TB 162 - Metro Rail Regional Connector Phase Flashcards
The MRCTC project will provide an underground light rail system connecting the what to the 7th/Fig station?
Metro gold line
What is the expected completion date for the MRCTC?
2020
When did excavation for the tunnel construction begin?
September 2014
What are the 3 new underground stations that will be implemented in the project?
1st/central
2nd/broadway
2nd place/Hope
What is the budget for the project?
1.366 billion dollars
How long is the addition from
The metro rails little Tokyo/arts district to the 7th/fig station?
1.9 miles
The connector will provide a 1 seat ride between Azusa and what between east LA and Santa Monica (phase II) without transferring lines?
Long Beach
The what site is located between the 1st and alameda branches of the alignment?
“Mangrove”
The what will provide the design build contractors use and space for a tunnel boring machine (TBM)?
“Mangrove”
The 1st street/central avenue cut and cover station ends beneath the intersection of 1st and alameda, the alignment splits into how many directions?
2
The what will be constructed by cut-and-cover excavation methods, with branches extending to east and north?
“Wye” (2 legs of a true eye)
The eastern branch extends approximately how many feet within a cut-and-cover excavation to the beginning of an open trench structure?
419 feet
The open trench structure extends approximately how many feet father east toward the end of the alignment along 1st street?
401 feet
The northern branch adjacent to alameda street extends approximately how many feet within a cut and cover excavation to the beginning of an open trench structure?
812 feet
The open trench structure extends approximately how many feet farther north to the beginning of an above grade section?
409 feet
The depth of the excavation will range from a few feet approximately how many feet farther north to the beginning of an above grade section?
409 feet
The depth of the excavation will range from a few feet to approximately how many feet?
45 feet
Along the 1,354 foot long section of the cut and cover tunnels (flower street), the depth of the excavation will range approximately how many feet?
50 to 55 feet
For the 1st/central station, the depth of the excavation will be approximately how many feet below existing ground surface?
45 to 50 feet
For the 2nd/broadway station, the depth of the excavation will be approximately how many feet below existing ground surface?
95 to 100 feet
For the 2nd/Hope station, the depth of the excavation is approximately how many feet below the sidewalk elevation adjacent to hope and general Thaddeus kosciuszko way?
105 feet
For the 2nd/Hope street station, the depth of the excavation will be approximately how many feet below the existing ground surface at the west end of the station?
85 feet
Where is the 1 minded crossover structure located?
Immediately east of the 2nd street/broadway station
The 1 minded cross over structure is how many feet in length?
289 feet