3.01 Quiz Flashcards

1
Q

Delores is leading a marketing project. She meets with the stakeholders to define and document all the needs for the marketing project. The activity that Delores is participating in is referred to as:

A

Collecting requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Kristi is in charge of planning a charity event for the hospital. She wants to review the requirements of each of the stakeholders. Kristi should be reviewing which document?

A

Requirements traceability matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Jackie is developing a document that will outline the methods to create and manage requirements, as well as the method used to prioritize requirements.
Jackie is working on the:

A

Requirements management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Sam is an event planner and is considering locations for an annual conference. He has decided to ask the board of directors to vote on two locations, so that whichever location receives over 50% of the group’s support will win. Sam is using which technique to collect requirements?

A

Majority

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Peter is working on a respiration project for firefighters. Before finalizing the product requirements, he would like to show a working model to the frefighters at the local station to gather feedback. The technique that Peter should use to test the working model would be a/an:

A

Prototype

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Kacie is working on a new car design for an automotive company. She is currently working on a way to analyze, document, and manage all the stakeholder requirements for the new design. Kacie is working on the:

A

Requirements management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Carol is managing a construction project and is considering relocating her team closer to the project construction worksite. She asks the stakeholders to vote on this decision and will make the move only if they all agree to it.
Carol is using which tool or technique to collect requirements?

A

Unanimity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The project manager is using group decision-making techniques in establishing requirements for the food refrigeration project. Which are the techniques she could use?

A

Dictatorship, majority, plurality, and unanimity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Heather is working on a project to create a new running shoe. She is working with her stakeholders to decide the color combination for the shoe. Heather decides that they will vote, and everyone has to agree on the color combination. Heather is using which tool or technique to collect requirements?

A

Unanimity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Angela is meeting with town officials to determine the needs for a transportation project that she is developing. The activity that Angela is participating in is referred to as:

A

Collecting requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly