TS 3.5.3 ECCS - Operating Flashcards

1
Q

LCO 3.5.3
2 ECCS trains shall be OPERABLE

APPLICABILITY: ___

A

MODES 1 and 2

MODE 3 with PZR pressure > 1837 psia or with RCS Tc > 485F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The function of the ECCS is to provide core cooling and negative reactivity to ensure that the reactor core is protected after any of the following accidents:

a. ___
b. ___
c. ___
d. ___

A

a. LOCA
b. CEA ejection accident
c. Loss of secondary coolant accident, including uncontrolled steam release or loss of FW
d. SGTR

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The addition of negative reactivity is designed primarily for ___ because ___

A

…Loss of secondary coolant accident

…because primary cooldown could add enough positive reactivity to achieve criticality and return to significant power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

There are 2 phases of ECCS operation:
1 ___
2 ___

A
  1. Injection

2. Recirculation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Each ECCS train consists of ___ and ___

A

HPSI and LPSI subsystems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

LCO 3.5.3 helps to ensure that the following acceptance criteria, established by 10 CFR 50.46 for ECCSs, will be met following a LOCA:

a. ___
b. ___
c. ___
d. ___
e. ___

A

a. Max fuel element cladding temperature is < 2200F
b. Max cladding oxidation < .17 times total thickness
c. Max H2 generation from a Zirconium water reaction is < .01 times hypothetical if all metal were to react
d. Core maintained in coolable geometry
e. Adequate long term cooling capability maintained

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

LCO 3.5.3 also limits the potential for a post-trip return to power following a ___ and ensures that CTMT temp limits are met.

A

Steam Line Break (SLB)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

LCO 3.5.3 CONDITION

A. One LPSI subsystem inoperable.

A

A.1 Restore subsystem to OPERABLE status (7 days)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The availability of at least ___% of the ECCS flow equivalent to a single OPERABLE ECCS train is implicit in the definition of Condition A.

A

100%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

LCO 3.5.3 CONDITION
B. 1 or more trains inoperable for reasons other than Condition A.
AND
At least 100% of the ECCS flow equivalent to a single OPERABLE ECCS train available.

A

B.1 Restore train(s) to OPERABLE status (72 hours)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

An ECCS train is inoperable if ___

A

…it is NOT capable of delivering the design flow to the RCS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The intent of this Condition is to maintain a combination of OPERABLE equipment such that ___

A

…100% of the ECCS flow equivalent to 100% of a single OPERABLE train remains available.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

LCO 3.5.3 CONDITION

C. Required Action and associated Completion Time not met.

A
C.1 Be in MODE 3 (6 hours)
AND
C.2 Reduce PZR pressure to < 1837# (12 hours)
AND
C.3 Reduce Tcold to < 485F (12 hours)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Per SR 3.5.3.1, A valve that receives an actuation signal is allowed to be in a nonaccident position provided the valve auto repositions within ___

A

…the proper Stroke Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Per SR’s 3.5.3.4-6, the following valve actuations MUST be verified:
___

A

“on an actual or simulated RAS, the CTMT sump isolation valves open, and the HPSI, LPSI and CS minimum bypass recirculation flow line isolation valves and combined SI mini flow valve close.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly