Chapter 11 Flashcards
Generally speaking, the lowest level in the WBS is referred to as: Level 3 Level 4 Level 5 The work package
The work package
Scope creep is generally the result of: Having too many levels in the WBS Poorly defined SOW Too much detail in the specifications Having the wrong people assigned to the project
Poorly defined SOW
Which of the following is not a benefit of having a highly detailed work breakdown structure?
Lower status reporting costs
Less likely that anything will be omitted
Better estimating
Better activity tracking
Lower status reporting costs
All work packages in a project must be at the same level of the WBS
True
False
False
Generally speaking, work packages are assigned to one functional unit.
True
False
True
If the customer’s SOW contains words such as nearly or approximately, then:
The project manager uses his discretion in determining the meaning
The sponsor uses his discretion in determining the meaning
The customer uses his discretion in determining the meaning
Scope creep is unlikely
The customer uses his discretion in determining the meaning
Which of the following documents is not defined in the text as one of the four critical documents for preliminary planning? SOW WBS Specifications Network Diagrams
Network Diagrams
Project managers often rewrite the customer’s SOW into a document that the project team can easily understand. The document is called: The redefined SOW The scope statement he deliverable statement The finalized SOW statement
The scope statement
Which of the following would be the first item to be discussed in the initial kickoff meeting for a project? Understanding of the requirements Understanding of the plan Understanding of the schedule Understanding of the budget
Understanding of the requirements
Which of the following is often overlooked when planning and budgeting a project?
Customer’s milestones
Cost and size of contractual documentation
Number of meetings with the customer
Timing of the deliverables
Cost and size of contractual documentation
Which of the following is normally not addressed in a change control board meeting to approve a scope change?
Cost of the change
Which functional unit will perform the change
Impact on the schedule
Value-added opportunity for the client
Which functional unit will perform the change
Which of the following is usually not validated by using the WBS? The schedule The Risks The quality of the deliverables The budget
The quality of the deliverables
A project manager desires a work breakdown structure that goes through 6 levels of detail. Level 3 through level 6 would most likely be prepared by: Project sponsor Project manager Subject matter experts Customer
Subject matter experts
Plans such as the cost plan, schedule plan and quality plan are referred to as: Integration plans Specialized plans Functional plans Subsidiary plans
Subsidiary plans
Which of the following is usually preferred for the placement of the project manager with regard to the WBS? The project manager’s salary should be:
Divided up at each work package.
Divided up at each WBS element not lower than level 3 of the WBS.
Divided up at each level 2 WBS element.
There should be only one WBS element covering the project manager’s salary.
There should be only one WBS element covering the project manager’s salary.