Bootcamp Chapter 5 Flashcards
When is a project considered successful?
A. When extra features have been added that the customer really likes
B. When senior management is happy with the project outcome and declares the project complete
C. When the project manager is promoted because of the way he or she managed the project
D. When the project meets stakeholder expectations
ANSWER: D
You have just joined Games R Us, and have been given a new project to manage. Your sponsor wants to meet with you to discuss your roles and responsibilities. Which of the following is not a responsibility of the sponsor?
A. Developing the project management plan
B. Providing resources for the project
C. Communicating about the project to higher levels of management
D. Protecting the project from changing
ANSWER: A
Answers B, C, D are the responsibilities of the project sponsor. Answer A is the responsibility of the project manager
Which technique should you use to determine the difference between the baseline and actual performance? A. Variance analysis B. Gap assessment C. Inspection D. Project analysis
ANSWER: A
Variance analysis is “a technique for determining the cause and degree of difference between the baseline and actual performance”
Which of the following techniques can help prevent scope creep?
A. Kaizen
B. Benchmarking
C. Work authorization system
D. Life-cycle costing
ANSWER: C
Work authorization system is a set of formal procedures that defines how project work will be authorized in order to ensure that work is done by the right resources, at the right time, in the right order
Various breakdown structures can be used on a project. Which of the following is not an example of a breakdown structure?
A. Risk breakdown structure
B. Organizational breakdown structure
C. Resource breakdown structure
D. Cost breakdown structure
ANSWER: D
There is no Cost Breakdown structure
Project Scope Management involves doing the work required to complete the project successfully:
A. Along with the creation of a scope management plan
B. No more, no less
C. In the eyes of all key stakeholders
D. At least one time in each project
ANSWER: B
PMBOK describes scope management as the processes to ensure that “all of the work required, and only the work required” is completed successfully.
During the Collect Requirements process, you should ensure that requirements documentation contains requirements that are:
A. Acceptable to the project team
B. Within the project budget
C. Testable
D. Explained at a high level in order to allow room for adjustment
ANSWER: C
PMBOK states the requirements need to be unambiguous, meaning they are measurable and testable.
Scope creep means that additional work is done. Which of these is an example of scope creep?
A. Work included in the project charter
B. Work in approved change requests
C. Work to deliver more function than requested
D. Work further decomposed within the WBS
ANSWER: C
Scope creep is defined as adding features and functionality without addressing the effects on time, costs, and resources, or without customer approval. C is correct because it clearly indicates an increase in functionality without approval by the customer.
What is scope creep?
A. Meeting the expectations of stakeholders
B. Providing customers with extras not originally included in the project charter or project plan in an effort to exceed their expectations
C. One of the key elements at the disposal of the project manager
D. Something endorsed by the PMI
ANSWER: B
Scope creep is always considered to be bad.
It is generally accepted that scope creep does not add___to the project
A. Time
B. Cost
C. Value
D. Resources
ANSWER: C
Scope creep undermines project value by adding extras without consideration of their impact on time, costs, or resources.
____ is defined as the features and functions that characterize the product, service or result of the project.
A. project scope
B. Boundary-based scope
C. Foundational scope
D. Product scope
ANSWER: D
Product scope refers to “the features and functions that characterize a product, service, or result”
____ is defined as the work required to deliver the product, service or result.
A. Project scope
B. Boundary-based scope
C. Foundational scope
D. Product scope
ANSWER: A
Project scope is “the work performed to deliver a product, service or result with the specified features and functions”
Typically, what is project scope detailed, managed, and measured against?
A. The scope statement
B. The project management plan
C. The statement of work
D. The project charter
ANSWER: B
A, C and D are components of the project management plan and either define or influence the definition of project scope
Which of the following is not one of the Project Scope Management processes?
A. Collect Requirements
B. Define Structure Control
C. Validate Scope
D. Control Scope
ANSWER: B
The PMBOK guide states that requirements are a condition or capability that must be met or possessed by a system, product, service, result, or component to satisfy:
A. Those expectations that can be traced back to requirements
B. The needs for which it was undertaken
C. A contract, standard, specification, or other formal document
D. All key stakeholders
ANSWER: C
This is correct because it completes the PMBOK guide definition of a requirement.