Summary of Experience Flashcards

1
Q

What is included within a CPD Decision Tree

A

Does the CPD have a formally structured programme

Does the learning involve classroom like interaction with others

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are your firms policies on gifts

A

All gifts must be added to a gift’s register, the timing of the gift has to be properly considered

Anything over the value of £100 has to be raised with your line manager and declined

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

On Laindon Place, what were the abnormals causing costs which exceeded the typical range

A

Large roof voids increased the w:f ratio

A high concentration of smaller units, meaning more M&E required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the H&S at Work Act 1974

A

Legislation which governs H&S in the UK

Aims
a. Protect health,safety and welfare of people at work
b. Protect others against risks to H&S at work
c. Control dangerous Substances
d. Control emissions into atmosphere
e. Firms must have written H&S docs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How can you ensure safe working when asbestos is present

A

Use appropriate PPE
Asbestos Survey
Do not undertake work where there may be exposure to asbestos

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the difference between assests and liabilities

A

Assets are what is owned by a firm

Liabilities are what is owed by a firm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What information are companies required to submit under Companies Act 2006

A

income and expenditure,
assets and liabilities
key details about the company and the people who control it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is shown on a balance sheet

A

Assets
Liabilities
Capital

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is within the RICS’s business plan

A

Greater engagement with members

Greater participation in RICS Communities

Digitisation

Increasing diversity of members

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the three volumes of NRM

A

Volume 1: OCE and Cost Planning for Building Works
Volume 2: Detailed Measurement for Building Works
Volume 3: OCE and Cost Planning for Building Maintenance Works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What were the changes to the RIBA Plan of Work in the 2020 update?

A

Improved guidance in relation to BIM and sustainability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the difference between tender price inflation and construction inflation

A

An allowance included in the OCE or cost plan for fluctuations in the basic prices of labour, plant and materials during the period

TPI - from the base date (date of rates in cost plan) to the date of tender return

CI - from the date of tender return to the mid-point of the construction period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is an ideal w:f ratio

A

0.5-0.6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is an ideal net to gross ratio

A

Between 70-80%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

On PP, what allowances did you have to make in your Stage 3 cost plan for temporary works

A

Scaffolding to install the hand laid brickwork

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What was included in the value engineering document on PP

A

Changing the façade from brick to cladding

Changing the glass balustrades on the balconies to metal railings

Reducing the Floor to Floor Heights

17
Q

What is the Payment Timeline under the JCT D&B 2016

A

Interim Valuation Date is agreed in the Contract Particulars

The Due Date is 7 days after (works valued to this date)

5 days later, the Employer must issue a Payment Notice

Final Date for Payment is 14 days after the due date

Pay less notice date is 5 days prior to the final date for payment

Payment Mechanism is Contractor led

18
Q

What is the Payment Timeline under the JCT SBC 2016

A

Interim Valuation Date is agreed in the Contract Particulars

The Due Date is 7 days after

5 days later, the Employer must issue a Payment Notice

Payment Mechanism is not Contractor led. CA/A must make own assessment if no application is submitted

19
Q

What was included in the Preliminaries document on Newton Road

A

Project Particulars

The Site and Existing Buildings

Description of the Works

Form of Contract

Health & Safety Information

Practical Completion requirements

20
Q

What were some of the requirements for PC on Newton Road

A

All statutory provisions complied with

Contractor to provide a month’s notice of anticipated PC

Schedule of meter readings

Key and Fob requirements

O&M Manuals - test certs, description of system installed

21
Q

What are modern methods of construction

A

Off-site construction techniques

e.g. prebarication

22
Q

What are the advantages and disdvantages of MMC

A

ADV
- Built in factory - better working conditions, not weather dependent and better h&s
- Less material waste

DISADV
- Cost to transport to site
- Damage to materials - risk
- Specialists required to assemble works
- Parts may not fit with other elements or may be missing

23
Q

What was the value engineering process on Prestage Place

A

Cost plan was over the client’s budget and they wanted to bring it back in line with their budget, whilst maximising value

I attended a meeting with the project team to discuss value engineering ideas

I then created a value engineering register and presented the suggestions and effects of those suggestions for the design team to advise

24
Q

What was returned in the PQQ on DPL6/ how was the PQQ scored

A

They were based on:

Organisation & CVs

Financial Standing

Previous Experience

Health & Safety

Subcontractors

25
Q

On DPL6 - what was included in the tender documents

A

Design Information

Draft programme

Instructions for tenderers

A form of tenders

ER’s

26
Q

What was the process of carrying out the normalisation exercise

A

Following opening of the tender returns, I checked for errors and omissions

I then created a table which broke down the figures into the pricing schedule provided

I then created a normalisation section below and adjusted any omissions with the RLB’s PTE

27
Q

What does the JCT Tendering 2017 Practice Note say about errors and omissions in Tender Returns

A

2 ways to deal with errors

Alternative 1 - Tenderer should be informed and given the opportunity to confirm or withdraw. The process then begins with the next tenderer

Alternative 2 - Tenderer should be informed and given the opportunity to confirm or amend. If the tender is then not the lowest, the next offer should be examined

28
Q

What is included in the Dashboard Reports on CIW

A

Progress Update

Programme status

Cost Changes

Procurement Update

Health and Safety Update

29
Q

What is the Change Control process on CIW

A

COs received from client

Logged on a tracker

CO issued to Contractor

Contractor shares time/cost implication

Reviewed by client and myself

If client is happy to proceed, EAI is issued

30
Q

What was included in the cost breakdown for the LV Room works and Basement Roof

A

Prelims

Underpinning

Breaking out and excavation

Drainage

Finishes

31
Q

What is BREEAM and how does it work

A

Building Research Establishements Environmental Assessment Method

Rates the sustainable performance of a building

It is based on Energy, Land use, Water, Health and wellbeing, pollution, transport, materials, waste management

A BREEAM certified Assessor will then provide a rating based on the criteria

32
Q

On NR, they were looking at a BREEAM of ‘Very Good’ - what % rating is this

A

Betweeen 55-75%

33
Q

What is ‘Passivhaus’

A

A method of reducing heat losses from a building so it requires less heating
It uses passive heat sources like the sun, human heat, heat from appliances
How - airtight buildings, high performing windows with insulated frames, insulated envelopes

34
Q

How would building to Passivhaus affect the cost

A

It can increase the cost of a building between 3-8%