Unit 4 Test Review Flashcards
Craig needs to weld the car chassis together before Jim can install the engine.
This represents a/an:
Mandatory dependency
The project manager and team have created the schedule for the hospital wireless network upgrade project. The schedule includes a five-day delay for the network approval before the hospital can use the upgraded network.
This causes the finish date of the project to slip by five days. This hospital network project is:
Lagging
Andy prefers to set up furniture before hanging window treatments for his interior design projects. This is an example of a/an:
Discretionary dependency
Due to a gasoline shortage, Ann is unable to secure the gasoline needed to fill up her tractor prior to planting. This is an example of a/an:
External dependency
Alex orders all of the plumbing supplies for his construction projects from the same vendor. Due to a recent fire, the vendor is unable to deliver the supplies when needed. This is an example of a/an:
External dependency
Ashlyn’s pottery project for art class must dry before she can put on a final coat of glaze. This is an example of a/an:
Mandatory dependency
Alex prefers to complete the plumbing work in his construction projects before completing electrical work. This is an example of a/an:
Discretionary dependency
Which best describes the critical path slack?
the earliest a new HVAC system can be ordered from a manufacturer without delaying the project
It took Scott’s team two hours to mow and edge one acre of land. He estimates that it will take his team eight hours to mow and edge four acres of land for an upcoming project. Scott’s duration estimation for this project is an example of:
Parametric estimating
The project manager is creating an estimate to set up an office building’s electrical system. He has twenty-two years of experience managing similar projects. The client needs the estimate quickly. Which type of estimate is he most likely to provide?
Analogous estimating
Maria determines the project duration by overestimating what she calculates by 15%. Maria is using:
Reverse analysis estimating
Adam’s Construction has accepted a contract to build a six-story office building. The company is using a timeline from a two-story building project the company completed in the previous month to develop the schedule for this project. Adam’s Construction is using:
Parametric estimating
Eva has been hired to landscape the new community park. She has sixteen weeks to complete the project, which will take a total of twelve weeks. Eva decides to begin the project immediately so that she has extra time for weather delays. Eva is using:
Reverse analysis
The prom committee is having a contest to design the invitation and poster for this year’s prom. To ensure getting the design to the printer by the January 15th deadline, the committee is holding the contest in November.
This is an example of:
Reverse analysis estimating
Dennis is unable to estimate the duration of his project with certainty, so he decides to break down the work into activities. He then adds up the total quantity for each of the activity durations. Dennis is using:
Bottom-up estimating