Which of the following is a cost estimating relationship?
Mathematical equations based upon regression analysis
Cost-quantity relationships
Cost-Cost relationships
All of the above

A

All of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
Which of the following standard project estimating techniques is usually accomplished in weeks?
Parametric
Analogy
Engineering
Grassroots
A

Analogy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
Pricing out the construction cost of a home by a cost per square foot would be representative of a \_\_\_\_\_ estimate.
Parametric
Analogy
Engineering
Grassroots
A

Parametric

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
When a functional manager tells you that your project is 10% more difficult than the standard project, the functional manager is providing you with a \_\_\_\_\_ estimate.
Parametric
Analogy
Engineering
Grassroots
A

Analogy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
Which of the following projects would most likely have reasonably good estimating techniques?
Construction
R & D
Software development
New product development
A

Construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
Material provided in a proposal to justify one’s estimates are called:
Supporting pricing
Back-up data
Risk justification
Proprietary pricing
A

Back-up data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
An employee earning $40/hour works in a department where the overhead is 125%. A billable or charge back hour to this department would be:
$ 40
$ 50
$ 90
$ 100
A

$ 90

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which of the following is an estimating pitfall?
Misinterpretation of the statement of work
Inaccurate work breakdown structure
Failure to use correct estimating techniques.
All of the above

A

All of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
Which of the following components of life cycle costing incurs the largest cost?
R & D
Production
Operational and Support
Disposal
A

Operational and Support

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
Which of the following is generally not part of capital budgeting?
Life cycle cost estimating
Net present value
Internal rate of return
Discounted cash flow
A

Life cycle cost estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly