1. Case Study Flashcards
What goes in a tender enquiry?
Invitation to tender
Form for tender
Bona fide
Quality questions
Assessment matrix/criteria
Contract
Client amendments
Contract documents/specs
NEC - how do you select design obligation and what could be required from subcontractor?
NEC secondary clause X15.
Subcontractor needs PII.
Need for collateral warranty.
Design obligation (reasonable skill and care or fit for purpose)
How to manage the performance of a subcontractor
Performance bond (conditional not on demand) x13
Damages x7
Incentives (early completion bonus) x6
Key dates
What is a Contractor’s Proposal and where is it found?
NEC4 Section 16 - contractor suggests scope changes that benefit the project.
Contractor’s proposal timescales?
PM has 4 weeks from issue to either:
- Accept and instruct the change
- Request a quote for the change
- Reject proposal
What were the delay damages on the scheme?
Phase A = 1.5k per day / 10k per week
Phase B = 3k per day / 21k per week
What is a standard door size?
1981mm x 533mm
What is the procedure for a road closure?
- TTRO(Temp traffic regulation order) issued to council.
- 12 weeks for council to deliberate
- Requirement for residents and businesses to be alerted.
What is a demolition notice?
- Also known as Section 80.
- Issue to local authority with details of demo.
- Section 81 with additional conditions.
- if you don’t receive this within 6 weeks its approved.
Planning process?