Hollie is managing a bathroom renovation project that has a budget of $1,500 and is 40% complete. Hollie planned to spend $500 a month on the three-month project. Hollie is evaluating the status of the project at the end of the first month. What is the project’s planned value?

A

$500

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Hollie is managing a bathroom renovation project that has a budget of $1,500 and is 40% complete. She planned to spend $500 a month on the three-month project. Hollie is evaluating the status of the project at the end of the first month. What is the project’s budget at completion?

A

$1,500

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Hollie is managing a bathroom renovation project. The project has a budget of $1,500 and is 40% complete. The project is a three-month project and Hollie planned to spend $500 a month on the project. Hollie is evaluating the status of the project at the end of the first month. What is the project’s earned value?

A

$600