CONFLICT AVOIDANCE AND DISPUTE RESOLUTION Flashcards

1
Q

What are good conflict avoidance processes

A

Good Management

Clear Contract Documentation

Good Project Management

Good Record Keeping

Good Payment Practice

Regular Reporting and Proactivity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How are good conflict avoidance processes implemented on a day to day basis

A

Client briefing allows the employers requirements to be understood

Taking minutes is a good for of record keeping

Monthly team meetings

Monthly valuations and interim assessments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is dispute resolution

A

Actions and processes to resolve contractual disagreements between parties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the three processes all dispute resolution techniques are built upon

A

Negotiation

Mediation/Conciliation

Adjudicative Processes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Name some forms of ADR

A

a. Mediation
b. Concilliation
c. Negotiation
d. Expert Determination

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Name formal methods of dispute resolution

A

a. Adjudication
b. Arbitration
c. Litigation
d. Dispute Boards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What would you consider prior to selecting a form of dispute resolution

A

a. The cost of dispute resolution in proportion to the claim being sought
b. The timescales involved
c. Impact on business relationships and reputation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Negotiation

A

Negotiation is where the parties work out between them how to resolve issues that have arisen. The power to settle the dispute rests with the parties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Mediation

A

The parties agree on an independent, third-party neutral system to facilitate discussions between them, with the goal of reaching a settlement.

The power to settle remains with the parties, but the process is led by the mediator.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Conciliation

A

The parties agree on an independent, third-party neutral system to facilitate discussions between them, with the goal of reaching a settlement.

The power to settle remains with the parties, but the process is led by the Conciliator, who makes a recommendation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the difference bewteen Mediation and Conciliation

A

A Conciliator only acts a ‘messenger’, whereas a Mediator tries to bring the parties together
Conciliator makes a recommendation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Expert Determination

A

The parties agreed by a contract that a third party will make a binding decision on them.
In most cases the decision of an expert will be final, and it will not be possible to appeal that decision.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is adjudication

A

Introduced by the Housing Grants, Construction and Regeneration Act 1996
Adjudication applies under most construction contracts except domestic, nuclear, food & drink
It was introduced to avoid contractors going bust from lengthy Arbitration & Litigation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What forces a building contract to have provisions for adjudication

A

Housing Grants, Construction and Regeneration Act 1996 (Construction Act)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the key steps and stages to Adjudication?

A

Either party to a contract may request the appointment of an adjudicator to be made within 7 days of serving a Notice of Dispute
The adjudicator has 28 days from issue of the referral to issue a decision
The period can be extended by 7 days by the referring party or 14 days by mutual agreement
The decision will be binding and enforcable in the TCC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is arbitration

A

Covered by the Arbitration Act 1996

The contract must contain a written agreement to arbitrate

A binding agreement must have been reached to escalate the matter to arbitration.

17
Q

How are Arbitrational tribunals arranged and what is the process?

A

JCT industry follows the process of Construction Industry Model
CIM process doesn’t have a formal hearing however on there maybe a short hearing
CIM process is document based

18
Q

What is litigation

A

Litigation is court hearing based dispute resolution
It is heard in the TCC, where a judge is appointed

19
Q

What are the three stages to a litigation case?

A
  1. Case Management Conference
    Outline how the case will be handled and what info will be needed prior to the hearing
  2. Pre-trial Review
    Ensure that all info requested has been provided
  3. Final Court Hearing
    The decision is legally binding and enforced
20
Q

What are the differences between arbitration and litigation

A
  1. Arbitration
    a. In order to arbitrate there must be an agreement to enter into arbitration by both parties.
    b. Parties have a wide degree of discretion as to how the proceedings are conducted.
    c. Procedures are similar to litigation with formal submissions by both parties, expert evidence, hearings and a decision by the arbitrator.
    d. It is a private process.
  2. Litigation
    a. Litigation differs in that proceedings are conducted in court.
    b. It is a public process that follows civil procedure rules.
    c. Despite having high costs, the process can deal with multi-party disputes and civil procedure rules which aim for accessibility, speed and efficiency.
21
Q

What does CPR stand for

A

Civil Procedure Rules