Case Study Level 3 Flashcards
How did you present your advice to the client in respect of the procurement strategy for the closure stores?
Initially I presented a written outline via email to ensure my advise was formally recorded. I then set up a meeting with the client to expand upon my written outline in the form of a presentation, which encompassed:
- summary the scope of the project in functional terms
- recap of the client’s and project objectives
- details of the strategy
- how the strategy would assist in achieving the client’s and project objectives
- SWOT analysis
- timelines
- lines of responsibility
Under what form of contract were the contractors contracted / appointed?
3 of the 5 contractors were client approved contractors, already part of a JCT SBC Framework Contract. So, they were contracted via the call-off mechanism under the framework.
The other 2 were approved vendors, as they had carried out work under a different remit for the client already. However, they were not signed up to the framework.
The Client’s In-House Procurement Team decided to issue the contractors with a Standard PO based on the total of their tender values for each store, prior to starting on site. The PO is accompanied by the client’s T&C’s.
Why were PO’s used and not contracts for each batch?
The client approved contractors were instructed under a ‘call off’ mechanism under their Framework Contract with the client.
However, the new contractors were not part of this contract and the Client’s In-House Procurement Team decided to issue the contractors with a Standard PO per store based on the agreed tender, prior to starting on site. The PO is accompanied by the client’s T&C’s.
As the programme was over an extended period, how did you deal with inflation in the contractor prices and overall budget?
Obviously the tender was fixed price. But the contractors were aware of the duration of the programme from the outset, so they were able to price for their within their tender.
On Key Issue 1, through your chosen option, did one contractor win more than others and how did you manage the allocation?
So, the allocation was split fairly evenly between 4 of the 5 contractors, with them having between 20-29% of the stores each.
However, Contractor 10 had much less of the stores at circa 3% of the programme. This is because they were awarded the Northern Ireland Region, which had less stores closing than any other region. In addition, they were a regional contractor as oppose to national.
How did the agreed/approved budget compare with the current/final projections?
The projected concluded at 47% under the approved budget.
Why does the client use a JCT SBC contract for their framework?
The client prefers to use one form of JCT contract for all of its works in existing stores. The Standard Building Contract was deemed sufficient by the client’s and their legal team for covering all types of works, ranging from minor works to re-fits.
You mention the call-off mechanism under the Framework. Can you tell me a bit more about that?
The Call-Off Instruction relates to contract information that varies from project to project, for example the works, site address, the contractor and other roles, the contract sum, possession, completion and IVD dates, insurance, LDs and Sections.
What was your role in relation to payment?
As the QS on the project, my role was to validate the contractor’s valuation applications for payment.
In the event the contractor did not submit their application by the IVD, I was required to undertake the interim valuation at the request of the contract administrator.
What were the key dates within the contract relating to payment?
The contract stipulated the 24th of each month as the IVD, which was the contractors deadline to submit their IV application for works up until the due date, which is 7 days past the IVD.
You mention design development risk being born by the contractor as a strength. Do you think that’s a fair allocation of risk?
With any risk, it should be allocated to the party most capable of managing it and dealing with it.
This risk related to the fluctuation in scope with reference the general store-to-store environments, i.e. one store may have a dis-used storage area with a significant amount of waste to remove, whereas another store may be well-kept. So by the same token, it was a win-some loose-some approach, which prevented administrative time and costs in dealing with these works on a store by store basis.
Of course, any substantial changes in scope which would be deemed as a variation were dealt with us such.
Therefore, I did deem this a fair allocation.
In relation to the core objectives, what was the waiting of each objective?
In relation to the core objectives -
As the time objective was a legal / contractual obligation under the agreement between the client and the landlord, this objective was first priority.
Following on from that, was the cost objective. As mentioned this was not a profit-making project for the client, so keeping expenditure to a minimum was important.
The quality objective came hand in hand with both the cost and time objective. As, scope needed to be kept to a minimum in light of the cost objective, but it also needed to meet the requirements set out by the lease agreement.
The confidentially objective was intertwined with the other objectives, and needed to be considered throughout.
How were defects dealt with under the JCT SBC Framework, especially as these are closure stores?
Contractually, the rectification period is 12 months, triggered by Practical Completion. But in reality, following Practical Completion, the client would then hand the unit back to the Landlord and upon the Landlords acceptance of the unit, the client was no longer in possession. Therefore, following Landlord acceptance and agreement of the final account, the Final Certificate was issued, which marked the end of the rectification period.
What did the JCT SBC Framework say about Final Accounts?
The contract states the FA must be submitted no later than 6 months after PC. Although this what was contractually required, because of the fast-paced, low value, high volume of works, the rules of engagement with contractors was for them to submit their FA’s for works completed that month in line with the IVD date.
Fortunately, this was adhered to by contractors. But if it wasn’t, the CA could instruct me to ascertain the FA value based on my own information.
What did the JCT SBC say about latent defects?
The contract did not specify limitation periods for latent defects, but the statutory limitation period outlined in the Limitation Act 1980 applies.
As the construction contract is executed as a deed, the limitation period is 12 years from the date of breach.