Chapter 17: Commissioning Flashcards
As-built Drawings
Drawing of the facility “as it was built.” Normally, they document any revisions made during construction as a result of change orders, re-locations, re-routing, etc.
BOD
Documentation by the design team of the primary thought processes and assumptions behind design decisions that are made to meet the Owner’s Project Requirements. The BOD describes the assumptions used for sizing and selection of systems (i.e. codes, standards, operating conditions, design conditions, weather data, interior environmental criteria, other pertinent design assumptions, etc.).
Cx
Commissioning
CxA
Commissioning Authority or Agent
Commissioning Plan
The document prepared for each project describes all aspects of the commissioning process, including schedules, responsibilities, documentation requirements, and functional performance test requirements.
Commissioning Issues Log
A formal and ongoing record of problems or concerns , as well as associated priorities, implications, and resolutions.
O&M
Operations & Maintenance
What is commissioning?
Commissioning is the process of ensuring systems are designed, installed, functionally tested, and capable of being operated and maintained according to the owner’s design intent and operational needs.
What is the goal of retro commissioning or recommissioning?
To ensure system operations and performance are in alignment with the operation’s current use or needs.
Who is the commissioning agent?
This is the person or persons with the knowledge, skills, and experience to plan, perform and execute a commissioning plan in one or more of the systems susceptible to commissioning in a building.
What is a continuous commissioning?
A systematic commissioning process that continues throughout the project’s lifecycle.
What are the phases of the commissioning process?
- Pre-design (program) Phase
- Design Phase
- Construction & Acceptance Phase
- Occupancy & Operations Phase
What commissioning phase determines the scope of work for the project?
Pre-design (Program) Phase
What types of documents are completed in the design phase?
- Contract documents
- Specification documents
- System documents
During which commissioning phase are maintenance plans developed?
Occupancy & Operations Phase