3.3 Project finance, Reporting & Quantification Flashcards
What is the NRM?
New Rules of Measurement
-NRM 1 - Order of cost estimating and cost planning for capital building works
-NRM 2 - Detailed measurement for building works.
-NRM 3 - Order of cost estimating and cost planning for building maintenance works
Why is it important to measure according to industry standards?
Consistency and accuracy
Minimise dispute as they are standardised
Tell me about NRM2?
Gives guidance on preparation of BoQ and schedules of works.
Split into building elements
Elements are split into three levels of detail.
What is an Order of Cost Estimate?
Defined in NRM1 as estimate based on similar projects.
What is the difference between an order of cost estimate and a cost plan?
Estimate provides a likely cost based on employer’s requirements. Cost plan is based on drawings with elemental breakdown of cost.
What are the RIBA Stages of Work?
Stage 0 - Strategic Definition
Stage 1 - Preparation and Brief
Stage 2 - Concept Design
Stage 3 - Spatial Design
Stage 4 - Technical Design
Stage 5 - Construction and Manufacturing
Stage 6 - Handover
Stage 7 - Use
What is SMM7?
Standard method of measurement 7th edition which was published by RICS in 1922 but it was superseded by NRM2.
What are the sources for cost information?
-BCIS
-Pricing books such as Spon’s
-Pricing information from previous schemes
-In-house cost models
-Speaking to subcontractors and suppliers
Key reasons for cost overruns on projects?
-Unrealistic cost estimates
-Ambiguous briefs or changes
-Inadequate risk allowances
-Poor design
-Poor tender review
-Inflation
-External factors (pandemics, recession…)
Examples of pricing documents?
-BoQ
-Schedule of rates
-Schedule of work
-Priced activity schedule
-Contract sum analysis
Examples of pricing options for construction contracts?
-Lump sum
-Cost-plus
-Remeasurement
-Target cost
-Guaranteed maximum price(GMP)
What the main elements of an interim valuation?
-Prelims
-Measured work
-Variations/CEs
-Materials
-Retention
-Fees
-OH&P
What happens if you fail to pay the contractor on time?
May be entitled to interest
May exercise their right to suspend works
What is a payless notice?
This the paying party the right to pay less than previously notified.
What is a payment timeline?
19 day payment terms is Due date to final payment date. Payment notice must be no more than 5 days from due date.