PROJECT FINANCIAL CONTROL Flashcards
What is the purpose of cost reporting
Provides the client of the likely out-turn cost of the project & allows them to make informed decisions
The client can understand where additions/omissions have occured
It provides an estimate of the final account
It keeps the client informed and avoids surprises for the client
What does a cost report contain
• Predicted cashflow against actual expenditure
• Instructed variations
• Anticipated variations
• Prov sums and prime costs
• Claims
What are the best practices when cost reporting
Each cost report should state the approved budget against which the variance is being stated.
All financial allowances in the budget should be exclusive of VAT
The quantity surveyor affords the client the earliest opportunity to take action to mitigate cost increases against a provisional sum, or make use of any cost saving achieved
The quantity surveyor should include a note in the cost report to draw attention to the costs provided by others and exclude liability for the accuracy of these costs.
What are the recommended course of actions if the likely outturn cost exceeds the budget
Omit elements of the construction works that are not critically required
Reduce the scale of elements e,g, size, height, spaces etc.
Reduce the specifcation of elements of works
What are the best practices when advising a client on loss and expense on reports
The basis of assessment should be explained to the clients
It is difficult to ascertain the full extent of loss and expense until the contractor makes his application as there could be also prolongation and disruptions costs from its sub contractors.
What are the best practices when reporting on LD’s
The amount of liquidated and ascertained damages which the client is entitled to recover from the building contractor should be reported in the cost report unless instructed otherwise by the client.
What is a provisional sum and what types are there?
A provisional sum is an allowance of money for works with limited design information
Defined provisional sums are when there is limited information available however sufficient amount for the contractor to allow time and resource within his programme .
Undefined provisional sums are when there is no or very little information available where by the contractor doesn’t allow for time and resource, and entitled to extension of time and loss & expense
What is cashflow
An analysis of when costs will be incurred and how much they will amount to during the life of a project.
How would you create a cashflow forecast
I would need to have access to the construction programme and contract sum analysis in order to populate the cashflow.
I would split the works into the different packages as shown on the contract programme and include individual s-curves for each package.
Obtaining drawdown schedules from specialist subcontractors and professional consultants can also assist when populating the cashflow.
What is the benefit of a cashflow forecast
a. Client can understand financial requirements over project duration and arrange funding
b. Used to check against valuations and indicate finanacial difficulties
What are variations
Changes to the design, quality or quantity of the contract works
Why might variations arise?
a. change to specification.
B. discrepancies between contract documents.
C. discrepancies with statutory requirements.
D. errors and omissions.
E. deficiencies in employer’s requirements.
What form must architect’s instructions take
Written is best practice
QS should not make changes to the contract for variations which aren’t written
Are oral instructions valid?
- It depends on the form of contract being used and whether they contain mechanisms for them to be valid.
- For example within the JCT DB:-
o Where the Contract Administrator issues an instruction not in writing, it shall have no immediate effect
o But the Contractor shall confirm in writing receipt of a verbal instruction within 7 days.
o If the CA does not dissent by notice to the Contractor within 7 days from receiving the contractors confirmation, it shall take effect as from the expiry of the latter 7 day period. - In my opinion it is always best practice to follow up verbal instructions with written instructions as soon as possible.
Can the contractor object to a variation
Some contracts allow the contractor to object to an instruction in special circumstances for example:-
• In the JCT SBC the requirement to comply with a valid instruction is subject to certain exceptions, where:-
o the instruction might affect the efficacy of the design of the Contractors Designed Portion.
o the instruction might affect the contractor’s compliance with the CDM Regulations.
o Where the instruction relates to a named specialist, and the contractor is unable to enter into a contract with that firm.
What can the architect do if the contractor does not comply with an instruction
- This depends on the form of contract being used however under JCT Suites if the contractor does not follow an instruction, the architect will be required to issue a ‘notice to comply’ to the contractor.
- If the Contractor still fails to comply within 7 days, the architect can instruct another party to carry out the work and the contractor will be liable for any additional costs incurred.
What 3 methods are there of obtaining a cost for variations under JCT forms of Contract
This depends on the form of contract being used, under JCT SBC, quotations can be made by:-
o Agreement between the employer and contractor.
o A schedule 2 quotation.
o Valuation by the QS under the valuation rules.
What are the time periods for Schedule 2 quotations under JCT SBC
o The architect should request via issue of an AI (EAI)
o The contractor has 7 days to notify that they will not provide one.
o If not, they have 21 days to provide the quotation.
o The architect then has 7 days to confirm in writing the acceptance or rejection.
o The acceptance is called the ‘confirmed acceptance’.