SIM LOIT Review Flashcards

1
Q

How do CHA-UV-505 and 506 FAIL?

A

Fail CLOSED on Loss of Air or Power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

U1 has a LOOP. PKA-M41 has just failed as well. What is status of CBO?

A

It is re-established with loss of M41

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of DFWCS “RTO”?

A

Prevent a post-trip overcooling transient

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Without Spray Pond support, how long can the EDG’s run?

A

2.6 Minutes Loaded

15 Minutes Unloaded

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

On a loss of 2 PN busses, what would we expect without Operator action?

A

RX TRIP and Full ESFAS Actuation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

On a SIAS and a LOP, what happens to NNN-D11/12/15/16?

A

D11 and 12 = Transfer to Class MCC’s
D15 = De-energized
D16 (U1/2) = De-Energized
D16(U3) = Transfer to Class MCC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When do PZR safeties relieve?

A

2475 PSIA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

On a loss of IAA-UV-2 what is impact to CVCS?

A

515 and 516 close

  • UV-2 closes on CSAS “A” and Loss of PKA
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the flow rates for SI PUMPS for a 1 Hour MIN FLOW LIMIT and UNLIMITED run times?

A
CS = 150 GPM (1 Hour) / 2100 GPM (UNL)
LPSI = 100 GPM (1 Hour)/ 2400 GRPM (UNL)
HPSI = 85 GPM (1 Hour)/ 225 GPM (UNL)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What do we classify Primary to Secondary Leakage as?

A

IDENTIFIED LEAKAGE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

As PZR LVL lowers, what type of actions would be taken to STOP the lowering (if can’t stop lowering)?

A
  1. Start ALL available CH Pumps
  2. Isolate LD
  3. Trip RX
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What alarms would we expect if Letdown was to ISOLATE (Time Critical Action-10 Minutes)?

A
  1. HI REGEN OUTLET TEMP
  2. LD LOW PRESSURE
  3. LD RAD MONITOR LOW FLOW
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the ways that CHN-UV-231P (Seal Injection Isolation valve) FAILS?

A
  1. Fails Open on Loss of Air/Power

2. Closes on HI-HI (150F) or LO-LO (70F), take open to reset (Temp inst. fails = doesn’t close)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The RVLMS normally has a delta of 90F, what would indicate a VOID?

A

Delta of 200F or HJTC > 700F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How is Turbine Cooling Water temperature maintained during Normal Ops?

A

Adjusting HX Outlet valve and Bypass valve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

U1 just had NBN-X03 fail. What impact does this failure have on NC Pumps?

A

NO Effect

17
Q

Both NC”A” and NC”B” pumps have tripped. EW has been cross-tied for Priority Loads. 30 minutes later what is status of the plant, assuming no further OPS actions?

A

Normal Ops with Letdown secured

18
Q

For the NC PSV’s (614/615) inside CTMT on the return line…what do they ensure?

A

Closure of CIV’s in event of RCP HP Seal Cooler tube rupture

19
Q

On a Loss of PW at Power, what is performed per the Loss of CW AOP?

A

Trip RX and Perform SPTA’s

20
Q

PLANT ANNUNCIATORS
Due to the differences in arrangement of power supplies between units, the following will occur on a loss of NKN-M45 with a SIAS:
Units 1 and 2 ___
Unit 3 ___

A

Units 1 and 2: Loss of ALL annunciators

Unit 3: Loss of 1/2 of the annunciators

  • Difference is U3 NNN-D16 backup supply is from PHB-M38 (not a SIAS load shed panel)