3.3 Project finance, Reporting & Quantification Flashcards

1
Q

What is the NRM?

A

New Rules of Measurement
-NRM 1 - Order of cost estimating and cost planning for capital building works
-NRM 2 - Detailed measurement for building works.
-NRM 3 - Order of cost estimating and cost planning for building maintenance works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why is it important to measure according to industry standards?

A

Consistency and accuracy
Minimise dispute as they are standardised

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Tell me about NRM2?

A

Gives guidance on preparation of BoQ and schedules of works.
Split into building elements
Elements are split into three levels of detail.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is an Order of Cost Estimate?

A

Defined in NRM1 as estimate based on similar projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the difference between an order of cost estimate and a cost plan?

A

Estimate provides a likely cost based on employer’s requirements. Cost plan is based on drawings with elemental breakdown of cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the RIBA Stages of Work?

A

Stage 0 - Strategic Definition
Stage 1 - Preparation and Brief
Stage 2 - Concept Design
Stage 3 - Spatial Design
Stage 4 - Technical Design
Stage 5 - Construction and Manufacturing
Stage 6 - Handover
Stage 7 - Use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is SMM7?

A

Standard method of measurement 7th edition which was published by RICS in 1922 but it was superseded by NRM2.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the sources for cost information?

A

-BCIS
-Pricing books such as Spon’s
-Pricing information from previous schemes
-In-house cost models
-Speaking to subcontractors and suppliers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Key reasons for cost overruns on projects?

A

-Unrealistic cost estimates
-Ambiguous briefs or changes
-Inadequate risk allowances
-Poor design
-Poor tender review
-Inflation
-External factors (pandemics, recession…)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Examples of pricing documents?

A

-BoQ
-Schedule of rates
-Schedule of work
-Priced activity schedule
-Contract sum analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Examples of pricing options for construction contracts?

A

-Lump sum
-Cost-plus
-Remeasurement
-Target cost
-Guaranteed maximum price(GMP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What the main elements of an interim valuation?

A

-Prelims
-Measured work
-Variations/CEs
-Materials
-Retention
-Fees
-OH&P

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What happens if you fail to pay the contractor on time?

A

May be entitled to interest
May exercise their right to suspend works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a payless notice?

A

This the paying party the right to pay less than previously notified.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a payment timeline?

A

19 day payment terms is Due date to final payment date. Payment notice must be no more than 5 days from due date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the components of a final account?

A

-Summary
-Measured work
-CEs
-Delay damages
-Retention
-Fees
-OH&P

17
Q

Reporting - Level 2 example?

A

Weekly staff time tracker.

18
Q

Reporting - Level 3 example?

A

CTC and CVR on RAF M. Save costs with the implementation of Cemar and remove the data admin personnel.

19
Q

Quantification - Level 2 example?

A

On Cov AQP bill production for surfacing or activity schedule for VRS.
Quotation requested for plane and relay. How I complied quote.

20
Q

Quantification - Level 3 example?

A

Advised on staged payments on RAFM.

21
Q

Why wasn’t the additional surfacing work done under BoQ rates?

A

If work is over 0.5% of contract sum it is a CE.

22
Q

What do you do following an instruction?

A
  • Acknowledge (clarify changes)
  • Investigate (design/programme/measure)
  • Get quotes and review
  • Draft final quote
  • Issue
23
Q

What is found in CVR?

A

Cost - booked and forecasted. (prelims/plant/materials/fees/OH/damages/risk)
Value - contract sum plus changes / cost plus flee / cost plus fees and incentives
Cashflow - shows the balance on an interim basis

24
Q

What was the method of measurement for VRS and Surfacing?

A

Method of measurement for highways work.
VRS - series 400
Surfacing - series 700

25
Q

Pavement build-up and what type?

A

40 sur / 50 bin / 220 bas
HRA - hot rolled asphalt
SMA - stone mastic asphalt

26
Q

What is ICMS?

A

International Cost Management Standard.
- Third edition for life cycle costing of construction works.
- Latest edition guides on carbon emssions.