Tech Specs Flashcards

1
Q

Per TS 3.9.4, SDC and Coolant Circulation - High Water Level, how many SDC Loops shall be operable and in-operation?

A

ONE

Applicability: M6 with water level >23’ above flange

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

TS LCO 3.9.1 requires Boron to hold RX Core subcritical under cold conditions. What system is credited to maintain those conditions?

A

CVCS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Per TS LCO 3.9.2, if we have 1 required SRM Inoperable, what are the actions (Condition A)?

A

A.1. Suspend Core Alts (Immediately) AND

A.2. Suspend Positive RX Adds (Immediately)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Per TS LCO 3.9.2, how may SU range monitors shall be OPERABLE?

A

2

Applicability: Mode 6
* Enter 3.3.12 BDAS if made inoperable by SRM’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

U2 in M6. SDC “A” OOS. Using SDC “B”.

What level must be maintained in RCS?

A

> 23’ above flange

Need 2 SDC Loops Operable if <23’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

ENG reported fuel cavity is 135’. What is done if we only have 1 SDC Loop?

A

Add 2’ of water is option, but can’t keep moving fuel (3.9.5 to 3.9.4)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When is TS LCO 3.9.3 CTMT Penetrations Applicable? And what is required if 1 or more penetrations are NOT in required status?

A

During CORE ALTS

A.1. Suspend CORE ALTS (Immediately) AND
A.2. Suspend Fuel Movement (Immediately)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Can you move FUEL <23’ above the flange?

A

YES

  • Only when fuel being moved are NEW and not Irradiated (only INITIAL Load)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Per TLCO 3.9.100, how long SHALL the RX be subcritical prior to fuel movement?

A

100 Hours

  • If LESS, Suspend all OPS Immediately
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

If 1 FBEV’s is NON-FUNCTIONAL during movement of irradiated fuel assemblies in the Fuel Bldg, what is required, and how long can you do it (TLCO 3.9.104)?

A

A.1. Verify Functional FBEVS train capable of being powered from emergency source (Immediately) AND
A.2. Restore FBEVS to Functional (7 Days)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Why do we maintain SOLUBLE BORON in SFP?

A

SDM

< .95 kEFF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Why do TS LCO 3.9.4 and 3.9.5 allow for off-load to continue with stopping SDC < 1 hour out of 8?

A

Permits Core Mapping, Core Alts near Hot Legs and/or ST’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Per TS LCO 3.3.8 (CPIAS) what is it the backup system to during Modes 1,2,3 and 4?

A

CIAS

Closes CTMT purge valves in event of HI RAD levels from primary leak in CTMT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Per TS LCO 3.3.4, Condition D, If the Unit is at 80%, RTCB’s have problems on Channels 1 and 3 what do we do?

A

Open 1 and 3 Immediately

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

100% power, RCS PRESS HI Channel A FAILED, BUT No RTCB’s are open, what does TS LCO 3.3.4 require?

A

OPEN or OPEN Redundant (in 1 hour) AND OPEN the Affected RTCB (48 Hours)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Per TS LCO 3.3.9, Unit is in M1, and we lose CREFAS Train A, what is required? If a B train CREFAS RAD Monitor was taken OOS, what is then required?

A

NOTHING

A.1. Place CREFS train in essential (1 hour)

17
Q

Per TS LCO 3.3.3, 2 CEACS shall be Operable based on what reason?

A

Because a single RSPT is used to provide RSPT input to 1 CEAC in all 4 channels, this LCO requires BOTH CEAC’s to be Operable in each channel (prevent required trip from occurring)

18
Q

Per TS LCO 3.9.4, if SDC Loop requirements are NOT met, how long do we have to CLOSE all CTMT penetrations that have DIRECT atmosphere access?

A

4 Hours

19
Q

If 1 CEAC is INOPERABLE (TS LCO 3.3.3, Condition A), How often do we Verify indicated position of each FS or PSCEA is < 6.6” of all CEA’s in its group?

A

Once per 4 hours (SR 3.1.5.1)

20
Q

When is LCO 3.2.1 applicable, and what is the specified limit in the COLR?

A

Mode 1 with RTP > 20%

  1. 1 KW/FT
    * Cond. A = If COLSS > Power Op Limit LHR, we have 1 Hour to restore within Limits
21
Q

Per TS LCO 3.1.5, all FSCEA’s shall be OPERABLE, and aligned 6.6” within group in Mode 1 and 2. What is requirement if only 1 CEA position indicator channel is OPERABLE for 1 CEA per Group?

A

B.1 Restore at least 2 position indicator channels to OPERABLE in 6 Hours, OR

B.2. Verify CEA Groups with INOPERABLE position are fully withdrawn/inserted, while maintaining 3.1.6/7/8 every 6 Hours AND Once per 12 Hours

22
Q

What RCS DNB parameters are required for TS LCO 3.4.1 and when are they applicable?

A
  1. PZR Pressure 2130 - 2295 PSIA (M1 and M2)
  2. RCS Tcold within figure 3.4.1-1 (M1 and M2 with Keff >1)
  3. RCS Total Flow >155.8E^6 lbm/hour (M1)
23
Q

Per TS LCO 3.4.1, if PZR Pressure went to as low as 2100# for 30 minutes, what is required Condition?

A

3.4.1 Condition C - C.1 Restore parameters to within limits in 2 hours (MET and Exit LCO)

If not restored - D.1 Be in M3 in 6 Hours

24
Q

Per TS LCO 3.4.2 (RCS Minimum Temp for Criticality), what shall each RCS Loop temperature be greater or equal to, and when is it applicable?

A

Greater than or Equal to 545F (M1 and M2 with Keff >1)

Condition A - if NOT within Limit - A.1 Be in M3 in 30 Minutes

25
Q

Per TS LCO 3.1.1 (SDM - RX Trip Breakers Open), if it’s discovered that SDM is NOT GREATER or EQUAL to the value in the COLR, what are ACTIONS in M3?

A

3.1.1 Condition A - A.1 Initiate Boration to restore SDM within limits…IN 15 Minutes

Figure 3.1.1-1 (SDM %deltaK/K vs Tcold)