CONTRACT ADMINISTRATION Flashcards
What is nomination
Selection of a particular subcontractor by the client to carry out works, manufacture or supply of materials.
This provides the architect and client with greater control of material choice and thereby quality.
It is often used when there are long lead-in times with the employer placing orders prior to the Main Contract award which reduces potential delays on site.
The Main Contractor is relieved of liability of design and compliance with the performance spec in addition to subcontractor delays in respect of the works that have been nominated.
How do nominated subcontractors get paid
Nominated Contractors are normally paid via the Main Contract, with sums identified separately.
Can the contractor object to a nominated subcontractor?
Any objections must be made during the tender period.
There are specific exclusions and grounds for an objection for example if they have found out the subcontractor is having financial difficulties and may be going insolvent
If there are problems with the design, after Novation of the architect, who would be responsible
At Novation, the client would agree the design
In Novation, the benefits and obligations are transferred, so now the contractor is responsible for the Architect and design issues
Disputes may arise where it becomes unclear when problems have arisen, either prior to the transfer of services or afterwards.
What is set-off
Money owed to the client by the contractor
They are deducted against payments due to the Contractor
Describe differences between Statutory Provisions and Contract Provisions
Statutory provisions are set out by law & must be complied with.
Contract provisions relate to the contract in question & therefore only apply to a specific project.
After valuation and certificate are issued, the client advised that they don’t have sufficient funding to make the payment. What would you do
Once the certificate has been issued to the contractor, the client is contractually obliged to honour payment of the certificate and cannot withhold money without a valid reason.
I would contact the client and contractor ASAP to arrange some form of payment. It may be the case that the client has insufficient funds available in time for the final date for payment and it may be possible to defer payment by 1-2 days.
Failing this or if the contractor is unwilling to delay the payment, the client would need to find finance the payment through other funds to honour the certificate.
If an instruction was issued during the contract which involved the fabrication of a substantial amount of materials off site would you pay for them as off site materials within the valuation
I would check if there is a provision for off site materials in the contract
There is no obligation on the client to pay for materials off site if this is not identified in the contract
However in the scenario where the client wishes to pay for them, I would ultimately check with the client before paying or rejecting them.
How would you deal with the urgent Verbal Instructions
If the instruction affects the critical path or programme, I would review the instruction with the contractor administrator, client & contractor.
If the instruction is valid under the contract I would ensure this is converted into a formal written instruction as soon as possible.
What documents would be required in incorporating a Contractor Design Portion Supplement into a project
Within a Design & Build project, the documentation to be included would be the Employers Requirements including the Scope, Specification, Drawings, Contractors Proposals along with any insurances
Could an e-mail constitute a contract document?
Yes providing there is offer, acceptance, intention to create legal relations and the responding email does not vary the conditions, a contract will be created.
What is your opinion of Oral Contracts?
Whilst they are legally binding the difficulty lies in proving the specific terms and conditions of the agreement
It is for this reason why the HGCRA only applies to written contracts.
What is the difference between an information requirement schedule & an information release schedule?
a. The information required schedule asks the Contractor to provide dates when design information is required.
b. The information release schedule informs the Contractor when the design information will be available.
What is Frustration
Frustration occurs when any event or circumstances beyond control of both parties changes the contractual obligations or makes it impossible or illegal to fulfil their contractual obligations. The happening of such events automatically discharges contract.
What is the defects liability period
The defects liability period is the duration at the end of the contract, usually 6-12 months after the PC Certificate has been issued whereby the contractor undertakes to rectify any defects that arise within the structure at the contractors expense, providing they were due to materials & workmanship not being in accordance with the contract.
In the event that the contractor failed to rectify any defects the employer may employ another contractor to carry out the works & recover the cost of doing so from the Main Contractor.
The retention money retained may be used to cover the costs of making good.