Terms Flashcards

1
Q

Adaptive Life Cycle

A

The progression of project phases characterized by a willingness to embrace change and involving significant stakeholder interaction with a focus on the incremental release of work, typically every 2 to 4 weeks; uses fixed time and resources; also called agile.

Exam Tip of the Day #1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Confidentiality

A

The act of not providing certain confidential information to those who should not know about it.

Exam Tip of the Day #2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Path Convergence

A

A node on a network diagram that indicates the merger of parallel paths; distinguished by an activity with multiple predecessors.

Exam Tip of the Day #3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Market Research

A

The process of gathering information about customers or markets.

Exam Tip of the Day #4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Bar Chart

A

A graphical representation of schedule-related information. Typically, schedule activities or work breakdown structure components are displayed vertically on the far left of the chart, dates are displayed horizontally across the top of the chart, and activity durations are displayed as date-placed horizontal bars. Also see Gantt chart.

Exam Tip of the Day #5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Learning Curve Theory

A

A theory which states that the more of something that is produced, the lower the unit cost of it becomes due to an improvement in efficiency.

Exam Tip of the Day #6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Decision Tree Analysis

A

A technique used to assess possible responses to a threat or opportunity in order to make the best decision; it involves diagramming the options and notating the expected monetary value (EMV) potential of each option.

Exam Tip of the Day #7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Professional and Social Responsibility

A

Ethics expected in project managers; includes balancing stakeholder interests and reporting violations.

Exam Tip of the Day #8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Histogram

A

A graphical representation, in the format of bar chart, that depicts the central tendency, dispersal, and shape of a statistical distribution.

Exam Tip of the Day #9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Tight Matrix

A

A phrase that describes a war room or close environment for the team; can also be used as a distracter answer on organizational-related questions.

Exam Tip of the Day #10

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Status Report

A

A report that states the current shape or state of the project to date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Change Log

A

A list of proposed project modifications and their associated details including description, date, requestor, and status.

Exam Tip of the Day #12

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Investment Power

A

A type of power that involves delaying key decision(s) so enough time passes that stakeholders or other such parties can make a significant time investment in the project.

Exam Tip of the Day #13

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Work Performance Information

A

The evaluation and integration of project execution statistics and measurements gathered from control processes.

Exam Tip of the Day #14

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Phase Gate

A

A review which is conducted at the end of a phase to decide if the project should continue to the next phase, if the project should continue to the next phase with modification, or if the project or program should be terminated.

Exam Tip of the Day #15

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Issue Log

A

A project document that tracks elements that cause stakeholder concern or dissension.

Exam Tip of the Day #16

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Risk Tolerance

A

The level of risk that an individual or organization is willing to permit; also known as risk utility.

Exam Tip of the Day #18

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Context Diagrams

A

A graphical representation of the scope of a business system that includes processes, equipment, and computer systems and indicates the manner in which people and other systems interact with the business system.

Exam Tip of the Day #19

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Business Case

A

A document that attempts to prove the economic feasibility of a business idea, such as a product or service, to justify the project.

Exam Tip of the Day #20

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Development Approach

A

The method (predictive, iterative, incremental, agile, or hybrid) utilized during the project life cycle to produce and elaborate the product, service, or result of the project.

Exam Tip of the Day #21

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Work Package

A

The smallest level of WBS work for which cost and time can be assessed and administered.

Exam Tip of the Day #22

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Mirroring

A

Matching behavior characteristics of another person or group.

Exam Tip of the Day #24

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Project Life Cycle

A

The phases, from initiation through closure, of a project associated with the work of the project, as opposed to being associated with its project management.

Exam Tip of the Day #25

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Update

A

A modification to any deliverable, project management plan component, or project document that has not been subjected to the formal change control process.

Exam Tip of the Day #26

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Validation

A

The process of determining that the results of the project are in compliance with requirements imposed by the customer and appropriate stakeholders and typically involving acceptance by them.

Exam Tip of the Day #27

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Plurality

A

The votes of the largest block in a group when a majority is not required, typically used to denote agreement with a decision.

Exam Tip of the Day #28

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Crashing

A

A compression technique to shorten the duration of the schedule, typically by adding additional resources to critical path activities.

Exam Tip of the Day #29

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Float

A

The amount of time an activity can be delayed without delaying successor activities or the project completion date.

Exam Tip of the Day #30

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Variation

A

The difference between the baseline and actual project data at a specific point in time.

Exam Tip of the Day #31

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Closed Procurements

A

The written formal notification, from the buyer to the seller, that the contract has been completed; typically completion is dependent on the seller meeting the terms and conditions of the contract.

Exam Tip of the Day #32

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Fixed Price Contract

A

A mutually binding agreement that compensates the seller for goods or services on the basis of a fixed amount identified in the agreement, notwithstanding the seller’s costs.

Exam Tip of the Day #33

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Project Calendar

A

A calendar that indicates working days and shifts available for project activities.

Exam Tip of the Day #34

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Sunk Cost

A

Money that has already been spent on a project; should not be considered when selecting or evaluating a project.

Exam Tip of the Day #35

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Quality Report

A

A project document that addresses quality management issues, recommendations for corrective actions, and a recap of findings from quality control activities; the report may include advice related to the improvement of process, project, and product.A mutually binding agreement that compensates the seller for goods or services on the basis of a fixed amount identified in the agreement, notwithstanding the seller’s costs.

Exam Tip of the Day #36

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Risk Owner

A

The person responsible for the monitoring of a risk and for the determination and implementation of an appropriate risk response strategy.

Exam Tip of the Day #37

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Task

A

An activity to be completed on the project.

Exam Tip of the Day #38

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Schedule Baseline

A

The authorized version of the schedule model that is used as the basis for comparison and can only be modified through a formal change control procedure.

Exam Tip of the Day #39

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Cost Aggregation

A

Adding together the work package cost estimates for high-level WBS components, including control accounts, for the purpose of establishing the value of the total project or the control account work.

Exam Tip of the Day #40

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Earned Value (EV)

A

The value of the work that has been completed as of a specific point in time calculated by multiplying the completion percent of activity by its planned value, then adding the results; also known as the budgeted cost of work performed (BCWP).

Exam Tip of the Day #41

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Quality

A

The degree to which a group of fundamental characteristics satisfies requirements.

Exam Tip of the Day #43

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Control Chart

A

A graphic representation of process data over time that is set against documented control limits and has a center line (mean) to assist in identifying trends.

Exam Tip of the Day #42

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Quality

A

The degree to which a group of fundamental characteristics satisfies requirements.

Exam Tip of the Day #43

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Attitude Power

A

A type of power that can involve using a middle person to negotiate for the project manager.

Exam Tip of the Day #44

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Team Management Plan

A

A component of the resource management plan that delineates the manner and timing in which team members are acquired and released.

Exam Tip of the Day #45

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

Risk Power

A

A type of power that uses calculated risks in negotiations to achieve project goals.

Exam Tip of the Day #46

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Execute

A

Perform the tasks of the project management plan, create the project deliverables, and generate work performance information.

Exam Tip of the Day #47

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Intellectual Property

A

Ideas and concepts created by an individual or company, typically eligible for copyright or patent, thus providing ownership properties.

Exam Tip of the Day #48

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Monitor and Control Project Work

A

The process of monitoring, evaluating, and governing performance progress as detailed in accordance with the project management plan.

Exam Tip of the Day #49

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Plan Schedule Management
(Schedule Process - Primary Function)

A

Provides “how to” direction to the team regarding schedule management and produces the Schedule Management Plan.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

Define Activities
(Schedule Process - Primary Function)

A

Decomposes the scope of the project into project schedule
activities.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

Sequence Activities
(Schedule Process - Primary Function)

A

Sequences the activities to optimize the schedule.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Estimate Activity Durations
(Schedule Process - Primary Function)

A

Estimates the timeframes required to complete the schedule activities.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

Develop Schedule
(Schedule Process - Primary Function)

A

Creates the project schedule and the schedule baseline.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

Control Schedule
(Schedule Process - Primary Function)

A

Maintains and controls the schedule baseline.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

Lead
(Schedule)

A

The amount of time a successor activity can be advanced with respect to the controlling predecessor. It is represented by a (-).

In a network diagram the Successor activity is the one that moves relative to the predecessor.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

Lag
(Schedule)

A

The amount of time a successor activity is delayed with respect to the Controlling predecessor. It is represented by a (+).

In a network diagram the Successor activity is the one that moves relative to the predecessor.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

Plan Cost Management
(Cost Process - Primary Function)

A

Provides “how to” direction to the team regarding cost management and produces the Cost Management Plan.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

Estimate Costs
(Cost Process - Primary Function)

A

Estimates the costs required to achieve the project objectives.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

Determine Budget
(Cost Process - Primary Function)

A

Develops a budget for the project and the Cost Baseline.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

Control Costs
(Cost Process - Primary Function)

A

Maintains and controls the cost baseline.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

Plan Resource Management
(Resource Process - Primary Function)

A

Provides “how to” direction to the team regarding resource management and produces the Resource Management Plan.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

Estimate Activity Resources
(Resource Process - Primary Function)

A

Estimates the resources required for the project based on schedule activities.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

Acquire Resources
(Resource Process - Primary Function)

A

Acquires both human and physical resources for the project.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

Develop Team
(Resource Process - Primary Function)

A

Ensures team develops to be able to perform the work of the
project.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

Manage Team
(Resource Process - Primary Function)

A

Manages the project team resources.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

Control Resources
(Resource Process - Primary Function)

A

Monitors planned resource usage and initiates changes, if required.

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

Stakeholder Register

A

A project document that lists stakeholder information including name, role, assessment, and classification.

Exam Tip of the Day #50

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Plan Risk Management

A

The process of determining the methods that will be used to execute project risk management activities.

Exam Tip of the Day #51

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

Communication Technology

A

The tools, systems, and computer applications utilized in the dissemination of information to project stakeholders.

Exam Tip of the Day #52

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

Network Diagram

A

A schematic of logical relationships that make up the flow of activities on the project; always drawn from left to right.

Exam Tip of the Day #53

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

Time and Material Contract (T&M)

A

A mutually binding agreement that compensates the seller for goods or services on the basis of fixed hourly rates for labor and the actual costs of materials; represents a composite of a cost-reimbursable contract (cost of materials can rise) and a fixed-price contract (labor cost are agreed on by buyer and seller before the start of the contract).

Exam Tip of the Day #54

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

Project Procurement Management

A

The processes required to purchase or acquire any products, services, or results from a source outside of the project team.

Exam Tip of the Day #55

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

Sam and Tracy are running their string theory project. They are in the process of monitoring project communications with the various stakeholders. This has been a challenge given it is a global project with many virtual employees. Which of the following is a tool and technique they will use with the monitor communications process?

(A) Communications management plan
(B) Change requests
(C) Work performance information
(D) Project management information system

A

Correct Answer: (D) Project management information system

Explanation: The tools and and techniques for the Monitor Communications process are: expert judgment, project management information systems, data analysis, stakeholder engagement assessment matrix, interpersonal and team skills, observation/conversation, and meetings.

Exam Tip of the Day #56

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

Agreements

A

A document or communication that defines the intentions of a project; examples include a contract, a memorandum of understanding (MOU), and letters of agreement.

Exam Tip of the Day #56

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

Root Cause Analysis

A

An analytical technique used to ascertain the fundamental reason a variance, defect, or risk exists.

Exam Tip of the Day #57

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

Fallback Plan

A

The plan that will supersede the original plan if it is not effective.

Exam Tip of the Day #58

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

Process

A

An ordered series of activities executed to create a product, result, service, or output.

Exam Tip of the Day #59

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

Project Phase

A

An aggregation of logically related activities that results in the completion of a deliverable or deliverables.

Exam Tip of the Day #60

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

Develop Project Charter

A

The process of evolving the document that authorizes the project and authorizes the project manager to employ organizational resources to do the work of the project.

Exam Tip of the Day #61

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

Enterprise

A

A company, business, or other formal structure that encompasses a business function.

Exam Tip of the Day #62

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

Plan Communications Management
(Communications Process)

A

Primary Function: Provides “how to” direction to the team regarding communications and produces the Communications Management Plan.

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

Manage Communications
(Communications Process)

A

Primary Function: Implements the communications management plan.

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

Monitor Communications
(Communications Process)

A

Primary Function: Monitors effectiveness of communications and makes adjustments, as necessary.

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

Communications Channels Formula

A

CC = [n * (n – 1)] / 2

CC = Communications Channel
n = number of people

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

Communications Planning
(Steps)

A

1) Determine who? (from Stakeholder register)
2) Identify communication needs of all stakeholders.
3) Determine methods (push, pull or interactive).
4) Review OPAs (lessons learned, historical info, templates).
5) Identify challenges.
6) Develop a communications plan.
7) Approve and publish the plan.

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

Managing Communications

A

▪ Implement the communications management plan
▪ Confirm communications is effective and feedback is received
▪ Monitor communications and make adjustments, as necessary
▪ Be alert to stakeholder adds or changes
▪ Changes to other aspects of the project may impact communications
(e.g., scope change)

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

Quality is…
(Concept)

A

“conformance to requirements or specifications.”

“The degree to which a set of inherent characteristics fulfill requirements”

  • Emphasis on Prevention over Inspection
  • Continuous Improvement
  • Management Responsibility
  • Conformance to Requirements & Fitness for Use
  • Keep Failures out of the Process / Keep failures out of the hands of the Customer

Q = Quality of the Product + Quality of the Project

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

Plan Quality
(Quality Concept)

A

Key Inputs:
- Project Charter
- Quality Policies
- Project Plan
- Process Assets

Output:
- Quality Management Plan

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

Manage Quality
(Quality Concept)

A

Process Focused

Key Outputs:
- Test & Eval Docs
- Quality Reports
- Process Improvement
- Change Requests

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

Control Quality
(Quality Concept)

A

Product Focused

Key Outputs:
- Verified Deliverables
- Quality Measurements
- Change Requests

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

Team Members
(Key Concept - Quality Responsibilities)

A

Responsible for the quality of their own work.

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

Project Manager
(Key Concept - Quality Responsibilities)

A

Responsible for the quality standards on the project.

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

Senior/Executive Management
(Key Concept - Quality Responsibilities)

A

Responsible for the quality standards at the company.

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

Grade versus Quality
(Quality - Key Concept)

A

▪ Grade is the category assigned to products or results to indicate similar functionality but different technical specifications. More functions/features = higher grade.

▪ Quality is defined as the degree to which a set of inherent characteristics fulfill requirements.

▪ Low or poor quality is always a problem, but low grade is not necessarily a problem.

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

5 levels of Quality Management
(Quality - Key Concept)

A

▪ Least effective: customers find the defects, leads to litigation, recalls, warranty issues, etc.

▪ Fix defects before they get to the customer; high appraisal and rework costs

▪ Use Quality Assurance (QA) to adjust the processes, not just repair defects

▪ Incorporate quality into planning and design

▪ Most effective: build a quality culture throughout the organization

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

Quality
(Key Documents)

A

▪ Quality Management Plan (from Plan Quality Management)

▪ Test and evaluation documents (from Manage Quality)

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

Plan Quality Management
(Quality Process)

A

Primary Function: Provides “how to” direction to the team regarding quality and produces the Quality Management Plan.

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

Manage Quality
(Quality Process)

A

Primary Function: Implements the quality management plan and provides ongoing
management of quality.

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

Control Quality
(Quality Process)

A

Primary Function: Verifies the quality of deliverables.

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

Quality Management Plan

A

▪ Describes how the quality policy will be implemented
▪ Provides input to the overall project plan

▪ Contains
̶ Quality policy
̶ Organizational structure
̶ Responsibilities
̶ Processes and procedures
̶ Metrics
̶ Resources needed to implement

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

Quality Tools - Quality Audits

A
  • Structured and independent audit of quality policies, processes and procedures
  • Can be scheduled or random
  • Usually conducted by a team external to the project (PMO or external group)

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

Cost Management Plan

A

▪ The Cost Management Plan describes how the project costs will be planned, estimated, structured, and controlled.

▪ Components
- Units of measurement
- Level of precision
- Level of accuracy
- Links to cost procedures
- Thresholds
- Performance measurements
- Reporting formats

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

Estimate Costs - Expert Judgement

A

▪ Experts can be individuals or groups

▪ Knowledge of internal cost processes

▪ Specialized knowledge in industry, discipline and cost estimating techniques

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

Estimate Costs – Analogous Cost Estimating

A
  • Estimating using historical costs of similar projects
  • Also known as top-down estimating
  • Expert judgment can help validate the estimate
  • Less time consuming and costly but less accurate
  • More reliable if previous projects are very similar to current project and project team members have the needed expertise

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
105
Q

Estimate Costs – Parametric Cost Estimating

A
  • Uses statistical relationship between historical data and other variables
  • Can produce higher levels of accuracy depending upon the sophistication and underlying data built into the model
  • Examples of parametric measures are:
    ▪ Square footage used in construction
    ▪ Electrical cabling priced by linear foot
    ▪ Highway construction by the mile

Rice Class 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
106
Q

Quality Tools – Statistical Sampling

A

Statistical Sampling - Small sample from a group can project what the total group will be like.

Advantages:
- Less product damage
- Quicker decisions
- Fewer inspection errors

Disadvantages:
- Unrepresentative sample
- Less information

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

Quality - Exam Tips

A

▪ Know the value of the quality management plan
▪ Know that manage quality is a continuous process and the umbrella for continuous improvement
▪ Understand how to use quality tools
▪ Know that control quality also validates approved changes
▪ Know the difference between manage quality and control quality
▪ Know the difference between control quality and validate scope

Control Quality ➔ Verified deliverables ➔ Validate Scope ➔ Accepted deliverables

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

3 Components of Risk / Score

A

The Event
Impact
Probability

Risk Score: R = I * P

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

Realized Risk

A
  • A risk threat or opportunity that has actually occurred
  • A realized negative risk is often called an issue

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

Risk – Key Documents

A

▪ Risk Management Plan (output from “Plan Risk Management”)
▪ Risk Register (output from “Identify Risks”, iteratively developed)
▪ Risk Report (output from “Identify Risks”, iteratively developed)

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

Plan Risk Management
(Risk Process)

A

Primary Function: Provides “how to” direction to the team regarding risk management and produces the Risk Management Plan.

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
112
Q

Identify Risks
(Risk Process)

A

Primary Function: Identify the risks to project objectives and create the initial risk register.

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
113
Q

Perform Qualitative Analysis
(Risk Process)

A

Primary Function: Rank risks and update the risk register.

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
114
Q

Perform Quantitative Analysis
(Risk Process)

A

Primary Function: Analyze high priority risks and assess probability of achieving project objectives. Update the risk register.

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
115
Q

Plan Risk Responses
(Risk Process)

A

Primary Function: Develop risk responses and update the risk register.

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
116
Q

Implement Risk Responses
(Risk Process)

A

Primary Function: Implement the planned risk responses.

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
117
Q

Monitor Risks
(Risk Process)

A

Primary Function: Monitor risks throughout the project duration, updating the risk register and initiating changes to the plan as needed

Rice Class 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
118
Q

Non-disclosure Agreement (NDA)

A

A document signed by the owner of intellectual property and those who view it when it is not generally exposed to the public, or if it is a new idea, before it is displayed to the public.

Exam Tip of the Day #63

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
119
Q

Team Charter Components

A
  • Team Values
  • Communication Guidelines
  • Decision-Making Criteria
  • Conflict Resolution
  • Meeting Guidelines
  • Team Agreements

Brain Dump - Rice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
120
Q

Knowledge Areas - 10

A
  1. Integration Management (7)
  2. Scope Management (6)
  3. Schedule Management (6)
  4. Cost Management (4)
  5. Quality Management (3)
  6. Resource Management (6)
  7. Communications Management (3)
  8. Risk Management (7)
  9. Procurement Management (3)
  10. Stakeholder Management (4)

Brain Dump - Rice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
121
Q

Process Groups - 5

A
  1. Initiating (2)
  2. Planning (24)
  3. Executing (10)
  4. Monitoring & Controlling (12)
  5. Closing (1)

Brian Dump - Rice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
122
Q

Initiating - 2
(Process Group)

A
  1. Develop Project Charter
  2. Identify Stakeholders

Brain Dump - Rice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
123
Q

Planning - 24
(Process Group)

A
  1. Develop Project Management Plan
  2. Plan Scope Management
  3. Collect Requirements
  4. Define Scope
  5. Create WBS
  6. Plan Schedule Management
  7. Define Activities
  8. Sequence Activities
  9. Estimate Activity Durations
  10. Develop Schedule
  11. Plan Cost Management
  12. Estimate Costs
  13. Determine Budget
  14. Plan Quality Management
  15. Plan Resource Management
  16. Estimate Activity Resources
  17. Plan Communications Management
  18. Plan Risk Management
  19. Identify Risks
  20. Perform Qualitative Analysis
  21. Perform Quantitative Analysis
  22. Plan Risk Responses
  23. Plan Procurement Management
  24. Plan stakeholder Engagement

Brain Dump - Rice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
124
Q

Executing - 10
(Process Group)

A
  1. Direct and Manage Project Work
  2. Manage Project Knowledge
  3. Manage Quality
  4. Acquire Resources
  5. Develop Team
  6. Manage Team
  7. Manage Communications
  8. Implement Risk Responses
  9. Conduct Procurements
  10. Manage Stakeholder Engagement

Brain Dump - Rice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
125
Q

Monitoring & Controlling - 12
(Process Group)

A
  1. Monitor & Control Project Work
  2. Perform Integrated Change Control
  3. Validate Scope
  4. Control Scope
  5. Control Schedule
  6. Control Costs
  7. Control Quality
  8. Control Resources
  9. Monitor Communications
  10. Monitor Risks
  11. Control Procurement
  12. Monitor Stakeholder Engagement

Brain Dump - Rice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
126
Q

Closing - 1
(Process Group)

A
  1. Close Project or Phase

Brain Dump - Rice

127
Q

Integration Management - 7
(Knowledge Area)

A
  1. Develop Project Charter (I)
  2. Develop Project Management Plan (P)
  3. Direct and Manage Project Work (E)
  4. Manage Project Knowledge (E)
  5. Monitor and Control Project Work (M&C)
  6. Perform Integrated Change Control (M&C)
  7. Close Project or Phase (C)

Brain Dump - Rice

128
Q

Scope Management - 6
(Knowledge Area)

A
  1. Plan Scope Management (P)
  2. Collect Requirements (P)
  3. Define Scope (P)
  4. Create WBS (P)
  5. Validate Scope (M&C)
  6. Control Scope (M&C)

Brain Dump - Rice

129
Q

Schedule Management - 6
(Knowledge Area)

A
  1. Plan Schedule Management (P)
  2. Define Activities (P)
  3. Sequence Activities (P)
  4. Estimate Activity Durations (P)
  5. Develop Schedule (P)
  6. Control Schedule (M&C)

Brain Dump - Rice

130
Q

Cost Management - 4
(Knowledge Area)

A
  1. Plan Cost Management (P)
  2. Estimate Costs (P)
  3. Determine Budget (P)
  4. Control Costs (M&C)

Brain Dump - Rice

131
Q

Quality Management - 3
(Knowledge Area)

A
  1. Plan Quality Management (P)
  2. Manage Quality (E)
  3. Control Quality (M&C)

Brain Dump - Rice

132
Q

Resource Management - 3
(Knowledge Area)

A
  1. Plan Resource Management (P)
  2. Estimate Activity Resources (P)
  3. Acquire Resources (E)
  4. Develop Team (E)
  5. Manage Team (E)
  6. Control Resources (M&C)

Brain Dump - Rice

133
Q

Communications Management - 3
(Knowledge Area)

A
  1. Plan Communications Management (P)
  2. Manage Communications (E)
  3. Monitor Communications (M&C)

Brain Dump - Rice

134
Q

Risk Management - 7
(Knowledge Area)

A
  1. Plan Risk Management (P)
  2. Identify Risks (P)
  3. Perform Qualitative Analysis (P)
  4. Perform Quantitative Analysis (P)
  5. Plan Risk Responses (P)
  6. Implement Risk Responses (E)
  7. Monitor Risks (M&C)

Brain Dump - Rice

135
Q

Procurement Management - 3
(Knowledge Area)

A
  1. Plan Procurement Management (P)
  2. Conduct Procurements (E)
  3. Control Procuremenents (M&C)

Brain Dump - Rice

136
Q

Stakeholder Management - 4
(Knowledge Area)

A
  1. Identify Stakeholders (I)
  2. Plan Stakeholder Engagement (P)
  3. Manage Stakeholder Engagement (E)
  4. Monitor Stakeholder Engagement (M&C)

Brain Dump - Rice

137
Q

Team Charter Components

A
  1. Team Values
  2. Communication Guidelines
  3. Decision-Making Criteria
  4. Conflict Resolution
  5. Meeting Guidelines
  6. Team Agreements

Brain Dump - Rice

138
Q

Integration
Key Process Documents

A
  1. Project Charter
  2. Assumption Log
  3. Project Management Plan
  4. Change Management Plan
  5. Compliance Management Plan
  6. Issue Log
  7. Lessons Learned Register
  8. Work Performance Reports
  9. Final Report

Brain Dump - Rice

139
Q

Scope
Key Process Documents

A
  1. Scope Management Plan
  2. Requirements Management Plan
  3. Project Scope Statement
  4. Scope Baseline

Brain Dump - Rice

140
Q

Schedule
Key Process Documents

A
  1. Schedule Management Plan
  2. Schedule Baseline
  3. Project Schedule

Brain Dump - Rice

141
Q

Cost
Key Process Documents

A
  1. Cost Management Plan
  2. Cost Baseline
  3. Funding Limits

Brain Dump - Rice

142
Q

Quality
Key Process Documents

A
  1. Quality Management Plan

Brain Dump - Rice

143
Q

Resource
Key Process Documents

A
  1. Resource Management Plan
  2. Team Charter
  3. RBS

Brain Dump - Rice

144
Q

Communications
Key Process Documents

A
  1. Communications Management Plan
  2. Project Communications

Brain Dump - Rice

145
Q

Risk
Key Process Documents

A
  1. Risk Management Plan
  2. Risk Register
  3. Risk Report

Brain Dump - Rice

146
Q

Procurement
Key Process Documents

A
  1. Procurement Management Plan
  2. Contracts

Brain Dump - Rice

147
Q

Stakeholder
Key Process Documents

A
  1. Stakeholder Register
  2. Stakeholder Engagement Plan

Brain Dump - Rice

148
Q

Scrum Key Points - 5

A
  1. 3 Pillars
  2. 5 Core Values
  3. 3 Roles
  4. Ceremonies
  5. Artifacts

Brain Dump - Rice

149
Q

3 Pillars
(Scrum Key Point - 1)

A
  1. Transparency
  2. Inspection
  3. Adaptation

Brain Dump - Rice

150
Q

5 Core Values
(Scrum Key Point - 2)

A
  1. Focus
  2. Courage
  3. Commitment
  4. Openness
  5. Respect

Brain Dump - Rice

151
Q

3 Roles
(Scrum Key Point - 3)

A
  1. Product Owner
  2. ScrumMaster
  3. Team

Brain Dump - Rice

152
Q

Ceremonies
(Scrum Key Point - 4)

A
  1. Release Planning
  2. Sprint Planning
  3. Daily Scrum
  4. Sprint Review
  5. Sprint Retrospective

Brain Dump - Rice

153
Q

Artifacts
(Scrum Key Point - 5)

A
  1. Product Backlog
  2. Sprint Goal
  3. Sprint Backlog
  4. Blocks List
  5. Product Increment

Brain Dump - Rice

154
Q

Story Format

A

As a …persona - who?
I want… something - what?
So that… some outcome is achieved - why?

Brain Dump - Rice

155
Q

Policy

A

A course of action adopted by an organization to facilitate operational and project work.

Exam Tip of the Day #64

156
Q

Law

A

A standard created by local, state, or national governmental authority that requires compliance and often carries penalties for non-compliance.

Exam Tip of the Day #65

157
Q

Project Management Knowledge Area

A

A recognized project management area that is qualified by its component practices, processes, inputs, outputs, tools, and techniques and delineated by its knowledge requisites.

Exam Tip of the Day #66

158
Q

Skill

A

The capability to execute project-related activities based on individual subject matter expertise and abilities.

Exam Tip of the Day #67

159
Q

Copyright

A

The legal protection of the ownership rights to a creative work such as literature, software, music, art, as well as the physical or electronic media containing the creative work.

Exam Tip of the Day #68

160
Q

Assumptions Analysis

A

The evaluation of project assumptions used to determine the risks that could be incurred as a result of the inexact, fragmentary, or unpredictable nature of the assumptions.

Exam Tip of the Day #69

161
Q

Stakeholder Engagement Plan

A

The document, part of the project or program management plan, used to depict all processes, procedures, tools, and techniques that will be used to effectively involve stakeholders in project determinations and performance based on the stakeholders’ requirements, concerns, and potential impact.

Exam Tip of the Day #70

162
Q

Risk Management Plan

A

Risk Management Plan: describes how risk management will be structured
and performed on the project.

Components:
̶ Methodology to perform risk management on the project
̶ Roles and responsibilities of risk management team members
̶ Budgeting
̶ Timing of risk activities
̶ Categories : Systematic way of identifying risks to a consistent level of detail
̶ Risk Breakdown Structure: Hierarchically organized representation of identified project risks
̶ Probability definitions
̶ Impact definitions
̶ Probability and Impact matrix
̶ Risk tolerances
̶ Risk thresholds
̶ Reporting formats
̶ Project document tracking

Rice Class 9

163
Q

Steps to Building a Risk Register

A

Process is Iterative.

  • Identify risks
  • Assess Risks: Qualitative analysis (ranking) & Quantitative analysis
  • Plan risk responses

Rice Class 9

164
Q

Quantitative Risk Analysis

A

Evaluate the combined effect of risk
̶ Determines measurable impact of each risk
̶ Provides insight into the combination effects of risk
̶ Contributes to assessment of overall project risk
̶ Focuses strategy for development of appropriate responses

Rice Class 9

165
Q

Expected Monetary Value (EMV)

A

Formula: EMV = I ($) x P

Example: Impact of Contractor delay is $10K; Probability is 50%

EMV = -$10K x .5 = -$5K

166
Q

Plan Risk Responses

A

Negative
- Avoid - choose something else or not to do it
- Transfer - such as with insurance
- Mitigate - lower your probability or impact by doing something

Positive Risks
- Exploit - you try to make it happen
- Share - opportunity to share by partnering (such as joint venture)
- Enhance - do somethign to improve the scores

Neutral:
- Escalate
- Accept - passive and active (team is actively doing something to accept)

167
Q

Risk Adjusted Backlog

A

▪ Agile iterative approach allows risks to be managed early
▪ Risk responses can be prioritized against business features or
stories
▪ Risk response work can be valued using the EMV concept

▪ Example of EMV of a risk:
Monetized impact is $10,000
Probability is 50%
EMV is $5,000 ($10,000 x 50%)

Rice Class 9

168
Q

Risk Based Spike

A

▪ Short proof of concept used to investigate an issue
▪ An experiment
▪ If successful, reduces or eliminates risk
▪ Can be used to evaluate options
▪ Considered “throw-away” work

Rice Class 9

169
Q

Monitor Risk

A

▪ Ongoing process
▪ Monitor the usage of contingency reserve
▪ Update the risk register as needed
▪ New risks may initiate a need for a change to the project plan

Rice Class 9

170
Q

Contract

A

A legal document between the buyer and the seller that represents a mutually binding agreement obligating the seller to provide specified products, services, or results, and obligating the buyer to provide monetary or other valuable consideration in return.

Rice Class 10

171
Q

Procurement Contract

A

̶ Terms and conditions
̶ Incorporate other items that the buyer specifies, such as special provisions
̶ To establish what the seller is to perform or provide

A contract means it’s subjected to a more extensive approval process.

Rice Class 10

172
Q

Procurement Management

A

▪ Can and usually is carried out by a specific procurement department
▪ Addresses the contract management and change control processes required to develop and administer contracts
▪ Builds upon and extends other processes

Rice Class 10

173
Q

Seller
(Procurement Management)

A

Manages the work as a project.

Seller = contractor, subcontractor, vendor, service provider, supplier

Rice Class 10

174
Q

Buyer
(Procurement Management)

A

Becomes the customer and becomes a key stakeholder.

Buyer = client, customer, prime contractor, contractor, acquiring organization, governmental agency, service requestor, or purchaser

Unless otherwise stated, the exam will reference all procurement
questions from the BUYER’S perspective

Rice Class 10

175
Q

Procurement
Key Document

A

Procurement Management Plan
(from Plan Procurement Management)

Rice Class 10

176
Q

Plan Procurement Management
(Procurement Process)

A

Primary Function: Provides “how to” direction to the team regarding procurement
management and prepares the team to evaluate proposals.

Rice Class 10

177
Q

Conduct Procurements
(Procurement Process)

A

Primary Function: Analyze proposals, select sellers and award contracts.

Rice Class 10

178
Q

Control Procurements
(Procurement Process)

A

Monitor and control performance of contracts.

Rice Class 10

179
Q

Procurement Planning

A

▪ Determine whether to acquire outside support:
̶ What to acquire
̶ How to acquire it
̶ How much is needed
̶ When to acquire it

▪ Consideration of potential sellers
▪ Project schedule can influence procurement strategy
▪ Decide to “make or buy” (make-or-buy decisions)
▪ Consider the risks involved in make-or-buy decisions
▪ Develop the Statement of Work (SOW) - define work of Seller
▪ Determine bid documents to be used
▪ Define source selection criteria
▪ Define procurement strategy
▪ Determine if independent cost estimates will be used

▪ Leverage OPAs:
̶ Pre-qualified vendors list
̶ Lessons learned
̶ Procurement processes
̶ Historical information

Rice Class 10

180
Q

SOW
(Statement of Work)

A

▪ A Statement of Work is the part of the contract that describes what the seller will do for the buyer

▪ When the Statement of Work is done or completed, the main work of the project is done and closing can begin

▪ Because the level of detail and planning can vary among contracts, you can take two different approaches to develop the Statement of Work in them contract:
1. Design
2. Functionality

Rice Class 10

181
Q

Enterprise Environmental Factors

A

Internal and external variables, not under the control of the project team, that impact the project.

Exam Tip of the Day #71

182
Q

Stakeholder Analysis

A

A technique by which quantitative and qualitative information is amassed and evaluated to determine whose interests should be considered throughout the project.

Exam Tip of the Day #72

183
Q

Explicit Knowledge

A

Knowledge that can be classified utilizing such symbols as words, numerals, and images.

Exam Tip of the Day #73

184
Q

Lessons Learned

A

The knowledge of what worked and what didn’t work during a project.

Exam Tip of the Day #75

185
Q

Stakeholder

A

Any person or entity that may impact, be impacted by, or perceive itself to be impacted by any decision, activity, or outcome of the project.

Exam Tip of the Day #74

186
Q

Termination Clause

A

A clause in the contract that allows both the buyer and the seller to end the contract.

Exam Tip of the Day #76

187
Q

Work Authorization

A

The authorization to begin work on an activity, work package, or control account at the correct time, by the correct entity, and in the correct progression.

Exam Tip of the Day #77

188
Q

Procurement Strategy

A

The buyer’s approach to determining the project delivery method and the class of legally binding agreement(s) that will be used to deliver the desired results.

Exam Tip of the Day #78

189
Q

Work Performance Data

A

Measurements or statistics related to the execution of project work.

Exam Tip of the Day #79

190
Q

Incentive Fee

A

An amount paid, in addition to the contract amount, for exceeding expectations, particularly in the areas of cost, schedule, or technical performance.

Exam Tip of the Day #80

191
Q

Scheduling Tool

A

A tool that accelerates scheduling by automatically producing activity start and finish dates based on the entry of activities, relationships, resources, and durations.

Exam Tip of the Day #81

192
Q

Control Costs

A

The process of observing project status in order to revise project costs and administer cost baseline revisions.

Exam Tip of the Day #82

193
Q

Affinity Diagram

A

A tool used to gather ideas and organize them into groupings so they can be reviewed and analyzed; typically used for ideas generated from brainstorming sessions.

Exam Tip of the Day #83

194
Q

Interpersonal Skills

A

The abilities that maximize the establishment and maintenance of relationships with project stakeholders; examples include the ability to communicate clearly, to motivate others, and to effectively negotiate; also known as soft skills.

Exam Tip of the Day #84

195
Q

Executing Process Group

A

The processes performed to achieve the work detailed in the project management plan in order to meet the requirements delineated in the project specifications per the work identified in the project management plan.

Exam Tip of the Day #85

196
Q

Business Value

A

An abstraction that includes tangible and intangible elements associated with project, program, and portfolio management that maximize the value to the organization.

Exam Tip of the Day #86

197
Q

Brainstorming

A

A creative technique used to gather a large amount of information from team members and/or subject matter experts; applicable to ideas, risk identification, and solutions.

Exam Tip of the Day #87

198
Q

Activity Resource Requirements

A

The determination of required resources for each work package and work period that are derived from the determination of required resources for each activity within the work package.

Exam Tip of the Day #88

199
Q

Code of Accounts

A

The numbering system used to distinguish constituents of the WBS.

Exam Tip of the Day #89

200
Q

Checksheets

A

A sheet that can be used as a checklist when gathering data.

Exam Tip of the Day #90

201
Q

Colocation

A

A technique for improving team effectiveness, as well as communication and collaboration among team members, by placing them in close proximity to each other.

Exam Tip of the Day #91

202
Q

Communication Infrastructure

A

Tools and techniques used to create the foundation for information transfer on a project.

Exam Tip of the Day #92

203
Q

Document Analysis

A

The evaluation of current documentation related to project risk.

Exam Tip of the Day #93

204
Q

Stakeholder

A

Any person or entity that may impact, be impacted by, or perceive itself to be impacted by any decision, activity, or outcome of the project.

Exam Tip of the Day #95

205
Q

Inappropriate Compensation

A

Money or other items of value that are “earned” via improper activities.

Exam Tip of the Day #96

206
Q

Functional Manager

A

A manager of any unit that creates a product or executes a service; also known as a line manager.

Exam Tip of the Day #97

207
Q

Change

A

A modification to any deliverable, project management plan component, or project document subject to the formal change control process.

Exam Tip of the Day #98

208
Q

Claim

A

A demand, under the terms of the contract, for consideration by the buyer from the seller or the seller from the buyer.

Exam Tip of the Day #94

209
Q

Collect Requirements

A

The process of arranging for, determining, and documenting the needs of the stakeholders to align with project objectives.

Exam Tip of the Day #99

210
Q

Actual Duration

A

The amount of elapsed time between the start and finish of an activity.

Exam Tip of the Day #100

211
Q

Control Account

A

A specific point in the work breakdown structure (WBS) where the project scope, budget, actual cost, and schedule are combined and then compared to earned value in order to establish performance metrics.

Exam Tip of the Day #101

212
Q

Common Cause

A

A predictable source of variation in a system.

Exam Tip of the Day #102

213
Q

Commitment Power

A

A type of power that uses commitment via alliances and partnerships on the project team to tackle challenges to the project as they arise; has a potential connection with referent power.

Exam Tip of the Day #103

214
Q

Communications Management Plan

A

The document, part of the project or program management plan, that addresses the communication flow of the project and contains a detailed description of the transmittal process, the transmittal schedule, and the administration process.

Exam Tip of the Day #104

215
Q

Expected Monetary Value (EMV)

A

A statistical technique, typically applied in decision tree analysis, used to determine the average outcome when contingent scenarios for future project risks must be considered.

Exam Tip of the Day #105

216
Q

Claims Administration

A

The process of managing a project’s contract claims.

Exam Tip of the Day #106

217
Q

Stakeholder Analysis

A

A technique by which quantitative and qualitative information is amassed and evaluated to determine whose interests should be considered throughout the project.

Exam Tip of the Day #107

218
Q

Intellectual Property

A

Ideas and concepts created by an individual or company, typically eligible for copyright or patent, thus providing ownership properties.

Exam Tip of the Day #108

219
Q

Functional Organization

A

An entity that is arranged by department or purpose and focuses on operational work rather than project work.

Exam Tip of the Day #109

220
Q

Change Control

A

The process of determining, documenting, reviewing, and then approving or rejecting any proposed modifications to project documentation, deliverables, or baselines.

221
Q

Context Diagrams

A

A graphical representation of the scope of a business system that includes processes, equipment, and computer systems and indicates the manner in which people and other systems interact with the business system.

Exam Tip of the Day #111

222
Q

Adjusting Leads and Lags

A

A technique used to align project activities with their scheduled target dates.

Exam Tip of the Day #112

223
Q

Control Costs

A

The process of observing project status in order to revise project costs and administer cost baseline revisions.

Exam Tip of the Day #113

224
Q

Compliance

A

Conformance to a rule, standard, law, or requirement.

Exam Tip of the Day #114

225
Q

Competition Power

A

A type of power that maximizes involvement in the project or idea in the form of competition to help enhance the commitment of those involved to work toward a more successful outcome of the project or idea.

Exam Tip of the Day #115

226
Q

Control

A

The process of contrasting actual performance to planned performance, assessing the resulting variances, and determining the actions that will improve performance levels.

Exam Tip of the Day #116

227
Q

Fallback Plan

A

The plan that will supersede the original plan if it is not effective.

Exam Tip of the Day #117

228
Q

Closed Procurements

A

The written formal notification, from the buyer to the seller, that the contract has been completed; typically completion is dependent on the seller meeting the terms and conditions of the contract.

Exam Tip of the Day #118

229
Q

Stakeholder Engagement Assessment Matrix

A

A matrix in which current and desired stakeholder engagement levels are listed for comparison.

Exam Tip of the Day #119

230
Q

Law

A

A standard created by local, state, or national governmental authority that requires compliance and often carries penalties for non-compliance.

Exam Tip of the Day #120

231
Q

Goods

A

Products that have been created and are available for purchase.

Exam Tip of the Day #121

232
Q

Change Control Board (CCB)

A

The group accountable for considering, appraising, and making decisions about (approval, postponement, or rejection) proposed project changes and for the documenting and communicating those decisions.

Exam Tip of the Day #122

233
Q

Control Scope

A

The process of observing project status and scope in order to administer scope baseline revisions.

Exam Tip of the Day #123

234
Q

Analogous Estimating

A

An estimation technique that relies on data (time, cost, resources needed) from a similar activity or project.

Exam Tip of the Day #124

235
Q

Cost Aggregation

A

Adding together the work package cost estimates for high-level WBS components, including control accounts, for the purpose of establishing the value of the total project or the control account work.

Exam Tip of the Day #125

236
Q

Conformance

A

Within the quality management system, the delivery of a product or result that falls within the acceptable tolerance levels of quality requirements.

Exam Tip of the Day #126

237
Q

Identify Risks

A

The process of identifying the risks that can impact the project and documenting their attributes.

Exam Tip of the Day #129

238
Q

Conduct Procurements

A

The process of receiving the seller response(s) to the request(s) for quote(s), information, proposal(s), or bid(s), then determining the seller(s), and awarding the contract(s).

Exam Tip of the Day #130

239
Q

Stakeholder Engagement Plan

A

The document, part of the project or program management plan, used to depict all processes, procedures, tools, and techniques that will be used to effectively involve stakeholders in project determinations and performance based on the stakeholders’ requirements, concerns, and potential impact.

Exam Tip of the Day #131

240
Q

Distribute Information

A

Deliver needed project information to stakeholders in an appropriate timeframe.

Exam Tip of the Day #128

241
Q

Compromise

A

A conflict resolution technique in which a solution involves (typically) a little of what everyone is proposing for a solution.

Exam Tip of the Day #127

242
Q

Non-disclosure Agreement (NDA)

A

A document signed by the owner of intellectual property and those who view it when it is not generally exposed to the public, or if it is a new idea, before it is displayed to the public.

Exam Tip of the Day #132

243
Q

Incremental Life Cycle

A

The progression of project phases characterized by an early determination of scope, the adjustment of time and cost estimates as the team learns more about the product, and an increase in functionality resulting from incremental delivery.

Exam Tip of the Day #133

244
Q

Change Control System

A

The procedures that govern modifications to project documents, deliverables, and baselines.

Exam Tip of the Day #134

245
Q

Create WBS

A

The process of breaking down the work of the project into minimal components for more effective management.

Exam Tip of the Day #135

246
Q

Applying Leads and Lags

A

A technique used to adjust time between activities by applying a lag (lengthening the time) or applying a lead (shortening the time).

Exam Tip of the Day #136

247
Q

Cost Baseline

A

The authorized project budget version, exclusive of management reserves, that requires a formal control process to effect changes and is used as the basis of comparison to actual costs.

Exam Tip of the Day #137

248
Q

Conformance to Requirement

A

The point where the project and product meet the standards of the written specifications defined at project inception (or modified through change control).

Exam Tip of the Day #138

249
Q

Conflict Management

A

The management of conflict within the project by applying such techniques as problem solving, collaboration, forcing, compromising, accommodation, and avoidance.

Exam Tip of the Day #139

250
Q

Exception Report

A

A report that includes significant variations from the planned activities.

Exam Tip of the Day #140

251
Q

Implement Risk Responses

A

The process of executing endorsed risk response plans.

Exam Tip of the Day #141

252
Q

Contract

A

A mutually binding agreement that requires, in accordance with the terms of the agreement, the seller to deliver goods or services to the purchaser and the purchaser to compensate the seller for those goods or services.

Exam Tip of the Day #142

253
Q

Stakeholder Register

A

A project document that lists stakeholder information including name, role, assessment, and classification.

Exam Tip of the Day #143

254
Q

Patent

A

A legal device which gives ownership of an idea or design to an individual or company that creates the idea or design.

Exam Tip of the Day #144

255
Q

Change Control Tools

A

Tools associated with modification and configuration management.

Exam Tip of the Day #146

256
Q

Decomposition

A

The process of breaking down the work of the project into smaller, more controllable components.

Exam Tip of the Day #147

257
Q

Backward Pass

A

A network diagramming method that calculates the late start (LS) and late finish (LF) dates of each activity by working backward through the schedule from the project completion date.

Exam Tip of the Day #148

258
Q

Cost Management Plan

A

The document, part of the project or program management plan, used to describe the framing, forming, observation, and control of project costs.

Exam Tip of the Day #149

259
Q

Conformance Work

A

Endeavors, typically related to prevention and inspection, that compensate for issues preventing organizations from achieving planned results.

Exam Tip of the Day #150

260
Q

Confrontation

A

Directly dealing with a conflict via problem-solving techniques so that the parties can work through any disagreement.

Exam Tip of the Day #151

261
Q

Forecast

A

The estimation of a future state of a project based on the performance levels of the organization or a previous project; typically includes measurements associated with estimate at completion (EAC) or estimate to complete (ETC).

Exam Tip of the Day #152

262
Q

Management Reserve

A

Funds set aside for unanticipated project work and excluded from the performance measurement baseline.

Exam Tip of the Day #153

263
Q

Contract Change Control System

A

System that manages contract amendments.

Exam Tip of the Day #154

264
Q

PMI Code of Ethics and Professional Conduct

A

A standard that PMI requires candidates to agree to before they take the PMP Examination.

Exam Tip of the Day #155

265
Q

Initiating Process Group

A

The processes associated with the inauguration of a new project or phase; typically involves obtaining approval and identifying project stakeholders.

Exam Tip of the Day #156

266
Q

Change Log

A

A list of proposed project modifications and their associated details including description, date, requestor, and status.

Exam Tip of the Day #157

267
Q

Define Scope

A

The process of developing the project scope statement, the document that details the expected results of the project.

Exam Tip of the Day #158

268
Q

Bar Chart

A

A graphical representation of schedule-related information. Typically, schedule activities or work breakdown structure components are displayed vertically on the far left of the chart, dates are displayed horizontally across the top of the chart, and activity durations are displayed as date-placed horizontal bars. Also see Gantt chart.

Exam Tip of the Day #159

269
Q

Cost of Quality

A

The total cost of achieving or failing to achieve desired quality: specifically the costs of achievement are those associated with planning, controlling, and assuring quality and the costs of failure are those associated with reworking, warranty, waste, and negative reputation.

Exam Tip of the Day #160

270
Q

Control Chart

A

A graphic representation of process data over time that is set against documented control limits and has a center line (mean) to assist in identifying trends.

Exam Tip of the Day #161

271
Q

Control Resources

A

The process of ensuring that the physical resources assigned and allocated to the project are available as planned and monitored throughout the project to determine that actual utilization conforms to planned utilization; non-conformance to the plan may require corrective action.

Exam Tip of the Day #162

272
Q

Information Gathering Techniques

A

Processes used to obtain and organize data from a variety of sources.

Exam Tip of the Day #163

273
Q

Monitor Risks

A

The process of monitoring known risks, reducing any risks, identifying any new risks, and monitoring risk reduction over the life of the project.

Exam Tip of the Day #164

274
Q

Control Procurements

A

The process of managing contract performance.

Exam Tip of the Day #165

275
Q

Professional and Social Responsibility

A

Ethics expected in project managers; includes balancing stakeholder interests and reporting violations.

Exam Tip of the Day #166

276
Q

Initiator

A

An organization or individual authorized and capable of starting a project.

Exam Tip of the Day #167

277
Q

Change Management Plan

A

A plan that defines the project change management process.

Exam Tip of the Day #168

278
Q

Delphi Technique

A

A technique used to gain concurrence from a group of experts about a specific issue; the technique is effected by using a questionnaire to solicit ideas from the experts, having the ideas summarized, having the experts add comments to the summaries, and repeating the process until a consensus is reached.

Exam Tip of the Day #169

279
Q

BIPERT (Bilogic Extension of the Network Diagram)

A

A model for parallel programs that depicts ingoing (inclusive) and outgoing (exclusive) links.

Exam Tip of the Day #170

280
Q

Cost Performance Index (CPI)

A

The ratio indicating the cost efficiency of resources, calculated by dividing earned value (EV) by actual cost (AC): a CPI of 1.0 indicates the project is proceeding as planned; a CPI greater than 1.0 more indicates the project is proceeding better than planned; and a CPI less than 1.0 indicates the project is not proceeding as well as planned.

Exam Tip of the Day #171

281
Q

Control Limits

A

The area comprised of three standard deviations that occur on either side of the mean of normal data distribution on a control chart.

Exam Tip of the Day #172

282
Q

Develop Team

A

The process of enhancing the capabilities, interaction and environment of the project team in order to refine project execution.

Exam Tip of the Day #173

283
Q

Kickoff Meeting

A

A meeting used to initiate the start of the project; typically attended by all the key stakeholders; can be done when Initiating or Planning is complete depending upon the organization.

Exam Tip of the Day #174

284
Q

Monte Carlo Simulation

A

A process that simulates possible project schedule or cost outcomes; often used to estimate required reserves based on the scatter diagram or probability table that is typically the output of the process.

Exam Tip of the Day #175

285
Q

Cost Plus Award Fee Contract (CPAF)

A

A contract in which the seller receives payments for actual costs related to completed work plus an award that is at the discretion of the buyer; the award that typically represents seller profit.

Exam Tip of the Day #176

286
Q

Input

A

Any internal or external item that is required before a process can continue; it can also be an output from a predecessor process.

Exam Tip of the Day #177

287
Q

Change Request

A

A formal solicitation for a project modification that relates to the approach to, or outcome of, the project.

Exam Tip of the Day #178

288
Q

Diagramming Technique

A

A method that indicates the logical links between data.

Exam Tip of the Day #179

289
Q

Bottom-up Estimating

A

An estimating technique in which individual estimates are rolled up to create a summary estimate for the project.

Exam Tip of the Day #180

290
Q

Cost Variance (CV)

A

The deficit or surplus of the budget at any specific point in time, calculated by subtracting the actual cost (AC) from the earned value (EV): a value of 0 indicates the project is on budget, a value greater than 0 indicates the project is under budget, and a value less than 0 indicates the project is over budget.

Exam Tip of the Day #181

291
Q

Control Quality

A

The process of testing a project’s product, service, or result and then issuing an approval or recommendation for change.

Exam Tip of the Day #182

292
Q

Log

A

Documentation of selected items that occur during a project, typically modified to reflect the condition of the item (issue, quality control item, action, or defect).

Exam Tip of the Day #184

293
Q

Multi-criteria Decision Analysis

A

A process that utilizes a decision matrix to systematically analyze project information such as risk levels, uncertainty, value, and prioritization.

Exam Tip of the Day #185

294
Q

Cost Plus Fixed Fee (CPFF) Contract

A

A contract in which the supplier receives payment for allowable costs plus a fixed fee typically based on estimated cost.

Exam Tip of the Day #186

295
Q

Iterative Life Cycle

A

The progression of project phases characterized by the development of scope details one iteration at a time, the adjustment of time and cost estimates as the team learns more about the product, and an increase in functionality resulting from iterative development.

Exam Tip of the Day #187

296
Q

Close Project or Phase

A

The process of completing each activity across all process groups in order to finalize a project or phase.

Exam Tip of the Day #188

297
Q

Facilitated Workshop

A

A focused session involving cross-functional stakeholders and a designated leader that is conducted to achieve a specific goal, such as the creation of project requirements.

Exam Tip of the Day #189

298
Q

Buffer

A

Reserves used to alleviate risks that could negatively impact the budget or schedule.

Exam Tip of the Day #190

299
Q

Cost-benefit Analysis

A

A financial analysis method that compares the potential revenue derived from an opportunity to the cost of that opportunity.

Exam Tip of the Day #191

300
Q

Cost of Nonconformance

A

Cost associated with not meeting quality expectations of the project or product.

Exam Tip of the Day #192

301
Q

```

~~~

Dictatorship

A

A decision-making technique that involves one person making the decision for the group.

Exam Tip of the Day #193

302
Q

Manage Communications

A

The gathering of meaningful project data to create communications that will be disseminated, placed in a repository for future access, and disposed of per the communications management plan.

Exam Tip of the Day #194

303
Q

Opportunity

A

A risk whose occurrence will result in a positive impact on the project.

Exam Tip of the Day #195

304
Q

Cost Plus Incentive Fee (CPIF) Contract

A

A contract in which the supplier receives payment for allowable costs, as well as a pre-negotiated fee and an incentive fee (if incentives are met).

Exam Tip of the Day #196

305
Q

Management by Projects

A

Performing day-to-day operations by a project management approach.

Exam Tip of the Day #197

306
Q

Configuration Management

A

A process which verifies that the products of the project are complete and accurate.

Exam Tip of the Day #198

307
Q

Focus Group

A

A focused session involving pre-qualified stakeholders, subject matter experts (SMEs), and a designated leader that is conducted to determine expectations and views regarding a potential product, service, or result.

Exam Tip of the Day #199

308
Q

Calendar Unit

A

The smallest time unit used in project schedules such as minutes, hours, shifts, days, weeks, months, quarters.

Exam Tip of the Day #200

309
Q

Definitive Estimate

A

A cost estimate that provides an accurate estimate of the project cost; the final cost estimate used before implementation; typically the range of -10% to +10%.

Exam Tip of the Day #201

310
Q

Which role controls resources in a typical exam question?

(A) Functional managers
(B) Project managers
(C) Senior managers
(D) Portfolio managers

A

Correct Answer: (A) Functional managers

Explanation: A typical exam question, unless otherwise stated, assumes a balanced matrix environment, which means that the project manager gets resources from the functional environment.

Exam Tip of the Day #202

311
Q

Dominators

A

A role that consumes project communication and focus with their own views without considering others.

Exam Tip of the Day #203

312
Q

Manage Stakeholder Expectations

A

The process of communicating with the stakeholders to determine their expectations and addressing issues in a timely manner.

Exam Tip of the Day #204

313
Q

Overall Project Risk

A

The impact that uncertainty, including the cumulative effect of individual risks, has on the project; the exposure of stakeholders to the implications of variations in project outcome, both positive and negative.

Exam Tip of the Day #205

314
Q

Cost Plus Percentage of Cost (CPPC) Contract

A

A contract that reimburses the seller for cost, plus a negotiated percentage of the total costs.

Exam Tip of the Day #206