Tendering and Procurement Flashcards
What is the difference between tendering and procurement?
Procurement is the overall act of obtaining goods and services from external sources (i.e. building contractor) and includes deciding the strategy on how those goods are to be acquired by reviewing the client’s requirements (i.e. time, quality and cost) and attitude to risk.
Tendering - is an important phase in the procurement strategy, that involves the bidding process, to obtain a price for goods/ services and how the contractor is appointed.
What are the main types of tendering strategies/procedures?
- Singe Stage
- Two-stage
- Negotiated
- Open
- Selective
- Framework
How can a robust tendering strategy ensure a positive tender result?
Robust tending can help ensure a positive tender by:
- accountability
- auditability
- ensuring everything has been picked up
- parity
- helping to reduce claims of corruption
- ensuring that the correct price has been paid for proposed works
What legislation covers Public Sector Procurement and when do they apply?
The Public Contracts Regulations 2015 when the employer is a public entity and the contract value exceeds a EU threshold.
What is the high level process for Public Sector Procurement?
The selection process is normally required to be preceded by issueing a notice on both Contracts Finder and the Official Journal of the European Union (OJEU)
When is single stage tendering approprait?
When the ERs are sufficiently defined to enable the work to be priced.
When is two-stage tendering appropriate?
Two Stage tends to be more appropriate for complex projects where the ERs have not crystallised and contractor/specialist input is required.
What is included within the enquiry letter?
An enquiry letter will be sent to the list of potential contractors and includes relevant project information often contained within a Project Information Schedule and a PQQ.
How long should be given for responses to PQQs?
JCT Tendering Practice note states 14 or 21 days for single-stage tendering however this can increase if there is an element of design required as part of the PQQ response.
What is included within the Project Information Schedule?
- The project and it’s estimated value
- The employer, professional team and point of contact
- tender procedure to be used (singe/two/neg)
- programme
- requirement for Contractors design (novation or not)
- any BIM requirements
- The Contract to be used
- draft Contract Particulars if available
- draft contract amends if available
- PCG or bond requoirements
- attetestation method
- basis of contract aware (lowest, quality time etc)
What is the purpose of the PQQ?
Establish the suitability of prospective tenderers based on their record, technical capacity etc.
What information is sought in PQQ?
- relevant or useful to the project. 4 main categories:
- Basic corporate particulars i.e. company name etc
- financial matters and good standing (i.e. convictions or open disputes)
- regulatory or compliance matters
- technical capacity - capability, skill and past performance
What is the recommended number of tenderers?
Depends on the project and context, however typically for most forms of contract between 3-6 tenders.
Design and Build scheme should have no more than 4.
What documents are included within the Tender pack?
- Drawings
- Bills of quants
- Specification or works schedules
- ERs
- Invitation to Tender
- Tender Form
How do you stipulate quality criteria during the tender?
If tendering is on a best value basis (quality and cost) the criteria and their respective weightings should be set out in the invitation to tender.