Days Flashcards

1
Q

After written notice, the contractor agrees to make repairs to correct defective work

A

5 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

From date of referral, C/M Fire Marshall shall submit recommendations to the Buidling Officials

A

5 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

From receipt of Notice to Proceed, computation of contract time

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Before date needed, contractor to make request on drawings and materials

A

10 days before needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Request for owner - furnished materials

A

10 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Before beginning, suspending or resuming work, contractor to issue written notice

A

10 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Before written notice, contractor’s insurance policy will not be cancelled

A

10 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Before commencing excavation, notify the owner of adjoining property

A

10 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Correction before final payment

A

10 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

From date of change order, assertion of claims

A

15 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

After receipt of any instructions, contractor to inform architect of the extra cost for extra work through written notice

A

15 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

After recognition of delay, contractor to issue a written notice

A

15 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

From NTP, contractor to submit complete breakdown of work and corresponding value

A

15 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

From request of payment, architect to issue or withhold certificate of payment

A

15 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

From approval of request of payment & issuance of payment, owner to pay certified amount

A

15 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

From date of bidding, contractor to seek architect’s clarification

A

15 days

17
Q

After request for payment, architect/owner fails to act, contractor may suspend or terminate work

A

15 days

18
Q

Upon certification of the Architect justifying Owner’s action, Owner to terminate contract:

  • Contractor declares bankruptcy
  • Disregard/violate provisions of contract documents/schedule
  • Fail to provide qualified people & materials
  • Fail to make payment to sub-contractors, workmen, or dealers
A

15 days

19
Q

From payment of required fees, issuance of building permit

A

15 days

20
Q

From receipt of advice of the non-issuance, suspension or revocation of permits, file an appeal to the secretary

A

15 days

21
Q

After award of arbitration, owner fails to pay contractor, contractor may suspend/terminate work

A

30 days

22
Q

Certificate of Occupancy

A

30 days

23
Q

To make good of known defects after issuance of certificate of completion

A

60 days

24
Q

Suspension of work through no act of contractor and employees or order of court

A

90 days

25
Q

Excavation shall not be left open without work being done.

A

120 days

26
Q

Suspension of construction exceeds ____ the fee for the remaining works shall be doubled.

A

180 days

27
Q

Contractor’s guarantee bond effectivity

A

365 days

28
Q

Building permit validity if there was no construction

A

365 days

29
Q

Changes, alterations, & repairs may be provided that in any 12 month period, the value of the work does not exceed 20% of the value of the existing building, and provided that, such changes do not add additional combustible material, and do not, in the opinion of the Building Official, increase the fire hazard.

A

365 days