Contract Practice Flashcards
*Where are LD’s included in a contract?
Section 2.29 of the Contract (JCT DB) with a value inputted into the contract particulars.
- What part of a contract relates to quality?
Section 2.2 Materials, Goods and Worksmanship
Can you please name some different types of a JCT contract?
Minor Works
Intermediate
Standard
Design & Build
Prime Cost
Management
Major Works
What are included in the Recitals?
Recitals contextualise the agreement, giving factual explanations for the basis of the contract. Seven recitals describe what is required and the events that have taken place.
1-7 Recitals
1- Describes the work required, site and preparation of design and bills of quants
2- Confirms a priced copy of the bills of quants has been supplied to the employer
3 - Identifies contract drawings
4 - Identifies whether employer is considered a contractor for tax purposes
5 - Refers to an information release schedule (Optional)
6 - Whether works are to be carried out in sections
7 - Only applies when contractor is obliged to complete design works under a CDP.
What is included in the Articles?
These set out what is agreed between the parties.
Article 1
The obligation of the contractor
Article 2
The obligation of the employer
Article 3
Identifies the architect (or contract administrator) or employer’s agent).
Article 4
Identifies the quantity surveyor.
Article 5
Identifies the principal designer.
Article 6
Identifies the principal contractor.
Article 7
Makes reference to the right to adjudication in the event of any dispute.
Article 8
Makes reference to the right to arbitration in the event of any dispute.
What are the Contract Particulars?
Sets out the variables that are particular to the specific project.
What is attestation and how is it completed?
Attestation is the process of confirming that something is correct or genuine or that a requirement has been met. It can be completed as:
- A Deed - (signed and witness) - 12 years limitation period
- Underhand - just signed by both parties - 6 years limitation period
What happens if the value of LDs is left blank?
It means they are unliquidated damages and the value is agreed in court. It can be unlimited.
What is novation?
Novation is a process in which contractual rights and obligations are transferred from one party to another.
How does novation differ from assignment?
Assignment transfers the benefits of of a contract, Novation transfers both the benefits and the burdens/obligations.
When does a novation agreement need to be agreed.
Novation agreements need to be agreed at appointment with the consultant and be written into the contract with the contractor.
What is an alternative to a novation agreement?
A consultant switch - simply transfers the consultant from working for the client to the contractor by terminating the current contract and entering a new one.
Retail Hornchurch - How did you ensure that you were competent to draft a contract?
I have experience in drafting contracts previously and pulled the contract together using NBS Chorus. Once it was drafted I issued it to the employers legal representatives and for ensuring that is was legally sound.
Retail Hornchurch - At what point did you issue the contract particulars to the contractor for comment?`
I would input the the contract particulars that I could at the time, I would issued these to the contractor in a table for comment.
What is the retention in the JCT Minor Works Contract?
5%
What is the typical max value for JCT MW Contract?
£250k
Was the contract issued via Docusign, if so, how did you ensure that data is secured when contracts issued over docusign?
I safely stored contract documents in password protected files. I issued the contract to the legal advisors via an password protected file send. I received confirmation from all parties that they were happy for me to share the document in this manner.
What is the difference between CA and EA?
EA is for Design and Build Contracts whereas CA is for traditional forms?
The CA is completely impartial and the role begins following the execution of the contract.
EA is reports to the Employer.
Could please describe the process of implementing insurance option C?
In understanding the project i knew that the works were occurring within an existing building. I inputted Insurance option c within the contract particulars and shared this with the client and contractor for approval. I inserted this into the contract and advised my client of the requirement to take out joint names insurance of the works and the existing structure against specified perils.