Chapter 08: Architectural Flashcards

1
Q

What areas of a data center are most vulnerable to water ingress?

A

Anything on or below the first floor of the building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the minimum clear access height, from finished floor to any ceiling obstructions, required for a building section in a data center?

A

3 m (10’)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What should be the minimum slab to structure height for a data center building?

A

4.5 m (15’)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the advantages of constructing a data center in the grade kevel (ground floor) of a building?

A

Equipment access and floor loading considerations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the disadvantages of constructing a data center on the upper floors of a building?

A
  • Equipment access
  • Floor loading considerations
  • Structural instability in areas with major lateral force issues (hurricane, wind seismic)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What equipment shall be in the command center?

A

A command center shall house environment monitoring equipment and computer systems monitors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the size and weight of the equipment for which the computer/ telecommunications equipment delivery pathway, including doors, shall be designed?

A

Delivery pathways shall be designed for equipment as large as 3 m (10’) long by 1.2 m (4’) deep by 2.4 m (8’) high, weighing greater than 3400 kg (7500 lbs)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the typical time frame for a data center to significantly change its ITE inventory?

A

3 to 5 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the maximum opening size for a glazed opening in a computer room door

A

Glazing within doors shall not exceed 0.065m^2 (100”^2).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What shall be the minimum thickness for data center doors?

A

45 mm (1.75 in)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the minimum access floor height required above the slab?

A

450 mm (18”)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the minimum clearance that shall be maintained from the sprinklers to raceways, cabinets, and racks to ensure they do not disrupt the sprinkler distribution pattern subject to the AHJ?

A

450 mm (18”)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What should the minimum access floor height above the slab for computer rooms with higher power density equipment where the underfloor space is used for cooling?

A

900 mm (36”)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the minimum recommended ceiling height for computer room spaces (from slab-to-slab)?

A

4.5 m (15’ or greater)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the minimum ceiling height from the finished floor to any obstruction in data center computer rooms and telecommunication spaces?

A

3 m (10’)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What should be used with floor slabs to act as a moisture barrier and to prevent dusting and particulating?

A

A non-penetrating seal such as an epoxy.

17
Q

What building types are defined by the International Building Code are suitable for housing a critical data center?

A

Type I, II, or III

18
Q

In what situations may the local access providers require access to the computer room?

A
  • The entrance room is a portion of the computer room.
  • The computer room houses access provider equipment such as DWDMs, SONET multiplexers, or any circuit provisioning equipment.
  • The carrier demarcation points (e.g., DS-1 or DS-3 DSX panels) reside in the computer room.
19
Q

If a data center is located in a multi-tenant building, how can you ensure the safety and reliability of data center operations?

A

The data center shall be located away from the hazards and mutual access points with other tenants.

20
Q

If batteries are in a dedicated battery room, where should the battery room be located?

A

Adjacent to the closest electrical room.

21
Q

What is the minimum fire rated required for media storage?

A

A 2-hour rating

22
Q

What is the maximum slope for ramps from horizontal for movement of cabinets with equipment?

A

8 degrees

23
Q

What should be the minimum width of a ramp used for equipment access in a data center?

A

900 mm (36”)

24
Q

What facilities are required to be located near the electrical and UPS room?

A

The main building electrical room and the generator.

25
Q

The proposed building architecture must take into consideration space for a variety of support equipment. List three.

A
  • Generator(s)
  • Fuel tank(s)
  • HVAC heat rejection systems
26
Q

What are some additional security requirements for data centers that house ITE from multiple users?

A

Additional physical security such as walls or cages at the partition levels or electronic controls.

27
Q

What is a “lights-out” philosphy?

A

A light-out approach is to have no personnel working within the data center on a normal basis.

28
Q

How may a “lights-out” approach impact a data center’s design?

A

A “lights-out” data center will require sophisticated and secure remote monitoring and control capability. The design will also have to address the operational challenges such as coordinating the delivery of supplies and ITE to a facility that has no personnel on-site on a regular basis.

29
Q

It is required that a 24/7 operational data center shall have __________ facilities with in the data center.

A

Break