Create WBS Flashcards
WBS is typically used for
To organize and define the total scope of the project.
WBS dictionary
Document that provides detailed deliverable, activity, and scheduling information about each component in the WBS.
WBS
Hierarchial decomposition of the total scope of work to be carried out to accomplish the project objectives and create the required deliverables.
Key Benefit of WBS
Provides framework for what has to be delivered.
Definition of the work package
Work defined at the lowest level of the WBS for which cost and duration are estimated and managed.
WBS represents
The work specified in the approved project scope statement
Create WBS Inputs
PM Plan;
OPAs;
EEFs;
Project Documents;
Create WBS Outputs
Project Document Updates;
Scope Baseline
Create WBS Tools & Techniques
Expert Judgement;
Decomposition
Describes the Scope Baseline
Approved version of scope statement, WBS, associated WBS dictionary;