Validate Scope Flashcards
Validate Scope Inputs
PM Plan (scope management plan, requirements management plan, scope baseline);
Project Documents (lessons learned register, quality reports, requirements documentation, requirements traceability matrix);
Verified Deliverables;
Work Performance Data;
Deliverables that are completed and checked for correctness through the Control Quality Process
Verified Deliverables
True about Validate Scope process
This is the process of formalizing acceptance of the completed project deliverables.
Deliverables that are formally signed off and approved by the authorized stakeholder
Accepted deliverables
Completed deliverables that have not been formally accepted are documented, along with the reasons for non-acceptance of those deliverables. Those deliverables may require a…
Change request for defect repair
Validate Scope Purpose
To obtain the customer’s acceptance of completed project deliverables
Validate Scope Key Benefit
Brings objectivity to the acceptance process;
Increases the likelihood that the final product, service or result will gain acceptance by validating each deliverable.
Validate Scope Concepts
Turn Verified Deliverables into Accepted Deliverables
Validate Scope Outputs
Project Document Updates;
Accepted Deliverables;
Change Requests;
Work Performance Information;
Validate Scope Tools & Techniques
Decision Making;
Inspection
Basis for performing the validation and for final acceptance of the deliverables by the customer or sponsor
Requirements documentation or the scope baseline as well as work performance data from other processes.