Unit 1 Test Review Flashcards

1
Q

Cheryl is watching the weather forecast for an outdoor senior picnic project that she planned to determine whether the picnic will need to be moved indoors. Which project process stage is Cheryl in?

A

Monitoring and Controlling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Johnny is organizing all the specifics for his parents’ 50th anniversary party.
He has made contact with all the vendors, secured the location, and created a weather contingency plan. Johnny is participating in:

A

Project Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Petrina sets up a timeline for the financial project she has been assigned. In her timeline, she includes benchmarks and milestones for her team to help keep the project on track. Petrina is establishing good project:

A

Time Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Amy recently opened a business and realizes that she needs assistance with the multiple projects that her business is completing. Amy hires an accountant to manage all financial aspects of her projects. Which project management facilitating function is Amy practicing?

A

Human Resource

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

David is planning an outdoor college soccer tournament and is expecting one hundred teams to attend. On the morning of the tournament, he evaluates the weather to determine whether the tournament might need to be moved to the next day. David is evaluating the project:

A

Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Lisa is working with her school’s FBLA club to create a budget for the upcoming dance. She recently took classes in Accounting and Personal Finance. Which facilitating function is Lisa exhibiting?

A

Human Resource

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Andrew is deciding on the details of a community service event for his career technical service organization. He will lead his organization through all stages of the life cycle by the end of this school year. Andrew is assuming the role of a:

A

Project Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Bobby negotiated a discount on the delivery fees when he ordered additional tables and chairs for his event. Which facilitating function has Bobby exhibited?

A

Procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

After the prom, the student planning committee meets to discuss what activities went well and what activities would need to be changed next time.
What project management process stage is the committee in?

A

Closing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A project manager facilitates a two-way process that reaches a mutual understanding by the participants. The facilitating function the project manager is using is:

A

Communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Andrew is the prom committee chairman. He is at the prom and realizes that the meal delivered to the attendees was steak and not chicken. Andrew makes the catering manager aware immediately that the chicken meal was agreed upon, so the steak meal is outside the project scope. Which project management process stage is Andrew in?

A

Monitoring and Controlling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Tara is meeting with her stakeholders to determine the scope of work. What process stage is she in?

A

Initiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Sierra is working with her sisters to determine how much money they have spent on their parents’ anniversary party to calculate the funds remaining in their budget. What process stage is she in?

A

Initiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Joe holds a team meeting to discuss lessons learned. He is in which process stage?

A

Closing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Alison holds weekly project team meetings to determine whether she needs to crash any project activities to help keep the project on track. What process stage is she in?

A

Monitoring and Controlling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Sierra is visiting and calling venues to see who is available to host her parents’ anniversary party. What process stage is she in?

A

Executing

17
Q

Andrew is the prom committee chairman. He is on-site at the prom to make sure all vendors show up at the event and all vendors’ activities are falling within the scope of work contracted. Which process stage is Andrew in?

A

Executing

18
Q

The organizational structure in which the project manager has the greatest amount of authority is a:

A

Projectized Organization

19
Q

After a wedding, Christina meets with the newlyweds to deliver the photographs she took and get the customer’s signature and payment for the work done. Which process stage is Christina in?

A

Closing

20
Q

Paul is contacting a list of potential suppliers to request price quotes for a key project material. He is in which process stage?

A

Executing

21
Q

The ability of stakeholders to influence the project is typically highest at which stage?

A

Initiating

22
Q

Senior graduation commencement ceremonies close the large project of high school course work. The group development stage when the class is broken apart is called:

A

Adjourning

23
Q

Tony, a member of a project team, has been noticing that the team’s members have been establishing specific roles for each other, and the team is starting to achieve consensus about the group objective. Which stage of group development is Tony’s team experiencing?

A

Norming

24
Q

In the first week of soccer practice, two players got into an argument over how a play should be run. Both players returned the next day and worked out a compromise with their coach. The argument over how the play should be run represents which stage of group development?

A

Storming

25
Q

What type of organizational structure utilizes full-time project support staff?

A

Projectized Organization

26
Q

Amy and Diane work for an organization where the assigned project manager has total authority over the project. Amy and Diane work in a:

A

Projectized Organization

27
Q

Jenna is in charge of planning and leading a community blood drive. Jenna is considered the:

A

Project Manager

28
Q

Kacie and Sarah both work at the same high school. Kacie works in the CTE department and Sarah works in the Science department. Both Kacie and Sarah work only within their department, and each has a vice-principal she reports to. Kacie and Sarah work in a:

A

Functional Manager

29
Q

Lauren is a fashion director who is leading a magazine styling project. She assigns roles to her team of stylists, makeup/hair artists, and photographers.
Lauren is considered the:

A

Project Manager

30
Q

Linda is a project manager who works in an organization where her functional manager controls her budget and Linda has no authority over her projects. In which organizational structure does Linda work?

A

Functional Organization

31
Q

Prom, senior picnic, and graduation are examples of:

A

Projects

32
Q

The organizational structure where the project manager has the least amount of authority is a:

A

Functional Organization

33
Q

Karen is a mechanical engineer who reports to the mechanical engineering department lead, Mike. Nadine is a project manager in the company who needs a mechanical engineer to assist with certain tasks on her project. Mike transfers Karen to Nadine’s team for two months to complete the mechanical engineering tasks and then Nadine transfers Karen back to Mike’s team.
Which type of organization structure do Karen, Mike, and Nadine work in?

A

Matrix Organization

34
Q

Jeff is a science teacher and Celeste is a computer programming teacher at a high school. The school they work in allows them to co-teach lessons based » on their area of expertise. Their students are creating a program to anticipate the temperature based on measurements taken for an ecosystem prediction project. Jeff and Celeste work in which type of an organizational structure?

A

Matrix Organization

35
Q

Highly skilled and capable employees can be shared between projects in which type of organization structure?

A

Matrix Organization

36
Q

Renovating a kitchen, planning a vacation. and starting a school club are all examples of:

A

Projects

37
Q

An organization uses an assembly line to ensure that the execution of each project’s activities produces a quality product. The organizational function that supports this work would be:

A

Operations

38
Q

John and Steve work in a software development company. John is the project manager, and Steve is a staff member who reports to Tracy. John sends all project tasks for Steve through Tracy in a:

A

Functional Organization

39
Q

The manufacturing of a smartphone, taking notes in class, and working out daily are all examples of:

A

Operations