QUANT & COSTING Flashcards

1
Q

Why was NRM introduced

A

a. The previous Standard Method of Measurement (SMM7) was designed for the production of bill of quantities for tender purposes.
b. This resulted in a lack of guidance and uniformity around preparing cost estimates and cost plans when using SMM7.
c. The NRM was introduced to provide a common and consistent basis for the production of order of cost estimates and cost plans and to give Employers more confidence around their inclusions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why should you use the NRM

A

a. The NRM provides a common and consistent basis for the production of order of cost estimates and cost plans.
b. This provides added confidence to Employers.
c. In the event that a QS or firm is pursued for negligence, the use of NRM would provide a means of defense as it represents best practice.
d. QS’s are not required to follow the NRM if they judge it as unsuitable for their specific project but they must have a good reason as to why this approach has been taken.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the NRM 1?

A

a. The RICS NRM 1 is the Order of Cost Estimating and Elemental Cost Planning.
b. This provides a structured basis for measuring building works and for the production of Cost Estimates and Cost Plans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the structure of the NRM 1

A

The key sections of NRM1 are:
1. Part 1: General introduction explaining the purpose of the document and how it should be used.
2. Part 2: Measurement rules for the production of order of cost estimates.
3. Part 3: Measurement rules for the production of elemental cost plans.
4. Part 4: Tabulated rules of measurement for elemental cost planning.
5. Appendices: With references to the definitions for GIA, functional units, NIA, elemental breakdowns, templates and general information required for cost plan production.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Where are GIA,GEA,NIA defined

A

The Code of Measuring Practice, produced by the RICS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the purpose of the Code of Measuring Practice

A

It precise definitions to permit the accurate and consistent measurement of buildings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What would you expect the percentage of NIA to GIA to be

A

For residential, ideally 80%
Range is around 75-85%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What do you measure in accordance with?

A

In the UK, NRM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the purpose of a BoQ

A

The purpose of the BoQ is to provide the estimator with an accurate picture of the scope of works and to provide a common and consistent basis for pricing.
Following receipt of Tender submissions, the BoQ also forms the basis of the Tender Analysis allowing an accurate like for like comparison to be undertaken.
Throughout the post contract stages it also provides the basis for the valuation rules of the contract for valuing variation items.
It also enables the contract works to be assessed and valued for the purposes of interim payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How would you structure a BoQ

A

In accordance with an elemental breakdown structure under NRM 2, I would include the following
sections:-
o Preliminaries (Main Contract).
o Facilitating Works.
o Substructure.
o Superstructure.
o Internal Finishes.
o Fittings, Furnishings and Equipment.
o Services.
o External Works.
o Provisional Sums.
o Dayworks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How would you describe the preliminaries section in a Bill of Quantities

A

• The preliminaries detail items of work that are required to enable the construction but are not
associated within the permanent measured works items.
• This could include items such as:-
o Site setup.
o Management & supervision.
o Insurances for the project.
o Task Lighting.
o Protections and temporary barriers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What information is required to measure preliminaries

A

• Contract duration.
• Location.
• Type of project (New Build vs. Refurb).
• The size of the project.
• Temporary works.
• Security.
• Methodology.
• Programme.
• Services.
• Employers accommodation.
• Contractor designed work.
• Sectional completion.
• Insurances / Bonds.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Who owns the copyright to a BQ

A

The originator owns the copyright.
This is the QS generally who provides the client permission to use the document for its intended purpose.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What would you include within the BoQ where works are to be carried out by Nominated Subcontractor

A

Prime cost sum would be incorporated including:-
o An allowance for the cost of the Nominated Subcontractors work (based on the quotation).
o An allowance for the contractor to price for attendances such as accommodation, welfare, storage, handling, materials & cleaning.
o An allowance for a percentage addition for any other charges & profit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How did you check that the items measured for the BoQ were accurate

A

• We have an internal peer review system where upon completion, a joint review of the drawings is carried out by my senior colleagues to ensure all scope of work items are captured.
• Junior colleagues assist with undertaking spot checks on the quantities to ensure these are accurate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a Preamble

A

• A preamble is an explanation of a document that is commonly found in contracts, specifications and bills of quantities.
• It can help with the interpretation of the document.
• It includes a description of the parties to the contract.
• The background to the document.
• Measurement procedures that have been adopted.

17
Q

What are method related charges

A

• A method related charge is a one-off item related to the method of carrying out the work and does not
form part of the permanent works.
• They are not considered proportional to the item of works to be carried out.
• For example provision of temporary propping required for a weakened elevation of an existing
building.

18
Q

What are time related charges.

A

• Time related charges are method related charges that are considered proportional to time taken to carry out the works for example plant hire

19
Q

What are fixed charges

A

• Fixed charges are method related charges that do not vary with time for example Service Connection Charges.

20
Q

What measurement items would you include in the measurement and construction of a basement or substructure?

A

Basement excavation (m3)
Disposal of excavated material (m3)
EO for disposal of contaminated material (m3)
Earthwork support (m2)
External basement retaining wall or shoulder to shoulder piles (m/m2)
Piling mats/platforms (m2)
Piles (nr)
Contiguous bored pile walls (m2)
Cutting off tops of excess piles (nr)
Pile tests (nr)

21
Q

How would you measure and what would you include in the ground floor or lowest level slab?

A

Ground floor/ lowest floor slab (m3)
Reinforcement (m2)
EO lowest floor construction for forming lift pits (m2)
Drainage below ground (m2)
Internal manholes (nr)
Testing & commissioning (%)

22
Q

How it the measurement of steel stated to be measured in the NRM

A

Structural steelwork in frames is to be measured in tonnage, including all fittings, fixings and components.
Fire protection to steel frame: to be stated and measured as the total mass listed separately
Factory applied paint systems

23
Q

What are the included components within the structural steel frame that are included within your measure

A

Columns, beams, lattice beams, braces, struts and the like
Fabrication, erection and permanent erection on site including holding down bolts, under base plates
Factory applied coatings, including fire protective coatings and paint systems.

24
Q

What would you include in the measurement of concrete frame?

A

Columns (m)
Beams (m)
Walls (m2)
EO for forminh openings in walls for doors, windows (nr)

25
Q

What would you include in the measurement of concrete frame of upper floors?

A

Suspended floor slabs (m2)
Rate of reinforcement (t)
Edge formwork (m)
Designed joints (m)
Surface treatments (m2)
Balconies (Nr)

26
Q

What wouuld you include in the typical measurment of a roof structure?

A

Pitched or flat roof structure (m2)
Roof coverings (m2)
Eaves, verge treatment to pitched roofs (m)
Edge treatment to flat roofs (m)
Flashings (m)
Gutters and rainwater pipe (m)
Testing and Comissioning (%)

27
Q

Can you name the group elements related to services

A

Sanitary installations
Disposal installations
Water installations
Lift and conveyor installations
Builder’s work in connection with services

28
Q

Can you name the group elements related to external works

A

Soft landscaping, planting and irrigation systems
Fencing, railings and walls
External fixtures
External drainage
External services

29
Q

What is included in the Contractor’s Prelimnaries

A

Site accommodation
Security
Management and staff
Insurance, bonds, guarantees and warranties.

30
Q

What other development costs are there that are usually excluded but need to considered

A

Land acquisition costs
Finanace charges
FF&E