Chapter 03: Project Implementation Flashcards
True or False: The general contractors and subcontractors are responsible for preparing and submitting their own bids.
True
Which procurement document is used to solicit prices from prospective providers or products of service?
Request for Quotation (RFQ)
DBB is a delivery method where the owner contracts with separate design and construction firms for a project. What are the three phases of this method?
Design, Bid, Build
What is the difference between DB and DBB delivery methods
A DB is a single method where the owner contracts a single entity with the design professionals working directly with the contractor. In the DBB method, the design professionals work directly for the owner.
Name the delivery method where a CM contracts to deliver a project with a Guaranteed Maximum Price (GMP).
Construction Manager at Risk (CMAR)
This approach combines all aspects of the design and construction process into one team effort, including design professionals, CMs, and contractors.
Integrated Project Delivery (IPD)
What two methods are used to award bids?
- Low Bid
- Negotiated Bid
True or False: Once an NTP has been used, the PM will begin the processes to organize and track the project.
True
True or False: The key members of the construction team are typically the CM, CMAR, GC, contractors, and subcontractors.
True
What type of contracts are utilized when the SoW cannot be determined at the time of the bid?
Unit Price
Which project document summarizes corrections that a contractor must make prior to work being accepted as complete?
Punch list
Name the document that is responsible for tracking issues raised in meetings and forms the agenda for subsequent meetings.
Meeting Minutes
True or False: The proposal request tells the contractor the date to begin work.
False. The proposal request is used to solicit a quotation from the contractor for a proposed change to the scope of the project. The notice to proceed (NTP) tells the contractor the date to begin work.
Drawings indicate that cables shall be fished through existing office walls. However, the ICT installer finds the walls are constructed with multiple fire barriers, prohibiting a top to bottom pathway. What document should be requested from the owner’s representative?
Request for Information (RFI). RFIs are used to request clarification, supplemental information, or approval of material substitutions.
What are submittals?
A form of communication between the contractor and the owner defining specifics of how the job will be undertaken.
True or False: Shop drawings are scaled drawings provided by specialty contractors that reflect specific details of the products to be used and their method of installation within a new or renovated space.
True
What types of submittals are used for documenting the specific equipment or products provided on the job?
Manufacturer Product Data Sheets
True or False: If a change occurs to the original SoW, there is no need for a change control process. Operations will continue as normal, and all parties will be notified of the change.
False