Case Study Flashcards
Explain the background to the development at Bellamy and Byng Street.
Were there any major site constraints /opportunities?
The site sat within the Isle of Dogs Opportunity area which is identified within the Mayors London Plan as an opportunity area with potential for 29,000 homes.
Why was Option 1 ruled out?
Option 1 was ruled out due to the height restrictions within the Millwall Inner Dock Tall Building Zone. The height alterations would exceed these limits.
What was the limit of the tall building zone compared to the proposed height?
The current height of the development was 25 storeys, an increase in 5 additional floors would mean it would surpass the 26 storey requirement.
Why was it considered that the building under Option 1 may face opposition from the local Council or residents?
Due to the height restrictions within the Millwall Inner Dock Tall Building Zone.
What were the affordable housing requirements underlined by LBTH’s Local Plan?
35% affordable housing by habitable room with a tenure split of 70% Social Rent and 30% Intermediate
What are the negative aspects of Options 2 and 5?
The lack of overall intermediate homes for local and key worker people who are unable to afford a private home and earn too much for social rented home.
Why did you consider that a combination of Options 2 and 5 was the best for your project?
This approach struck a balance between increasing overall housing supply, as indicated by Option 2, and prioritizing an elevated level of social rented housing, as highlighted in Option 5.
How did your chosen option respond to the need for intermediate dwellings?
What would have been as conflict of interest and how did you check for this?
Someone else was to be advising the local council on Viability implications for the development. Therefore before undertaking the instruction, a conflict check was issued out.
What was the Local Plan mentioning about the need of family homes?
To provide a higher level of affordable family homes
Did your chosen Options assist with this requirement? (family homes)
It provided an increased amount of Social Rented family homes compared to the existing scheme
How did you do your research in regard to the private and affordable sales?
By using comparable evidence
Explain your methodology for comparable evidence to inform your development appraisal.
For the private sales values I gathered local market data (focusing on factors such as location, size, tenure, amenities)
What information was included within your detailed financial appraisal?
Revenue
Costs
Finance
Why is it useful to verify build costs using BCIS?
it ensures accurate project budgeting by using real constriction data.