1
Q

Which of the following is NOT an input to the Manage Quality process?

A

Quality Audits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What document outlines quality standards, policies, and objectives for a project?

A

Quality Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which input to Manage Quality specifies criteria for measuring project performance against quality requirements?

A

Quality Metrics

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which input contains historical project data that can be used to improve quality processes?

A

Organizational Process Assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which factor influences quality management but is outside the control of the project team?

A

Enterprise Environmental Factors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

If a product does not meet specifications and needs fixing within the project scope, what should be done?

A

Rework

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A stakeholder requests an additional feature not in the original scope. What is the correct action?

A

Submit a Change Request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which document formally proposes modifications to project scope, cost, or schedule?

A

Change Request Form

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who is responsible for reviewing and approving project change requests?

A

Change Control Board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What process ensures changes are formally evaluated before being implemented?

A

Integrated Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A stakeholder is completely unaware of a project’s existence. How should they be classified?

A

Unaware

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A stakeholder who is neither for nor against a project is classified as?

A

Neutral

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What type of stakeholder is actively engaged in supporting project success?

A

Leading

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A stakeholder who initially resists a project but later becomes engaged is classified as?

A

Resistant to Supportive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What stakeholder classification is most likely to cause unexpected project roadblocks?

A

Resistant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which is a best practice for recurring project meetings?

A

Schedule them as early as possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What should be distributed before a project meeting to improve effectiveness?

A

Meeting Agenda

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is the most effective way to document key meeting discussions?

A

Meeting Minutes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Why should meetings have a set time limit?

A

To prevent wasted time and maintain focus

20
Q

What is the primary reason for allowing stakeholders to contribute to the meeting agenda?

A

To ensure key concerns are addressed

21
Q

Which skill involves motivating teams and managing relationships?

A

Power Skills

22
Q

Which skill focuses on task execution, planning, and scheduling?

A

Management Skills

23
Q

What power skill involves leading teams without direct authority?

A

Influencing without Authority

24
Q

What is the primary focus of management skills?

A

Executing project tasks and ensuring compliance

25
Which skill is most useful for resolving team conflicts?
Power Skills
26
Which input to Manage Quality outlines how processes will be optimized?
Process Improvement Plan
27
A stakeholder learns about a project late and expresses frustration. What is their likely classification?
Unaware
28
A meeting without an agenda is likely to suffer from what issue?
Lack of direction and efficiency
29
Which skill is emphasized as critical in modern project management?
Power Skills
30
What is a key difference between Manage Quality and Control Quality?
Manage Quality is proactive, Control Quality is reactive
31
A software company discovers a defect in its final testing phase. What action should the team take if the defect falls within the original project scope?
Rework
32
A company’s quality audits reveal inefficiencies in its processes. Under which process would these be addressed?
Manage Quality
33
A project manager ensures all team members are aligned with the project’s quality expectations. Which process is he performing?
Manage Quality
34
Which document provides guidelines for process optimization in a project?
Process Improvement Plan
35
Which quality input helps determine if quality processes are being followed correctly?
Quality Metrics
36
Which stakeholder classification would require targeted communication to increase project engagement?
Unaware or Resistant
37
What is a key purpose of a change control process?
To formally evaluate and approve project modifications
38
A project manager wants to ensure that all quality assurance activities align with project requirements. What should they reference?
Quality Management Plan
39
What stakeholder classification represents someone actively working against the project?
Resistant
40
What document should be referenced before implementing a change request?
Change Management Plan
41
Which input to Manage Quality is used to determine if quality processes are executed as planned?
Quality Control Measurements
42
A project faces delays due to inefficient team communication. Which skill should the project manager improve?
Power Skills
43
Which meeting best practice ensures stakeholders are well-prepared?
Distributing an agenda beforehand
44
A stakeholder is unaware of a project and later becomes opposed to it. What classification applies?
Unaware to Resistant
45
An organization wants to proactively improve processes to enhance project outcomes. Which process should they focus on?
Manage Quality