Days Flashcards
After written notice, the contractor agrees to make repairs to correct defective work
5 days
From date of referral, C/M Fire Marshall shall submit recommendations to the Buidling Officials
5 days
From receipt of Notice to Proceed, computation of contract time
7 days
Before date needed, contractor to make request on drawings and materials
10 days before needed
Request for owner - furnished materials
10 days
Before beginning, suspending or resuming work, contractor to issue written notice
10 days
Before written notice, contractor’s insurance policy will not be cancelled
10 days
Before commencing excavation, notify the owner of adjoining property
10 days
Correction before final payment
10 days
From date of change order, assertion of claims
15 days
After receipt of any instructions, contractor to inform architect of the extra cost for extra work through written notice
15 days
After recognition of delay, contractor to issue a written notice
15 days
From NTP, contractor to submit complete breakdown of work and corresponding value
15 days
From request of payment, architect to issue or withhold certificate of payment
15 days
From approval of request of payment & issuance of payment, owner to pay certified amount
15 days