10.3d CPA - Interpretation Flashcards

1
Q

What does the critical path show?

A

The route where there is no float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does is mean if there is no float?

A

There is no room for delay in the activities if you want the project to finish in the shortest time possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does the float show?

A

Those tasks which can overrun without holding up the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Total float time formula

A

Total float time = LFT - duration - EST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Benefits of using CPA:

A
  • Helps reduce risk and costs of complex projects
  • Encourages careful assessment of requirements of each activity
  • Decision-making tool
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Drawbacks of using CPA:

A
  • Reliability based on accurate estimates and assumptions
  • Does not guarantee success
  • Too many activities may make diagram too complicated
  • Takes time to plan
  • Tight deadlines - lead to lower quality
  • Doesn’t tell anything about costs or how good the project is
How well did you know this?
1
Not at all
2
3
4
5
Perfectly