Kacie is working on a new car design for an automotive company. She is currently working on a way to analyze, document, and manage all the stakeholder requirements for the new design. Kacie is working on the:
requirements management plan
Group decision making process to collect requirements in which everyone has a vote, and everyone has to agree on the decision.
unanimity
A document that will outline the methods to create and manage requirements, as well as the method used to prioritize requirements.
Requirement management plan
Group decision making technique for collecting requirements in which everyone gets a vote and there is a requirement for over 50% of the group’s support to make the decision.
Majority
Carol is managing a construction project and is considering relocating her team closer to the project construction worksite. She asks the stakeholders to vote on this decision and will make the move only if they all agree to it.
Carol is using which tool or technique to collect requirements?
Unanimity
A project manager is using group decision-making techniques in establishing requirements for a project. Which are the techniques they could use?
Dictatorship, majority, plurality, unanimity
A document used to review the requirements of each of the stakeholders.
Requirement traceability matrix
Meeting with stakeholders to define and document all the needs for a project.
Collecting requirements
The technique of showing a working model of a product to gather feedback before finalizing the product requirements.
Prototype
Angela is meeting with town officials to determine the needs for a transportation project that she is developing. The activity that Angela is participating in is referred to as:
Collecting requirements
Jo Anne is meeting her curriculum team to break down pieces of the project.
At the meeting, she leads her team through the process of decomposing to encompass all of the work on the project. This allows Jo Anne’s team to track, define, and manage each activity. Jo Anne’s team is participating in:
Defining the scope
Tammy is a construction project manager and is currently working on the project scope statement. The stakeholders for this neighborhood project refuse to have a community clubhouse and pool. This requirement would be listed under what section in the project scope statement?
Project exclusions
Breaking down a project into work packages in order to determine milestones.
Creating the WBS
Steve is in charge of building a house, and he is currently working on the project scope statement. Steve has collected all necessary requirements from the stakeholders. He has determined that he needs to provide three bedrooms, two bathrooms, and a two-car garage in a 1,700-square-foot house. These components would be listed under what section in the project o scope statement?
Project deliverables
Steve is in charge of building a house, and he is currently working on the project scope statement. Steve has listed the following:
1. We will have good weather on all workdays, so there will be no delay in the building of the house.
2. All contractors will work efficiently with each other and cause no problems or delays on the house.
These would be listed under what section in the project scope statement?
Project assumptions