Chapter 3.1 Flashcards

1
Q

define project life cycle

A

stages that a project goes through from its initiation to its closure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

define product life cycle

A

the entirety of the products life, from initiation to retirement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

define pre-work activity

A

-tasks and processes undertaken before a project is formally initiated
-ensure project is well-planned, feasible, and aligned with organizations goals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

acronym SOW

A

statement of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

name 3 pre-work ativities

A

SOW, feasibility study, and business case

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

define a business case

A

-provides detailed analysis of costs, benefits, and risks with project
-justify project to stakeholders by demonstrating ROI and impact on org

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

define feasibility study

A

-evaluation of whether project is technicially, financially, and economically feasible
-assesses potential risks and benefits, determines whether project is work pursuing based on resources, market conditions, and other factors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Define SOW

A

-outlines scope and objectives of project, as well as work that will be performed to achieve them
-what needs to be done, who will do it, how it will be done, and when

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what do project phases do?

A

-see the project as a whole and still focus on completing the project one phase at a time
-allow pm/org to have better control over work done in each phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what is determined before each phase of a project?

A

-work that will happen in phase
-deliverables from that phase
-how deliverables will be reviewed, approved, and validated
-needed resources for that phase
-how phase will be approved to allow successor phase to launch

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

common flow of a construction project in relation to phases?

A

research, preconstruction, site work, foundation, framing, rough-in, interior finishes, exterior finishes, landscaping

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

define a phase-end review

A

determines whether the phase deliverable has met all its obligations and, if it has, authorizes next phase
-phase exit/phase gate, or go/no-go point

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

define fast-tracking

A

overlapping phases

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

how can fast-tracking put a project at risk?

A

insufficient planning, overlapping tasks, and increased resource constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

when is a projects success most at risk of not being successful?

A

early phases of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

define process

A

set of actions and activities to achieve a product, result, or service

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

a successful project depends on what 5 things? (pertaining to processess)

A

-using appropriate processes at appropriate times
-following defined pm approach for execution and control
-developing solid pm plan for all areas of project
-comforming project to customer requirements and expectations
-balancing project scope, schedule, cost, quality, resources, and risks while meeting project objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

define the “plan-do-check-act” method

A

the end of one process launches another.
-ie, end of the planning process enables the launch of the doing process.
-once completed, you check it, and if its good, you move right into the acting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

acronym PDCA

A

plan-do-check-act

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

what is a project portfolio?

A

-defines the rules for selecting, maintaining, and even funding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

define project portfolio management

A

-defines the projects that should be selected based on need, risk and reward, ROI, and any other issues an organization identifies
-focuses on initiation of best programs and projects org should invest in
-not overly concerned with how program and project should be managed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

who is generally directly involved with portfolio management?

A

senior management, usually not PM
-senior mgmt is focused on what best works for organizations mission/goals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

what do portfolio managers do?

A

-manage portfolio management processes (selecting projects, distributing risk exposure, and ensuring strategic alignment with org

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

what is project portfolio management?

A

-selection, management, and collection of projects within org
-unlike program, project in portfolio may not be directly related, but contribute to org success
-ie construction company portfolio of high-profile projects that could change a cities skyline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
what is a program?
-collection of related projects organized to gain benefits from the projects that wouldn't be realized if projects were managed independently -not a large project, just collection of projects -ie a skyscraper program: structure, elevators, electrical, plumbing, etc.
26
main takeaway for a program?
projects are usually contributing one major delierable and can work together to save time, effort, and dollars -program managers manage programs, and pm work within them on seperate projects
27
what is progressive elaboration when it comes to project planning?
start with a very broad concept, then, throughs steady progressions, gather more detail to clarify the concept of the project.
28
define organizations that “management by projects”
org that operates by relying heavlily on project management principles to complete work. -generally treat every undertaking as a project
29
name some reasons a project will be put into action
-opportunity (market demand, etc) -organizational needs -customers -technology -legal requirements
30
what are ways that projects can create value?
-improved efficiency -enhanced customer experience -increased revenue -competitive advantage -improved employee satisfaction -better quality -better decision making
31
what is a sub-project?
smaller project thats been lopped off from a larger project -ie when building a new house, adding a home theater
32
what are some examples of subprojects?
-single phase within a project life cycle (ie construction of house, each phase could be a subproject) -human resource skill sets (plumbers, electricians, carpenters, on a new house) -specialized tech, materials, or activities (new type of siding for home construction)
33
difference between projects and operations?
projects are temporary, operations are ongoing
34
when will a pm most likely work directly with operations?
at the end of a project, when transfering deliverables
35
what is operational transfer?
transfering the deliverables of the project ownership into operations
36
acronym SLA
Service-Level Agreement
37
what is a development approach?
means used to create and evolve a product, servie, or result during the project life cycle
38
what is a predictive approach?
predicts the work that will happen in each phase of the project -also called plan driven or traditional approach -changes to scope are less common/more controlled
39
what is an adaptive approach?
-great deal of uncertainty -little planning can be done up front -ie highly complex IT projects
40
what is an iterative approach?
-starts with a vision of project scope, BUT schedule/costs are rough estimates -work is divided into chunks of time (Iterations) -allow to work on top requirements first and also apply lessons learned on future iterations -have predefined types of work, such as features defined, designed, developed, and tested -iterations also called timeboxed periods or sprints
41
what is an incremental approach?
-similar to iterative, BUT deliverables are created in increments -features are added incrementally until project is complete -like an assembly line process: feature added in predefined increments from start to finish
42
what is a hybrid approach?
combination of predictive and adaptive -components that are established will follow predictive approach -components that are not fully defined follow adaptive
43
basic difference between all of the approaches? (Predictive, etc)
-predictive predicts as much as possible, uses baselines to minimize changes -iterative repeats same steps for each iteration, building outcome in chunks -incremental builds in increments, adding functionality until complete -adaptive uses iterative and incremental -hybrid is combination of predictive and addaptive
44
what are some factors that can impact success of a project?
issues, risks, assumptions, and constraints
45
what are "issues"?
unexpected events that you document and manage to prevent them from causing risks -events that have happened, that reoccur, or that are going to happen
46
what goes on a project issue log?
-date identified -person identifying issue -details about the issue -summary of the issue -prioritization -issue owner -target resolution date -current status -final outcome
47
what are some common "issues"?
-difference of opinion -situations to be investigated -unanticipated responsibilities that need to be assigned
48
what is a risk?
uncertain event or condition that could have POSITIVE or NEGATIVE impact -negative risks are threats -positive risks are opportunities -ie leftover shrimp cocktail
49
what is the willingness to accept risk called?
utility function
50
term for the amount of risk youll take on if you go ahead?
risk tolerance
51
term for how much risk youll accept in relation to the reward the risk may bring?
risk appetite
52
where can risks exist?
organizatoin, program, portfolio, and a project...everywhere
53
term for risks you can readily identify
known risks
54
term for risks that are more ambiguous (weather)
known unknowns
55
define project risk
likelihood of the overall project being successful for the organization
56
the project manager will need what documents to identify project risks?
-assumption log -cost estimates -duration estimates -issue log -lessons learned register -resource requirements -resource documents -stakeholder register
57
what is one of the first steps taken in risk identification in a project?
-review project documentation (project plan, scope, and other project files)
58
what is an "assumption"?
-something you believe to be true but isnt proven -can include expected performance from a vender, reliability of equipment, access to resources, weather, and more
59
what is assumption analysis?
-examining assumptions to see what risks may stem from false assumptions
60
what do you do when an assumption is identified
document it in the assumption log
61
what are constraints?
-factors that limit the options of the pm -can quickly endanger project success -ie schedule, budget, resources, risks, etc -mgmts responsibility to analyze impacts that changes will have according to constraints
62
what are communication constraints?
-anytning that limits project manager teams options when it comes to communication -geographical, incompatible software, etc.
63
what type of projects use the triple constraints of project management?
predictive
64
what type of projects use the inverted triangle to represent constraints?
agile
65
which type of projects do not necessarily use milestones?
agile, as they are often changing/unknown -use roadmaps, attempt to lay out release points like milestones
66
describe the triple constraints triangle (clockwise), and the agile triangle of constraints (inverted)
-scope, cost, time, on the triple, where scope is fixed and cost varies -cost, scope, time on agile, where time is fixed and scope varies
67
one of the major tasks of project management dealing with this area?
balancing of competing constraints on a project
68
what is scope creep?
-doing what should never have entered the scope in the first place -means wasted time and dollars
69
what is a predictive-plan based approach?
predicts what will be created and how
70
what is an adaptive approch?
expects change to happen
71
how is the scope handled in an adaptive approach project?
-defined and decomposed in the product backlog -in each iteration, team will collect requirements, define scope, and create the WBS for that iteration
72
what are user stories?
quick descriptions of the requirement from the user perspective
73
what are story points?
represent how much effort is required to create the user story -only so many points available for each iteration (also called sprints in agile projects) -number of available points vary by project
74
what are epics?
describe really big requirements broken down into stories and span multiple iterations of the project
75
what 2 processes happen in each iteration of a project?
-validate scope -control scope
76
acronym RTM?
Requirements traceability matrix
77
what is the RTM?
-documents and numbers each requirement and status, shows how each requirement is linked to specific deliverable -tool for controlling project scope -ensures all project requirements are addressed and fulfilled -provides clear way to track relationship between requiremetns and deliverables, tasks, or test cases
78
what are some benefits to tracing requirements in project scope?
-improved project planning -enhanced communication -better risk management -increased project visibility -improved quality assurance -better stakeholder engagement`
79
4 key foundational values for any pm?
-responsibility, respect, fairness, honesty