Bootcamp Chapter 7 Flashcards
Which of the following is not included in the analysis of life cycle costs?
A. Operating costs
B. Warranty costs
C. Interest on advances
D. Requir costs
ANSWER: C
Interest on advances is a financial term unrelated to life cycle costing.
What is the difference between costs and price?
A. Price includes inflation and cost does not
B. Price minus cost equals cash flow, which is tied to the company’s chart of accounts.
C. Cost is more accurate than price because it is based on the WBS
D. Cost is the amount of money it will take to create the project, and price is an organizational business decision on what to charge for the project
ANSWER: D
Which of the following is a tool/technique for the Estimate Costs process?
A. Bottom-up estimating
B. Vendor invoices
C. Project management estimating hardware
D. Constrained optimization
ANSWER: A
Bottom-up estimating is one of several methods for estimating costs.
A ROM (rough order of magnitude) estimate is most appropriate for which phase of project management?
A. Preliminary RAM
B. Initiating
C. Planning
D. When a SWAG is required
ANSWER: B
Answer A is unrelated to estimating ranges; C is where you would produce a budget estimate or definitive estimate; and D is a slang acronym related to a method of estimating.
A definitive estimate, developed late in planning, has a ____ % range.
A. -5 to +10
B. -10 to +25
C. -1 to +5
D. There is no defined range
ANSWER: A
Which term is used to refer to the project’s initial cost, plus the cost of using the project’s output over time?
A. Benefit cost ratio
B. Life cycle cost
C. SG&A
D. Operating cost
ANSWER: B
Which of the following is not an input to the Determine Budget process?
A. PERT
B. Project schedule
C. Resource calendars
D. Contracts
ANSWER: A
PERT (program evaluation and review technique) is unrelated to the Determine Budget process.
Which of the following quality costs should be included in the project cost estimate?
A. The cost of the Quality Control manager
B. Costs of conformance and nonconformance
C. Costs of only the quality assurance
D. Costs of only nonconformance
ANSWER: B
Answer A is only part of the quality cost and might or might not be included in project cost depending on the organizational policy. Answers C and D offer only part of the answer.
In which document would you find funding constraints?
A. Scope statement
B. WBS
C. EVM
D. Life cycle cost
ANSWER: A
None of the other documents, methods, or processes in Answers B, C or D includes funding constraints
Which of the following is true for management reserves?
A. They are controlled by the project manager
B. They are not part of the project costs baseline
C. They are always included in an EV calculation
D. They are set aside for known knowns
ANSWER: B
Answer A is not correct because management reserves are controlled by the project sponsor; C is not correct because management reserves are never included in EV unless they have been released to the project and the budget has been changed. Answer D is not correct because management reserves are set aside for unknown unknowns
What is sunk cost?
A. Money ready to be spent on a project
B. Money already spent on a project
C. Money in contingency for unknown unknowns
D. Part of accelerated deprecation
ANSWER: B
A, C and D are financial terms, but not sunk cost.
A project sponsor asks you to determine the cost performance needed with the remaining project resources in order meet the project goal. What measurement do you need to find to convey this information to the project sponsor?
A. TCPI
B. EV
C. BAC
D. SV
ANSWER: A
To-complete performance index is “a measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
You are the PM. you have purchased a large crane to aid in field construction on your long-term project (10 years). This crane cost $250k to purchase and install. At the end of its life (10 years) it will have a scrap value of $50k. Using straight line depreciation, how much would you depreciate the crane, each year, if the expected long term interest rate was 5% and the company used an IRR of 15%?
A. $25k
B. $200k
C. $27.5k
D. $20k
ANSWER: D
The correct calculation is ($250k-$50k)/10=$20k. Interest rate and IRR are unusable information
Which of the following cannot be a category of cost?
A. Direct.
B. Indirect-variable
C. Direct-indirect
D. Direct-variable
ANSWER: C
Direct and indirect are separate and mutually exclusive categories of cost.
Name two methods of accelerated depreciation?
A. First cost and life-cycle cost
B. Direct and fixed
C. Sum of the year’s digits and double declining balance
D. Linear and nonlinear
ANSWER: C
Answer A is not related to depreciation, B refers to categories of cost, D refers to constrained optimization project selection methods