11 - Project Schedule Management Terminology Flashcards
Activity
A unique, scheduled segment of project work that typically has associated cost, duration, and resources; sometimes called a task.
Activity Attributes
The characteristics of an activity that include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.
Activity Duration
The span of time, expressed as calendar units, between a scheduled activity’s start and finish.
Activity Duration Estimate
The projected duration of an activity.
Activity Identifier
A unique number or code used to identify an activity that is used to eliminate confusion with a similarly named activity.
Activity List
A listing of scheduled activities, with such details of a description, identifier, and scope of work, used to ensure that team members comprehend the work that will be performed during the project.
Activity Network Diagrams
A graphical representation of the interconnectivity of project activities.
Activity Resource Requirements
The determination of required resources for each work package and work period that are derived from the determination of required resources for each activity within the work package.
Actual Duration
The amount of elapsed time between the start and finish of an activity.
Adjusting Leads and Lags
A technique used to align project activities with their scheduled target dates.
Analogous Estimating
An estimation technique that relies on data (schedule, cost, resources needed) from a similar activity or project.
Applying Leads and Lags
A technique used to adjust time between activities by applying a lag (lengthening the schedule) or applying a lead (shortening the schedule).
Activity-on-arrow (AOA)
A network diagramming method in which activities are represented by arrows and connected at nodes to show their sequences; also known as ADM (arrow diagramming method).
Activity-on-node (AON)
A network diagramming method in which activities are represented by boxes or circles and connected via arrows; also known as PDM (precedence diagramming method).
Backward Pass
A network diagramming method that calculates the late start (LS) and late finish (LF) dates of each activity by working backward through the schedule from the project completion date.
Bar Chart
A graphical representation of schedule-related information; typically, schedule activities or work breakdown structure components are displayed vertically on the far left of the chart, dates are displayed horizontally across the top of the chart, and activity durations are displayed as date-placed horizontal bars; also see Gantt chart.
BIPERT
(Bilogic Extension of the Network Diagram)
A model for parallel programs that depicts ingoing (inclusive) and outgoing (exclusive) links.
Bottom-Up Estimating
An estimating technique in which individual estimates are rolled up to create a summary estimate for the project.
Buffer
Reserves used to alleviate risks that could negatively impact the budget or schedule.
Burst
The separation (or divergence) of activities on a network diagram from a central node.
Calendar Unit
The smallest time unit used in project schedules; it could be minutes, hours, shifts, days, weeks, months, quarters.
Control Schedule
The process of observing project status in order to revise progress and administer schedule baseline revisions.
Crashing
A compression technique to shorten the duration of the schedule, typically by adding additional resources to critical path activities.
Critical Chain Method
A technique applied to the schedule so the project team can ascertain the amount of float needed to offset uncertainties or limited resources that appertain to a schedule path.