Days Flashcards
After written notice, the contractor agrees to make repairs to correct defective work
5 days
From date of referral, C/M Fire Marshall shall submit recommendations to the Buidling Officials
5 days
From receipt of Notice to Proceed, computation of contract time
7 days
Before date needed, contractor to make request on drawings and materials
10 days before needed
Request for owner - furnished materials
10 days
Before beginning, suspending or resuming work, contractor to issue written notice
10 days
Before written notice, contractor’s insurance policy will not be cancelled
10 days
Before commencing excavation, notify the owner of adjoining property
10 days
Correction before final payment
10 days
From date of change order, assertion of claims
15 days
After receipt of any instructions, contractor to inform architect of the extra cost for extra work through written notice
15 days
After recognition of delay, contractor to issue a written notice
15 days
From NTP, contractor to submit complete breakdown of work and corresponding value
15 days
From request of payment, architect to issue or withhold certificate of payment
15 days
From approval of request of payment & issuance of payment, owner to pay certified amount
15 days
From date of bidding, contractor to seek architect’s clarification
15 days
After request for payment, architect/owner fails to act, contractor may suspend or terminate work
15 days
Upon certification of the Architect justifying Owner’s action, Owner to terminate contract:
- Contractor declares bankruptcy
- Disregard/violate provisions of contract documents/schedule
- Fail to provide qualified people & materials
- Fail to make payment to sub-contractors, workmen, or dealers
15 days
From payment of required fees, issuance of building permit
15 days
From receipt of advice of the non-issuance, suspension or revocation of permits, file an appeal to the secretary
15 days
After award of arbitration, owner fails to pay contractor, contractor may suspend/terminate work
30 days
Certificate of Occupancy
30 days
To make good of known defects after issuance of certificate of completion
60 days
Suspension of work through no act of contractor and employees or order of court
90 days
Excavation shall not be left open without work being done.
120 days
Suspension of construction exceeds ____ the fee for the remaining works shall be doubled.
180 days
Contractor’s guarantee bond effectivity
365 days
Building permit validity if there was no construction
365 days
Changes, alterations, & repairs may be provided that in any 12 month period, the value of the work does not exceed 20% of the value of the existing building, and provided that, such changes do not add additional combustible material, and do not, in the opinion of the Building Official, increase the fire hazard.
365 days