Tendering and Procurement Flashcards

1
Q

What is the difference between tendering and procurement?

A

Procurement is the overall act of obtaining goods and services from external sources (i.e. building contractor) and includes deciding the strategy on how those goods are to be acquired by reviewing the client’s requirements (i.e. time, quality and cost) and attitude to risk.

Tendering - is an important phase in the procurement strategy, that involves the bidding process, to obtain a price for goods/ services and how the contractor is appointed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the main types of tendering strategies/procedures?

A
  • Singe Stage
  • Two-stage
  • Negotiated
  • Open
  • Selective
  • Framework
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How can a robust tendering strategy ensure a positive tender result?

A

Robust tending can help ensure a positive tender by:
- accountability
- auditability
- ensuring everything has been picked up
- parity
- helping to reduce claims of corruption
- ensuring that the correct price has been paid for proposed works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What legislation covers Public Sector Procurement and when do they apply?

A

The Public Contracts Regulations 2015 when the employer is a public entity and the contract value exceeds a EU threshold.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the high level process for Public Sector Procurement?

A

The selection process is normally required to be preceded by issueing a notice on both Contracts Finder and the Official Journal of the European Union (OJEU)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When is single stage tendering approprait?

A

When the ERs are sufficiently defined to enable the work to be priced.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When is two-stage tendering appropriate?

A

Two Stage tends to be more appropriate for complex projects where the ERs have not crystallised and contractor/specialist input is required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is included within the enquiry letter?

A

An enquiry letter will be sent to the list of potential contractors and includes relevant project information often contained within a Project Information Schedule and a PQQ.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How long should be given for responses to PQQs?

A

JCT Tendering Practice note states 14 or 21 days for single-stage tendering however this can increase if there is an element of design required as part of the PQQ response.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is included within the Project Information Schedule?

A
  • The project and it’s estimated value
  • The employer, professional team and point of contact
  • tender procedure to be used (singe/two/neg)
  • programme
  • requirement for Contractors design (novation or not)
  • any BIM requirements
  • The Contract to be used
  • draft Contract Particulars if available
  • draft contract amends if available
  • PCG or bond requoirements
  • attetestation method
  • basis of contract aware (lowest, quality time etc)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the purpose of the PQQ?

A

Establish the suitability of prospective tenderers based on their record, technical capacity etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What information is sought in PQQ?

A
  • relevant or useful to the project. 4 main categories:
  • Basic corporate particulars i.e. company name etc
  • financial matters and good standing (i.e. convictions or open disputes)
  • regulatory or compliance matters
  • technical capacity - capability, skill and past performance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the recommended number of tenderers?

A

Depends on the project and context, however typically for most forms of contract between 3-6 tenders.

Design and Build scheme should have no more than 4.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What documents are included within the Tender pack?

A
  • Drawings
  • Bills of quants
  • Specification or works schedules
  • ERs
  • Invitation to Tender
  • Tender Form
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do you stipulate quality criteria during the tender?

A

If tendering is on a best value basis (quality and cost) the criteria and their respective weightings should be set out in the invitation to tender.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is included within the Invitation to tender?

A
  • the documents referenced within
  • time and date for return of tender bids
  • Point of contact for queries
  • basis of award (i.e. best value, lowest cost)
  • Arrangements and procedures selected for priced documents
  • the documents to be supplied by the tendering contractor (e.g. CPs, designs etc)
17
Q

What should you do if you receive a tender bid outside the submission window?

A

This tender should be discarded to ensure a fair tender inline with the recommended practice within the JCT Tender Strategies Practice Note.

18
Q

How do you ensure tender compliance?

A
  • Ensure all tenderers are issued with the same level of information.
  • ## If tender clarifications are issued these should be issued to all tenderers at the same time.
19
Q

What if a tenderer issues a qualified tender?

A

A qualified tender has exclusions or limitations away from contractual requirements. The tenderer should have the ability to amend to comply this at no change in price, otherwise the tender should be rejected.

20
Q

What should you do if you identify an error in a tender return?

A

There are two options which must be set out in the Invitiation to Tender.

Alternative One - the tenderer is given the option to stand by the potential error or withdraw their tender. Should they stand by it this should be documented.

Alternative two - The tenderer is given the oportunity to stand by their bid or amend their bid.

21
Q

What is a Private Finance Initiative?

A

A PFI is a long-term contract between a government entity and a private party to design, build, finance and operate a public asset and related services.

An example of this is The University College London Hospitals NHS Trust PI Project to develop the hospitals along Euston road etc.

22
Q

What would you do if you only received two acceptable PQQ responses?

A

Depending on time.
- I would reissue to oither parties as two parties doesnt provide an adequate number to ahvea competitive tender and good analysis.
- Undertake a negotiated tender

23
Q

What are the different types of procurement?

A
  • Design and Build
  • Traditional
  • Managment
  • Partnering
  • Design Build Finance Operate
24
Q

What is management procurement?

A

The works are constructed by a number of different contractors who are contracted to a management contractor appointed by the client.

25
Q

What are the of management procurement advantages and disadvantages

A

Advantages
- Early contractor engagement
- Early works can be progressed (excavations)

Disads
- Price uncertainty
- Cost premium
- Unsuitable for smaller projects
- Market Volatility

26
Q

What is the difference between management contracting and construction management?

A

Management contracting differs from construction managament in that management contractors contract works contractors direct, whereas construction managers only manage trade contracts, the contracts themselves are placed by the client

27
Q

Can you tell me about the E-tendering guidance note?

A

RICS Guidance Note: E-tendering 2010

  • E-tendering ten point plan
  • Methods of data exchange (physical media (CD, USB) emails, Cloud based
  • Security
  • Tender procedures (what format files should be sent in word, pdf, excel, dwg etc)

All in all it is good guidance however has to be taken with a pinch of salt as is dated from 2010 and since then there has been considerably advancements in technology and online infrastructure.