10.3b Network Analysis (CPA) Flashcards

1
Q

Critical path analysis definition

A

Project analysis and planning method that allows a project to be completed in the shortest possible time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Information needed for CPA:

A
  • List of activities required to complete the project
  • Duration that each activity will take to completion
  • Dependencies between the activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does CPA calculate?

A
  • The shortest path of planned activities to the end of the project
  • Earliest and last time that each activity can start and finish without making project longer
  • Which activities are ‘critical’ and which have ‘total float’
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does it mean if an activity is ‘critical’?

A

It is on the shortest path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does it mean if an activity has ‘total float’?

A

It can be delayed without making the project longer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a node in CPA?

A

A circle that represents a point in time where an activity is started or finished

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is shown in the left half of the node?

A

The unique node number

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is shown in the top right section of the node?

A

The EST that this activity can commence based on completion of the previous activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is shown in the bottom right section of the node?

A

The LFT by which the previous activity must be completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is an activity shown as on the network?

A

A line/arrow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is shown above the relevant line in the network?

A

A letter representing the activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is shown below the relevant line in the network?

A

The length of time it takes to complete an activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When two activities meet, the next activity EST will be the lowest or highest figure?

A

Highest

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When two activities meet, the previous activities LFT will be the lowest or highest figure?

A

Lowest

How well did you know this?
1
Not at all
2
3
4
5
Perfectly