Contract Administration Flashcards

1
Q

What is the key difference between Contract Administrator and Employers Agent?

A

Contract Administrator - is for traditional forms of contract and is impartial enforcing the obligations under the Contract.

Employers Agent - is for D&B contracts and is acting on behalf of the employer under the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is NBS Contract Administrator?

A

NBS CA provides a platform to assist in administoring JCT Contracts. It provides templates and guidance on forms for JCT Contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the JCT Contract Timeframes for payment notices?

A
  • Contractor required to make a payment application before valuation date.
  • Due Date 7 days after the Interim Valuation date.
  • Payment notice must be issued by EA no less than 5 days post Due Date.
  • Payless notice must be issued no later than 5 days before Final Date for Payment.
  • Final date for payment is 14 days post due date.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the EA payment notice called under JCT MW and IN?

A

Interim Certificate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does the Notice of Making Good do?

A

It confirms that the contractor has made good any latent defects during the rectification period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is included in the Notice of Completion of Making Good?

A
  • Project Stakeholder details (employer, Contractor, issuer (EA))
  • Issue Date
  • Contract Date
  • Site location
    -Works reference
  • Statement of confirming that the works required have been discharged and on the date that this occured.
  • Signatures of issuer
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How long does the contrator have to rectify defects raised after the rectification period?

A

The Contractor has reasonable time, otherwise the employer can employ someone else to rectify and deduct this from the retention.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How long is the latent defects period under the Limitation Act 1980?

A

6 or 12 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Should PC be issued if defects are present?

A

This depends on the defects. De mimimis defects can be undertaken post PC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What should you do if the employer is pressuring you to issue PC ahead of when you deem the works to be completed?

A

Warn client of the risks and then obtain written consent from the client. Written consent should also be sought from the contractor that they will finish any of the outstanding works/snags.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a latent defect?

A

A defect that could not have been reasonably discovered through inspection before the completion of the works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

For your Residential contract admin job in hornchurch, what other options could you have considered to solve the tenants furniture being left on site?

A

I considered whether deferring possession o site was an option. You can defer upto six weeks. However due to the tenant staying in an airbnb it was decided it was best to proceed and have the contractor protect adn remove furniture.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What were the cost and programme implications for the residential hornchurch project?

A

No programme impact, however cost of £400 to protect and or remove and store items and return them at completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does the CAI include?

A

Drafted on NBS it includes?
- Contract Details (employer, contractor)
- CAI Date
- Contract date
- CAI number
- Instruction description w/ reference to any design
- Instruction cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What section of the contract does it mention off-site materials?

A

Section 2.22 Unfixed Materials and Goods

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a Listed Item under the Contract?

A

a listed item is a material, good or prefab item for inclusion in the works which are listed in the ERs. If a listed item is paid for it becomes the employers property.

17
Q

Why couldn’t you have paid for the material in the York Way lab fit out and taken ownership of it under S.2.22?

A

Well this particular piece of kit was not a listed items and only listed items apply to this clause.

18
Q

What is a vesting certificate?

A

It is a document that proves that a material or item will transfer from one party to the other on payment.

19
Q

What are the risks of accepting goods that arent on site?

A

You can never be sure on the retention of title clause for further up in the supply chain. therefore if the contractor goes pop, although he vested with the employer. the supplier may have no vesting with the contractor.

20
Q

What is a non-completion notice?

A

The notice of non completion gives formal written notice that the contractor has failed to complete the contract works by the completion date.

21
Q

If the employer wants to leverage liquidated damages what do they have to do?

A
  • Issue non completion notice.
  • Issue notice of intention to leverage LDs
  • Issue payless notice.
22
Q

What is a letter of comfort, as mentioned in the Camley Street Office project?

A

In this instance a letter of comfort was a document that said the works would be granted building control approved subject to the approval of a fire damper arrangement, the change of location of a maglock to prevent head collision, supporting calcs to support SBEM and EPC output docs.

23
Q

Under the Letter of Comfort what would have happened should the contractor not have completed the outstanding items?

A

In addition to not having received PC, under Regulation 18 of the building regs 2022, if the outstanding building regs works aren’t completed in 3 months, the approved inspector will issue a cancellation notice and the works will revert to the local authority for enforcement.

The above would apply after 4 weeks if the building had become occupied.

24
Q

What are liquidated damages?

A

Are damages paid to cover the loss the client receives as a result of the project being in delay.

25
Q

What were the liquidated damages for the Camley Street project?

A

Stepped with incremental increases every 2 weeks starting at £5k capping at £20k pwk

26
Q

What does the Housing Grants, Construction and Regeneration Act do?

A

It is intended to ensure that payments are made promptly throughout the supply chain and that disputes are resolved swiftly.

27
Q

What are some provisions of the Housing Grants, Construction and Regeneration Act?

A
  • The right to be paid in interim, periodic or stage payments
  • The right to be informed of the amount due, or any amounts to be withheld.
  • The right to suspend performance for non-payment
  • The right to adjudication
  • Disallowing pay when paid clauses
28
Q

Was there any legal considerations you had to consider when handling and moving tenants belongings?

A

All tenant communication and dealings was handled by the property manager, who was also our client point of contact, however should this have fallen to me to arrange i would have reviewed the The Interferace with goods act 1977.

29
Q

Explain in detail the reasons you advised the client against including the off-site materials in the valuation at that stage. What risks were involved for the employer by including these costs without the materials being on-site?

A
  • No vesting cert in place
  • Should the contractor go bust there may be no recourse to collect the materials from the supply chain.
  • Cost wouldn’t be recoverable
30
Q

Describe the process and criteria you used to decide that the materials should not be included in the current payment application. What specific regulations or standards guided your decision?

A

Sale of Goods Act 1979 and Supply of Goods and Services Act
1982 would be pertinant and relevant legilsation that governs the transfer of ownership of materials which starts by saying that title passes to the purchaser/employer upon delivery regardless of payment.

The RICS also have a guidance note on interim valuations and payments

31
Q

How can you establish a contractors financial stability?

A

Dun and Bradstreet Rating assesses a companies financial risk.

32
Q

Who must issue the F10?

A
  • Commercial clients
  • PD or PC for domestic clients

However the client can instruct others to do this on their behalf however the responsibility still lies with them.

33
Q

What is included in an F10?

A
  • The date of forwarding the notice
  • Site adress
  • Local authority of the site
  • brief description of works
  • Details of PC and PD
  • Start and finish date of project
  • No. of people at work on site
  • Client declaration
34
Q

What should be done with the F10?

A

Issued to HSE and a copy kept on site.

35
Q

What is the CIS and what does it do?

A

Construction Industry Scheme

  • Under the CIS contractors deduct money from subcontractor’s payments and pass it to HMRC.
36
Q

What qualifies you as a contractor under the CIS?

A
  • You pay subcontractors for construction work
  • Your business does not do construction work but you have spent more than £3mil on construction in the 12 months since you made your first payment.
37
Q

Why did you increase the level of retention held for the Sandwich fit-out?

A
  • It provided more protection for my client and wasn’t challenged by the contractor.
  • Volatile market and allows for potential material price hikes
  • Accepted and and fairly industry standard