Unit 3 Test Review Questions Flashcards

1
Q

Meeting with stakeholders to define and document all the needs for a project

A

Collecting requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Marty is in charge of managing an event for the special Olympics. He has completed the project scope statement and requirements documentation. He is currently working on creating a graphic design by breaking down all the work that needs to occur for the event. Marty is working on:

A

Work breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Mark meets with the conference project stakeholders to determine and document that the number of rooms and meals needed for the conference aligns with the conference project objectives. Which process is Mark conducting?

A

Collect requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Sarah is in charge of a charity event, and she is currently communicating with the catering company and requesting work performance information regarding their progress to compare to her scope baseline. Sarah is working on which process?

A

Verify scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Hollie is a financial project manager. Tina asks Hollie’s team to produce a financial report at the end of the year that includes her company’s income statement and balance sheet. When Hollie’s team completes the work and the deliverables are presented to Tina, Hollie asks Tina to sign off to formally accept the deliverables m. Which process is Hollie conducting?

A

Verifying the scope of

How well did you know this?
1
Not at all
2
3
4
5
Perfectly