Sequence Activities Flashcards

1
Q

Mandatory Dependency

A

Relationship that is contractually required or inherent in the nature of the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Precedence Diagramming Method (PDM)

A

Technique in which activities are graphically linked by logical relationships to show the sequence in which the activities are to be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Sequence Activities - Inputs

A

PM Plan (Schedule Management Plan, scope baseline);
Project Documents (activities attributes, activity list, assumption log, milestone list);
EFFs;
OPAs;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Sequence Activities - Outputs

A

Project schedule network diagrams;

Project documents updates (activities attributes, activity list, assumption log, milestone list);

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Most common relationship in the precedence diagram method?

A

Start-to-Finish;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Project schedule network diagrams

A

Identify and document relationships among project activities and show you the logical sequence of project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Precedence Diagram Method (PDM) Logical Relationships

A

Finish to start - an activity cannot start until a predecessor has finished
Finish to finish - an activity cannot finish until a predecessor has finished
Start to start - an activity cannot start until a predecessor has started
Start to finish - an activity cannot start until a predecessor has finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Dependency determination and integration

A

allow you to sequence your activities according to how they are dependent on each other

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

4 types of dependencies

A

Mandatory;
Discretionary;
External;
Internal;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Consider when creating a network diagram

A

Leads (negative value)

Lags (positive value)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Schedule Baseline

A

Formal schedule developed from properly sequenced activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly