Perform Integrated Change Control Flashcards
Inputs - Perform Integrated Change Control
Change Requests; Project Documentation; PM Plan; Organizational Process Assets; Enterprise Environmental Factors; Work Performance Reports;
Outputs - Perform Integrated Change Control
Approved Change Requests;
PM Plan Updates;
Project Documents Updates;
What change request is an intentional activity that ensures the future of performance of project work aligns with the project management plan?
Preventive Action
Role of PM in Perform Integrated Change Control
Stakeholders can request a change request at any time;
Change requests are approved, deferred, or rejected, by either the CCB or the project sponsor or PM;
PM is member of CCB;
Configuration Management
Deals with modifications made to the product or the process used to make the product
Change Management
Deals with changes made to the project baselines;