3.6 Contract Administration Flashcards

1
Q

Who is responsible for administering the contract?

A

NEC is PM
JCT is Employer’s Agent or Contract Administrator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is PC?

A

Practical Completion is the when the project is complete and there are only minor defects that don’t interfere the use of building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What happens at PC?

A

-50% of retention is released
-Defect rectification starts
-The employer starts insuring and securing the building
-Damages end

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Contract admin - Level 2 example?

A

I instructed the change in carpet type and colour. For the office refurb.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Forms of JCT Contracts?

A

Design and build
Minor works
PCSA - Pre-Con Services agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Forms of NEC Contracts

A

NEC ECC suite. (also come in subcontract form and short form)
Professional services contracts
Design build operate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the pain gain share, what was it on AQP?

A

110% of target = 100%
105% of target = 70%
100% 0f target
90% of target = 30%
80% of target = 50%
below 80% = 0%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is included in an NEC contract?

A

Contract data P1 - Client
Contract data P2 - Client
Core clauses
Secondary clauses
Y(UK)
W(1-3)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Sectional completion vs partial possession?

A

Sectional completion is pre-agreed. Same as PC. Partial possession is not pre agreed but same procedure happens pending the contractor’s acceptance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is “Time at Large”?

A

No completion date in the Contract or it is invalid. Best endeavours should be used to meet completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What clause did you refer to in your instruction?

A

14.3 for the changes to scope or key date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What clause would you refer to for EWN? and why would you raise it?

A

Clause 15 for EWN. For potential changes in cost, time or performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How did did you manage to issue instruction if you’re not the PM?

A

Delegated powers by the PM notified to the subcontract to do so. Stated in 14 (instructions)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the time scales for compensation events for both main and sub contracts?

A

Quotation Response Notify of no reply
M/C 3 2 2
S/C 2 4 3

(In weeks)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the Y(UK) clauses?

A

1 - project bank account
2 - HGCR Act
3 - third party rights

How well did you know this?
1
Not at all
2
3
4
5
Perfectly