd 1450mm
Hnadles to windows located at 450mm and 1400mm from floor level
Wireless thermostat controls

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Warley Hill, Office Refurb
What was the relevant building regulation and how was it applied to the specification of the polypearl porcuct?

A

The relevant building regulation is Part L. It required the improvement in thermal performance of the existing elements to have an improved U-value of 0.55 W/m2.k. The polypearl system improved the U value to 0.23.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Tottenham Feasibility
Why did you present a range of different options to solve the security issues?

A

There were leaseholders within the block
Client asked for a range of options relating to cost
Options that included the renewal or modifcation of door entry system
The was scope to re-arrange the bin store within the car park to solve the issue subject to cost
Client wanted to present options during S20 process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Tottenham Feasibility
What options did you present to your client?

A

Installing a manual swing gate on the existing property
Installing a automatic swing gate on the existing boundary line
Installing a cantilever gate system on now boundary to maximise space
Moving the boundary line to incorporate a parking space that was currently outside the existing wall

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Tottenham Feasibility
How did you determine the space outside the existing boundary belonged to your client?

A

I procured the title plans from the land registry which outlined that the space outside existing boundary was included within the clients freehold

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Tottenham Feasibility
Were there any regulatory issues you encountered?

A

Neighbour had an easement through the car park
Client ahd to follow the S20 process
Planning would also be required due to nature of works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Tottenham Feasibility
What issues did you encounter with your suggestions

A

Any automated gate would need to be interegrated with existing entry system
I attendted site with a specclist contractor to determien whetehr it was feasible
Due to age and current condition of system, it could nto be intergrated
Therefore, there was a signifcant cost to renew the system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Explain your understanding of the RICS Design and Specification Guidance Note 2013

A

Provides professional practitioners with best practice guidance relevant to the tasks and processes of design and specification (small to medium projects)
Guidance covers;
Roles of the lead consultant
Management
Common considerations (compliance, sustainability, safety)
Design Process Management Documetnation (documents, NBS, standardsiation)
Design Process (RIBA)
Specifciation and preperation
Legilsative compliance
Construction stage
Comissionin/Occupation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What should be included in a client brief?

A

Statement of the problem they want to solve
Address of property
Vulnearble residents/ contact details

Hazards/Asbestos Register
Instruction f services they want to include
Access provisions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What is a client brief?

A

The purpose of a client brief is to provide a firm foundation for the initiation of the project.
It is a formal statement of the objectives and functional and operational requirements of the finished project.
It should be in sufficient detail to enable the integrated project team to execute the specification and detailed design of the work and is therefore an essential reference for the team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

You mention technical standards, name some?

A

Architects Journal Guidance & Articles
British Standards
BRE Digests and Good Repairs Guides
English Heritage Journals and Guides

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Explain your understanding of the RIBA Works Stages 2020

A

0- Strategic Definition (clients business case and strategic brief are assessed)
1-Preparation and Brief Developing the detail of the brief to ensure that everything needed for the design process is in place.
2-Concept Design Getting the concept right and ensuring it meets the clients requirements.
3-Spacial Coordination spatially coordinate the design before detailed design is prepared.
4- Technical Design Developing the information to manufacture and construct.
5-Manufacturing and Construction Building gets built
6- Handover PC cert, Insurances, release of 2.5% retention, H&S (O&M)
7-Use Building is in full use until its end of life.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What sustainable considerations do you make during the design stage?

A

Depends on the project
Future proof the building? Working to upcoming changes?
Local sourced materials
Waste management plan (no longer compulsory)
uPVC Windows made from recycled plastics etc.
Re-Use materials where possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

What considerations would I advise my client of if they were replacing windows?

A

I would determine determine the property arcitype (flat/house)
Advise that houses non-conservation not require planning
I would assess the locality (conservation, Listed)
Blocks of flats require planning for change of window type.
Conservation/ listed require planning (listed building and conservation) areas act 1990

35
Q

What is MMC? (Modern Methods of Construction)?

A

Off-site construction methods
Control of sustainability, materials and construction
Off-site Volumetric Modules
On-site MMC methods
Off-site Penalised Systems
Off-site Hybrid Systems

36
Q

What do you include in a feasibility study?

A

Includes 6 sections
1- Introduction
2- Background information
3-Requirements
4-Evaluation
5-Conclusions
6-Receommednations

37
Q

Explain what is included in a specification?

A

Preliminaries
Preamble
Specification/Materials and Workmanship clauses
SOW/Sor and Bill of Quants
Drawings/Schedules

38
Q

What is a Preamble?

A

The interpretation / Explanation document
Description of the parties to the contract
Description of Competence
Background
Summary of Negotiations
Tendering Procedure
Objectives

39
Q

What are the Preliminaries ?

A

Description of the project to allow cost assessment and to specify general conditions and requirements for execution
The Site (description, access, parking)
The Works
Contract Conditions (rectification, payments, insurance, collateral warrantees)
Management of the works (working hours etc.)
Security, health and safety
Site set up and welfare

40
Q

Explain Fire Door sets?

A

A door set is a complete unit consisting of a door frame and a door leaf or leaves, supplied with all essential parts from a single source
This means that a fire door set is supplied as a complete unit from one manufacturer, so is;
Fully fitted up and finished, direct from the manufacturer
Fitted with all compatible components and glazing, and
Pre-essembled in the factory

41
Q

Explain conservation areas, what statutory consent do you need?

A

A special consent known as ‘conservation area consent’ is required for the ‘substantial demolition’ of any building in a conservation area, and it is a criminal offence to demolish (or substantially demolish) one without consent.

42
Q

What works require conservation consent?

A

Single storey extensions that extend more than 3 metres beyond the back wall of the house (or 4 metres in the case of a detached house) Extensions at the back of a house with more than one storey. Any extensions at the side of a house.
Window and door & roof replacement (change of material)

43
Q

What is a listed building?

A

A building is listed when it is of special architectural or historic interest considered to be of national importance and therefore worth protecting.
As the term implies, a listed building is actually added to a list: the National Heritage List for England.

44
Q

Explain how you appoint a structural engineer or sub consultant?

A

Internal List of Approved Consultants
Check insurances and previous experience with them
Brief them on requirements
Check terms and conditions and fee
Obtain clients approval and instruct in writing

45
Q

Explain the types of asbestos and the types of survey?

A

CHRYSOTILE (white)
AMOSITE (Brown)
CROCIDOLITE (Blue)
Management Survey - Identify and manage (advised)
Refurbishment and Demolition - for works at risk of disturbance

46
Q

What is licenced and unlicenced asbestos?

A

Most higher risk work with asbestos must only be done by a licensed contractor but any decision on whether particular work is licensable is based on the risk. Licensed work is explained at ‘Licensable work with asbestos’.
Non- Licenced - sporadic, low intensity, control, short duration

47
Q

Explain the advantages of a prescriptive specification.

A

Prescriptive specifications give the client much more certainty about the end product when making investment decisions (such as when they appoint the contractor), and place a greater burden on the designer to ensure proper installation rather than the contractor.

48
Q

What is building control? And when is it relevant?

A

Building control ensures design and regulation standards are met - building regs
Put up a new building.
Extend or alter an existing one.
Provide services and/or fittings in a building such as washing and sanitary facilities, hot water cylinders, foul water and rainwater drainage, replacement windows, and fuel burning appliances of any type.

49
Q

What would you do if a contractor got to site and recommended swapping a product you have specified?

A

BS Standard check
Statutory affects / planning?
Guarantee difference?
client approval?
Issue a CI design change?

50
Q

Name some British Standards you have referred to in your specifications?

A

BS7974- Fire Safety Principles to the design
BS 476- Fire testing requirements
BS 7913: 2013- Conservation and Hisotric Buildings

51
Q

What are the different stages of the design process?

A

0- Strategic Definition (clients business case and strategic brief are assessed)
1- Preparation and Brief (Developing the information that the design team will need to commence the design process) Feasibility Studies
2- Concept Design (The concept design represents the design team’s initial response to the project brief)
3- Spatial Coordination (Design in which the client’s Spatial Requirements and the spaces required for any Building Systems – such as structural and building services engineering aspects, including grids, risers and plant rooms – have been determined and fixed to allow Stage 4 to progress without any further iterations.)’
4- Technical Design (..involves the preparation of all information required to manufacture and construct a building)
5- Manufacturing and Construction (Comprises the manufacturing and construction of the Building Systems in accordance with the Construction Programme agreed in the Building Contract)
6- Handover PC cert, Insurances, release of 2.5% retention, H&S (O&M)
7- Use Building in use

52
Q

Following a client instruction, how might you ensure that their brief if met?

A

I issue a project plan with gateway stages for report and revew
I set deliverable targets within the brief
I match the gateway stages to the targets for delivery
I obtain client sign off and communication throughout

53
Q

How might a building be made more energy efficient?

A

Double glazing,
Insulation upgrade
Better heating system
LED lighting

54
Q

Explain the key difference between Prescriptive and Performance specifications.

A

Performance Specifications address the operational requirements of an installation. The focus is on the project outcome, indicating how the final project must be able to function.
Prescriptive Specifications contain detailed descriptions of what specific materials must be used as well as the installation instructions.

55
Q

Why might you recommend the use of a performance specification?

A

The performance of the works are specified, the contractor reserves the option of design.
Performance specification gives the contractor and suppliers more scope to innovate and adopt cost effective methods of work, potentially offering better value for money.

56
Q

How do you determine the length of contract period for a project - what factors are considered?

A

Lead in period
Statutory consents/ inspctions
Marterial delivery / manufacture
Time for works / number of workers on site.

57
Q

How do you make your client aware of their duties under the CDM Regulations?

A

Initial fee proposal
Initial feasibility report

58
Q

What are the benefits of using specification writing software such as NBS?

A

Collaboration
Consistant Standards
Audit trail of decisionmaking
Up to date standards and products

59
Q

What version of RIBA do you use?

A

RIBA 2020.

60
Q

What were the changes to the 2020 version of RIBA?

A

Introduction of BIM and focus on sustainbility. Stae 1 name change to Preperation and breifing
Stage 3 name change to Spatial co-ordination
Stage 7 name change to Use

61
Q

Hillcrest
What were the asbestos materials and what was the type?

A

The riser cupboards had asbestos insulation board containing amosite.

62
Q

Hillcrest
How did you know what type of asbestos was included?

A

A demolition survey had been undertaken before we were appointed. Determining that it was amosite.

63
Q

Hillcrest
How was the client managin their responisbility toward the asbestos before the projecT?

A

The ACM had been encapsulated and management reports were being completed.

64
Q

Warley Hill Office Conversion and Refurbishment
WHat regulations did you neeed to ensure the office conversion met to be desiganted as an adaptable dwelling?

A

Building regulations part M - Access
Specifically M4 (2) Category 2: Accesible and adaptable dwellings?

65
Q

Warley Hill Office Conversion and Refurbishment
What design considerations did you make to the design of the access ramp?

A

Gradient beetween 1:12 and 1:20 due to arrangement this required a change of direction.
All changes of direction required an intermediate landing with a width 1200mm.
The ramp must maintain a width at all times, with all lengths having a top and bottom.

66
Q

Warley Hill Office Conversion and Refurbishment
What document did you use to determine that the caivty wall insulation would provide an imrpveoemtn in the U-value of the external wall?

A

I referred to building regulations part L to determine the requirement for the imrpovement of thermal performance.

This outlined the requirment for the type of insulation and the width of the cavity.

67
Q

Warley Hill Office Conversion and Refurbishment
What was the U-value requirement of building regulations that you needed to meet?

A

For the cavity size (50mm) the requirement was for U value to be 0.59

68
Q

Warley Hill Office Conversion and Refurbishment
How did you ensure that the office conversion met the appropraite regulations to be designated as an adaptable dwelling?

A

o Access ramp: gradient between 1:12 and 1:20, due to arrangement this meant it required a change of direction. All changes of direction required an intermediate landing with a width of 1200mm. The ramp must maintain 900mm width at all times. All lengths must also have a top and bottom landing.
o Front access doors: Level access threshold, 1200mm width, 850mm clear opening, light outside of door
o Corridors: must be 900mm wide, no radiators opposite door openings and must allow clear manouvering area for wheelchair
o Services: Sockets between 450-1200mm above floor level and CU centre line between 1300-1400mm
o Kitchen: clear 1200mm clear space is provided in front of and between units
o Bedroom: 700mm clear space either side of the double bed

69
Q

Bergen and Brooklyn Feasibility
What experience do you have with developing feasibility drawings and reports?

A

I have recently completed feasibility drawings for the installation of a new gate at residential block in Brent.

The puprose of them was also for s20 purpose, to give the residents options of what to choose depending on their cost.

70
Q

Bergen & Brooklyn Security Works, Tottenham
What were the main objectives of the project?

A

The main objectives was to explore options of installing increased security measures at the property.

I completed the report to allow the client to present the options to the residents for s20 purposes.

71
Q

What experience do you have in developing designs and specifications, including at outline and detail levels?

A

I have recently develop a feasibility for the installation of an entry gate and improved security in Brent. The feasibility allowed me to develop the outline design.

Once the outline design had been agreed I was able to develop a formal specification and issue it out to tender. Including style and manufacturer of the gates.

72
Q

Bergen and Brooklyn Feasibility
What challenges did you face in developing the feasibility report for the client?

A

I needed to understand how to pracitcally intergrate the existing entry system into my proposals. This was outsied of my experience.

I invited a contractor to attend site with me to review the condition of the existing entry system and how it culd be used.

73
Q

Bergen and Brooklyn Feasibility
What design options did you present to the client?

A

I presented 4 different options to the client:
- Manual gate on existing boundary
- Automatic gate on existing boundary
- Automatic gate on moved boundary
- Manual gate on moved boundary

These boundaries gave options for cheaper or more expensive options whilst also giving a range of options for making the most of the space at the car park and the more convienent gate (automatic).

74
Q

Bergen and Brooklyn Feasibility
What techniques did you use to ensure that the feasibility was effective in outlining the process/issues with each design option?

A

To ensure that each of the design options was outlined effectively I inclued a seperate drawings for each, included an indvidual section within the report exlpaining each of the options and the works that were included.

I also included a table comparing the costs and outlining the benefits and draw backs of each.

75
Q

Hillcrest Fire Remedials
What types of floors, walls and roof covering did the flats have?

A

The property had concrete floors, cavity brickwork walls and a slate roof covering.

76
Q

Hillcrest Fire Remedials
What was the value of the JCT IM?

A

£150K

77
Q

Hillcrest Fire Remedials
What did you advise teh cleitn to do regarding teh asbestos and the electrical meters?

A

From reviewing the clients asbestos survey records and attending site to understand the construction, I advised the client that the appointment of specialist asbestos and M&E contractors would be required due to it being outside of my area of expertise.

78
Q

Hillcrest Fire Remedials
What specification did you provide for the electrical components?

A

I included a specification that was developed from an M&E on our approved consultant list. We have technical service agreements set up with all of our agreed subconsultants.

I also made it clear within the spec that the design responsibility lied with the M&E consultant.

79
Q

Hillcrest Fire Remedials
What design and construction did you specify for the compartmentatino of the gas services?

A

I specified a gyproc shaft system that included a a layer of fireline board and intumescent grills of a total of 0.05m2 as outlined in S6891 table 6. I included 2 fire rated mainteance hatches at high and low level.I also required for the concrete slab to be core drilled to allow for through ventilation from the top to the bottom.

80
Q

Hillcrest Fire Remedials
What advice did you give your client regarding the procurement route?

A

I advised the client that due to the nature of the works being high risk, we should maintain as much design control as possible. I therefore recommended that we procure the contract traditionally.

81
Q

HIllcrest Fire Remedials
What did you understand about the design of works requried when you attended site?

A

The FRA identified that the riser door sets needed to be repalced with FD30 units. From attending sites I understood that the asbestos board was fit into the door frame and would need to be removed in order for the door sets to be replaced.

Furthermore, I identified that the electrical meters were fixed directly to the amosite and to allow for the board to be removed there could be a requirement for the meters to also be replaced.

82
Q

Hillcrest Fire Remedials
What did you comunicate with and manage the specialist to produce?

A

I appointed specialist M&E and asbestos subconsltants from our approved subconsultant list.

I communicated the objectives of the project and outlined the works.

With the M&E specialist I advised them that we would need to produce a specifiaction for the replacement of the meters, all replacement services and it should also include provision for deailing with statutory undertakers.

For the asbestos specialist, I explained that we would need a plan of work for removing to determine how the asbestos would be removed safely without contaminating the rest of the property.

83
Q

Hillcrest Fire Remedials
What were the challenges that you faced specifying this project?

A

The main challenge was in realtion to removing the meters and asbestos.

In order to remove/replace the meters power would need to be shut off, the asbestos would then need to be removed in order to install the new meters.

The asbestos management would require a pressurised unit to be set up in the hallway to prevent contaminination, which would prevent escape of the residents.

The only way that the works could be acheived safely was to decant the residents.