Unit 1 Test Review Flashcards
Cheryl is watching the weather forecast for an outdoor senior picnic project that she planned to determine whether the picnic will need to be moved indoors. Which project process stage is Cheryl in?
Monitoring and Controlling
Johnny is organizing all the specifics for his parents’ 50th anniversary party.
He has made contact with all the vendors, secured the location, and created a weather contingency plan. Johnny is participating in:
Project Management
Petrina sets up a timeline for the financial project she has been assigned. In her timeline, she includes benchmarks and milestones for her team to help keep the project on track. Petrina is establishing good project:
Time Management
Amy recently opened a business and realizes that she needs assistance with the multiple projects that her business is completing. Amy hires an accountant to manage all financial aspects of her projects. Which project management facilitating function is Amy practicing?
Human Resource
David is planning an outdoor college soccer tournament and is expecting one hundred teams to attend. On the morning of the tournament, he evaluates the weather to determine whether the tournament might need to be moved to the next day. David is evaluating the project:
Risk
Lisa is working with her school’s FBLA club to create a budget for the upcoming dance. She recently took classes in Accounting and Personal Finance. Which facilitating function is Lisa exhibiting?
Human Resource
Andrew is deciding on the details of a community service event for his career technical service organization. He will lead his organization through all stages of the life cycle by the end of this school year. Andrew is assuming the role of a:
Project Manager
Bobby negotiated a discount on the delivery fees when he ordered additional tables and chairs for his event. Which facilitating function has Bobby exhibited?
Procurement
After the prom, the student planning committee meets to discuss what activities went well and what activities would need to be changed next time.
What project management process stage is the committee in?
Closing
A project manager facilitates a two-way process that reaches a mutual understanding by the participants. The facilitating function the project manager is using is:
Communications
Andrew is the prom committee chairman. He is at the prom and realizes that the meal delivered to the attendees was steak and not chicken. Andrew makes the catering manager aware immediately that the chicken meal was agreed upon, so the steak meal is outside the project scope. Which project management process stage is Andrew in?
Monitoring and Controlling
Tara is meeting with her stakeholders to determine the scope of work. What process stage is she in?
Initiating
Sierra is working with her sisters to determine how much money they have spent on their parents’ anniversary party to calculate the funds remaining in their budget. What process stage is she in?
Initiating
Joe holds a team meeting to discuss lessons learned. He is in which process stage?
Closing
Alison holds weekly project team meetings to determine whether she needs to crash any project activities to help keep the project on track. What process stage is she in?
Monitoring and Controlling