Contract Practice Level 1 Flashcards
How do variation requests work?
A variation is an agreement supported by consideration to alter terms of a contract. There must be express terms within contracts to instruct variations.
Standard forms of contract generally contain express terms for the contract administrator to instruct variations. Written notice of the variation must be given to the contractor and they must comment upon the impact of the variation in relation to cost and programme.
What are the JCT Suite of Contract options?
- Standard Building Contract
- Intermediate Building Contract
- Minor Works Building Contract
- Major Project Construction Contract
- Design and Build Contract
- Management Building Contract
- Construction Management Contract
- Constructing Excellence Contract
- Measured Term Contract
- Prime Cost Building Contract
- Repair and Maintenance Contract
- Homeowner Contract
- Tracked Change Contract
What are the NEC alternatives to JCT Suites?
A - Priced Contract with Activity Schedule
B - Priced Contract with BOQ
C - Target Contract with Activity Schedule
D - Target Contract with BOQ
E - Cost Reimbursable Contract
F - Management Contract
How do JCT and NEC suites differ?
NEC attempts to eliminate legal terms & is said to be written in plain english & explains terms in their natural meaning
NEC operates ‘early warnings’ where both the PM and contractor are responsible for highlighting any event which can impact time, cost or quality
JCT deals with time and cost separately, whereas NEC deals with the effects of time and cost together
JCT uses variations - NEC uses compensation events
JCT uses a contract administrator - NEC uses the project manager
NEC does not contain provisional sums
How does standardisation provide benefit for a project?
In terms of contract practice, standardisation provides benefit by offering clarity and consistency. For example:
1. Standardised contracts provide a common framework and language for all parties involved, reducing ambiguity and encouraging a clear understanding of roles, responsibilities and obligations.
2. They have predefined provisions for managing risks like defects, delays and changes to scope, helping to ensure the method by which these are dealt with is already set out by the contract.
3. Consistency across project and the uniformity this brings helps contractors, clients and consultants apply lessons learned from one project to another.
What typical contractual amendments have you encountered?
Do you agree with the typical contractual amendments you have encountered?
What would you do if you were asked to provide advice on contractual amendments you have encountered?
What are the parties’ responsibilities and duties under a contract?
Client / Employer:
1. Define project requirements
2. Provide funding
3. Appoint the Design & Construction Team
4. Make timely decisions
5. Contractual obligations
6. H&S Compliance
Contractor:
1. Complete the work as per the contract
2. Resource management
3. Adhere to the programme
4. H&S compliance
5. Quality control
6. Reporting & communication
7. Rectify defects
What is the significance of the Local Democracy, Economic Development and Construction Act 2009?
It caused changes to the operation of construction contracts which had a knock on to the Housing Grants, Construction & Regeneration Act 1996
What changes did the Local Democracy, Economic Development and Construction Act 2009 bring to the construction industry?
- Section 109 - a party’s entitlement to stage / periodic payments & instalments
- Section 110 - ensures every contract provides adequate mechanisms for payment due dates
- Section 111 - means payment cannot be held without notice
- Makes both written and oral contracts subject to the act
How is the Local Democracy, Economic Development and Construction Act 2009 recognised in standard forms of construction contracts?
Primarily through its amendments to the Housing Grants, Construction & Regeneration Act 1996. It influences standard forms of contract by reinforcing adjudication rights, streamlining payment processes and providing mechanisms for dealing with non-payment.
What are the essential components of a valid contract?
- Offer - by a party to provide goods or services.
- Acceptance - by a party to procure such goods or services
- ‘Consideration’ - the promise made by both sides to do something e.g. providing the works in return for money
- Intent - the intention of the parties to create binding legal relations
By way of examples, can you tell me how the essential components of a valid contract find their way into a JCT construction contract?
What is the principal difference between a parent company guarantee and a performance bond?
The principal difference is that a bond is a financial commitment backed by a third party if the contractor does not fulfil the works.
Whereas a PCG is where the parent company will step in to remedy the works should the contractor not perform.
Can you name 2 types of performance bond?
- On-demand bonds - money set out in the bond is immediately available on demand without needing to satisfy any pre-conditions whatsoever (including establishing the contractor’s liability)
- Conditional / on-default bonds - requires the employer to provide evidence that the contractor has not performed their obligations under the contract and that they have suffered a loss consequently.
What current challenges is Covid and/or Brexit bringing to Contract Practce?
- Sanctions and export controls
- Cost increases
- Delays
How does contractors design portion under JCT SBC work?
The CPD is utilised when any element having a design is required of which the architect does not wish to design.
Under SBC for example, the architect prepares a performance specification in the form of ER’s to which the contractor responds with its CP’s.
Both documents become part of the contract documents, together with a breakdown of the part of the Contract Sum related to the CPD work, known as the CPD analysis.
What is A, B & C in relation to contractors design?
Schedule 1 of JCT SBC & D&B includes provision for submission of design drawings by the contractor. The architect or employer under D&B must return one copy of each drawing marked A, B or C.
A - the contractor may proceed
B - may be used provided the contractor strictly adheres to the comments
C - must be resubmitted after the comments are taken into account.
This cannot be used as an opportunity for the architect or employer to amend the design. B and C drawings can only be marked as such if they do not comply with the ER’s.
What works are typically included within the JCT SBC CDP?
Typically more complex and specialised elements of design, such as structural works, temporary works or MEP elements.
What are recent changes to the JCT Contracts?
JCT have released a 2024 version of their contracts including SBC, C&PCSA, R&P, PC, MPC, D&B and MT Contracts.
The updated includes for collaborative working, sustainability & environmental impacts, notification & negotiation of disputes, making previously supplemental provisions now mandatory.
The updates also include for the adoption of more inclusive language and increased flexibility surrounding digital communications.
The updates also include for legislative changes with reference to the new Part 2A of the Building Regulations 2010, The Construction Act 1996 and Corporate Insolvency and Governance Act 2020.
The 2024 version also encompasses a Target Cost Suite.
The 2016 version is still available to purchase.
Can you tell me more about the legislative changes to JCT 2024?
- Part 2 A of the Building Regulations 2010 - naming the key dutyholders
- Construction Act 1996 - termination accounting & payment provisions added to Section 8
- Corporate Insolvency & Governance Act 2020 - new insolvency grounds have been added to Section 8
What is a collateral warranty?
A form of contractual agreement which runs alongside another contractual agreement - it’s purpose is to create a contractual relationship between 2 parties where one would otherwise not exist.
A working example would be -
An employer has a contract with a contractor. The contractor then has several subcontractors with it’s suppliers to do the works. So, the employer has a direct contractual relationship with the contractor, but no contractual relationship with any of the subcontractors.
Therefore, in this scenario, a collateral warranty can be utilised to either enforce obligation that the subcontract owes directly or to create other obligations and rights between them.
This may be considered a security measure if the contractor should become insolvent or if its employment would be terminated for any reason.
What is the difference between a bond and a collateral warranty?
A bond is a financial commitment backed by a 3rd party, whereas a collateral warranty passes on contractual obligations.
Bonds are contained within the contract, whereas collateral warranties are a side agreement to the contract.