Chapter 15 Flashcards

1
Q
If the schedule variance is positive and the cost variance is negative, the project’s status is:
Over budget and behind schedule
Over budget and ahead of schedule
Under budget and behind schedule
Under budget and ahead of schedule
A

Under budget and ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
The EVMS term that represents the value of work actually accomplished is:
PV
EV
AC
BAC
A

EV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
Which of the following terms is used to determine the trend on cost?
CV
EAC
CPI
AC
A

CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
If PV = $100, EV = $200 and AC = $300, the status is:
Over budget and behind schedule
Over budget and ahead of schedule
Under budget and behind schedule
Under budget and ahead of schedule
A

Over budget and ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
If SPI = 1.05 and CPI = 0.96, the project’s trend is:
Over budget and behind schedule
Over budget and ahead of schedule
Under budget and behind schedule
Under budget and ahead of schedule
A

Over budget and ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
Consider the following: BAC = $1000, VAC = -$200 , and AC = $400. Therefore EV = \_\_\_\_\_.
$ 480
$ 600
$ 800
Cannot be determined
A

Cannot be determined

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
Consider the following: BAC = $1000, VAC = -$200, and AC = $400. Therefore, SV = \_\_\_\_\_.
$ 480
$ 600
$ 800
Cannot be determined
A

Cannot be determined

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
The difference between the cost baseline and the contracted cost is the:
Cost at completion
Management reserve
Profit
Cost of scope changes
A

Management reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
The best source of revenue for a customer-requested scope change is:
A customer-funded contract amendment
Management reserve
Undistributed budget
Profits
A

A customer-funded contract amendment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
The form that is used to establish charge numbers is the:
Responsibility Assignment matrix
Work authorization form
Work package
Cost account change notice
A

Work authorization form

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
The weakness in all of earned value measurement is the way we calculate:
PV
EV
AC
EAC
A

EV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The best method to price out a work package is to use the:
Average departmental labor rate
Average pay grade labor rate
Actual salary of the workers assuming they are
Statistical data from the Payroll Department

A

Actual salary of the workers assuming they are

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
Which of the following escalation factors are usually paid for with funds from the management reserve?
Salaries
Overhead rates
Material costs
All of the above
A

All of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
A common cause for a favorable SV but unfavorable CV might be:
Using lower salaried workers
Using overtime
Using less expensive raw materials
All of the above
A

Using overtime

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
A common cause for a favorable CV but unfavorable SV might be:
Too many workers on the project
Too few workers on the project
Crashing the project
Use of overtime
A

Too few workers on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
An S-Curve plots:
Cumulative cost as a function of time
Schedule variance as a function of time
Work package schedules as a function of time
None of the above
A

Cumulative cost as a function of time

17
Q

If PV > AC, then we are spending less than the plan called for but we do not know if that’s good or bad without having a value for EV.
True
False

A

True

18
Q

Earned value measurement systems must be capable of:
Measuring resources consumed
Measuring status and accomplishment
Provide a basis for diagnosis and replanning
All of the above

A

All of the above

19
Q
The person or group with greatest ability to influence cost at project initiation is:
The customer / owner
The project manager
The project team
The users
A

The customer / owner

20
Q

At project initiation:
Few cost reduction opportunities exist and the cost of each change is large
Few cost reduction opportunities exist and the cost of each change is low
Many cost reduction opportunities exist and the cost of each change is high
Many cost reduction opportunities exist and the of each change is low

A

Many cost reduction opportunities exist and the of each change is low

21
Q
The establishment of all of the charge numbers for a project is called the:
Work package codes
Code of accounts
Summation of charge numbers
Cost accounts
A

Code of accounts

22
Q
Work that does not lend itself to subdivision into discrete scheduled increments of work, such as project support, is called:
Measurable effort
Level of effort
Discrete estimates
Work package effort
A

Level of effort

23
Q

Variance envelopes are usually established because:
All cost variances must be accounted for and explained
Not all cost variances must be explained even though they exist
All schedule variances must be explained
All cost overruns require sponsor authorization

A

Not all cost variances must be explained even though they exist

24
Q
The 50-50 rule is a technique used to determine:
EV
EAC
CPI
VAC
A

EV

25
Q
In which type of project report would we most likely find EAC and ETC?
Performance
Status
Forecast
Exception
A

Forecast