Bootcamp Chapter 6 Flashcards
For which of the following process is the network diagram the main output (see image):
A. Estimate Activity Resources
B. Develop Schedule
C. Sequence Activities
D. Estimate Activity Durations
ANSWER: C The network diagram shows the logical relationships and sequence of the activities.
Work performance information is a primary output for which process?
A. Estimate Activity Resources
B. Develop Schedule
C. Control Schedule
D. Estimate Activity Durations
ANSWER: C Performance information is the means by which the project manager knows if the project is progressing according to the schedule and the basis used for making decisions and communication with stakeholders
Which of the following statements is false?
A. A schedule baseline is one way to graphically depict the project schedule
B. A schedule baseline is a component of the project management plan
C. A baseline is accepted and approved by the appropriate stakeholder
D. A schedule baseline is the original plan, plus approved changes
ANSWER: A The PMBOK lists three ways that a project schedule can be shown graphically; milestone chart, bar chart, and schedule network diagram.
Which of the following is not a tool and technique for the Define Activities process?
A. Expert judgement
B. Milestone list
C. Rolling wave planning
D. Decomposition
ANSWER: B Milestone list is an output of the Define Activities Process. The others are tools and techniques for this process
Which of the following is not an output of Control Schedule? A. Work performance information
B. Organizational process assets updates
C. Enterprise environmental factors updates
D. Change requests
ANSWER: C The others are all outputs of this process
Which of the following is the most important input to the Develop Schedule process?
A. Activity list
B. Activity attributes
C. Project schedule network diagram
D. Resources calendars
ANSWER: C Although the other inputs are important, the logical relationships of the activities are the most important for developing the schedule.
What document should you use in order to look up the successor activities for a given activity?
A. Rolling wave plan
B. Activity list
C. Activity attributes register
D. Milestone List
ANSWER: C Activity attributes include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.
You are using a project management software tool to develop your project schedule model. Which of the following woul dnot be needed for the software to develop the schedule?
A. Logical relationships among the tasks
B. Duration of each task
C. Milestones
D. Resources
ANSWER: C
A scheduling tool needs the relationships, the duration, and the names of the resources, and their availability in order to automatically develop a network diagram. Milestones are significant events that you want to track by completion dates to show progress along the schedule.
The following network diagram is an example of which type of scheduling tool and technique?
A. PERT
B. AOA
C. PDM
D. GERT
ANSWER: B
This is an AOA (activity-on-arrow) diagram because the activities are on the arrows.
You have already defined the project activities and sequenced the activites. Which of the following tools will you use as you work on the next step in time management?
A. Dependency determination
B. Bottom-up estimating
C. Rolling wave planning
D. Analogous estimating
ANSWER: B
Bottom-up estimating is a tool and technique for the Estimate Activity Resources process, the next process in time management.
The following is an example of which kind of network diagram?
A. PERT
B. AOM
C. ADM
D. GERT
ANSWER: D
This is a GERT network because it contains a loop between activities A and B.
Which of the following is not needed to determine the critical path?
A. Tasks
B. Duration of tasks
C. Sequence of tasks
D. Resources
ANSWER: D
All the other components must be known before you can develop the network diagram to determine the critical path. The critical path will need to be recalculated after resources have been applied within the schedule since resource availability and constraints may cause the critical path to shift within the schedule network?
You are working on defining the activities for the project. If you want the most accurate results, who are the most important people to involve in decomposing the WBS work packages into project activities?
A. Team members
B. Project manager
C. Experts
D. The Sponsor
ANSWER: A
Team members are responsible for completing the work packages and should know the work that will be required to produce the deliverables.
Which of the following is most important for the Define Activities process?
A. The project scope statement
B. Enterprise environmental factors
C. Organizational process assets
D. The WBS
ANSWER: D
The WBS is the most important because the deliverables identified in the WBS establish the required results for a successful project, and the Define Activities process is focused on identifying the specific work necessary to produce the required results.
Project documents updates are an output of all except one of the following processes. Which one?
A. Define Activities
B. Sequence Activities
C. Estimate Activiities Resources
D. Estimate Activities Durations
ANSWER: A
The outputs of this process are the activity list, activity attributes, and the milestone list. Project documents updates are outputs for the other processes.