Monitor and Control Project Work Flashcards
Inputs - Monitor & Control Project Work Process
PM Plan (Assumption logs, Issue logs); Work Performance Information; Project Documents; Agreements; Organizational Process Assets Enterprise Environmental Factors;
Change requests are processed for review and disposition through the Perform Integrated Change Control process and may include which of the following types of change activities?
Preventive action
Outputs - Monitor & Control Project Work
Updates to project documents (schedule, cost, work performance reports, issue log);
PM Plan Updates;
Work Performance Reports Updates;
Change Requests;
Tools & Techniques - Monitor & Control Project Work
Expert judgement;
Data Analysis (alternative analysis, cost-benefit analysis, earned value analysis, root cause analysis, trend analysis, variance analysis);
Decision Making;
Meetings;
Purpose of Monitor & Control Project Work Process
Track, review, and report progress to meet performance objectives defined in the PM Plan.
Key Benefit - Monitor & Control Project work
Allows all stakeholders to compare current state to planned state
Role of PM in Monitor & Control Project Work
Compare actual performance against PM Plan;
Assess performance to determine if corrective actions are needed;
Check status of risks;
Maintain accurate and timely information base about project’s products;
Provide status reports, work performance measurements, and forecasts to update cost and schedule information;