Chapter 15 Flashcards
1
Q
If the schedule variance is positive and the cost variance is negative, the project’s status is: Over budget and behind schedule Over budget and ahead of schedule Under budget and behind schedule Under budget and ahead of schedule
A
Under budget and ahead of schedule
2
Q
The EVMS term that represents the value of work actually accomplished is: PV EV AC BAC
A
EV
3
Q
Which of the following terms is used to determine the trend on cost? CV EAC CPI AC
A
CPI
4
Q
If PV = $100, EV = $200 and AC = $300, the status is: Over budget and behind schedule Over budget and ahead of schedule Under budget and behind schedule Under budget and ahead of schedule
A
Over budget and ahead of schedule
5
Q
If SPI = 1.05 and CPI = 0.96, the project’s trend is: Over budget and behind schedule Over budget and ahead of schedule Under budget and behind schedule Under budget and ahead of schedule
A
Over budget and ahead of schedule
6
Q
Consider the following: BAC = $1000, VAC = -$200 , and AC = $400. Therefore EV = \_\_\_\_\_. $ 480 $ 600 $ 800 Cannot be determined
A
Cannot be determined
7
Q
Consider the following: BAC = $1000, VAC = -$200, and AC = $400. Therefore, SV = \_\_\_\_\_. $ 480 $ 600 $ 800 Cannot be determined
A
Cannot be determined
8
Q
The difference between the cost baseline and the contracted cost is the: Cost at completion Management reserve Profit Cost of scope changes
A
Management reserve
9
Q
The best source of revenue for a customer-requested scope change is: A customer-funded contract amendment Management reserve Undistributed budget Profits
A
A customer-funded contract amendment
10
Q
The form that is used to establish charge numbers is the: Responsibility Assignment matrix Work authorization form Work package Cost account change notice
A
Work authorization form
11
Q
The weakness in all of earned value measurement is the way we calculate: PV EV AC EAC
A
EV
12
Q
The best method to price out a work package is to use the:
Average departmental labor rate
Average pay grade labor rate
Actual salary of the workers assuming they are
Statistical data from the Payroll Department
A
Actual salary of the workers assuming they are
13
Q
Which of the following escalation factors are usually paid for with funds from the management reserve? Salaries Overhead rates Material costs All of the above
A
All of the above
14
Q
A common cause for a favorable SV but unfavorable CV might be: Using lower salaried workers Using overtime Using less expensive raw materials All of the above
A
Using overtime
15
Q
A common cause for a favorable CV but unfavorable SV might be: Too many workers on the project Too few workers on the project Crashing the project Use of overtime
A
Too few workers on the project