SI (Safety Injection) Flashcards
The HPSI cold leg injection orifice is used during simultaneous hot and cold leg injection to:
A. help balance SI flow to the hot and cold leg injection headers by being sized to allow approximately 50% flow.
B. provide instrumentation to measure flow to the hot and cold leg injection headers.
C. provide minimum recirculation flow for the HPSI pumps to prevent overheating.
D. prevent exceeding runout condition in the HPSI pumps to prevent pump cavitation.
Answer: A
Which one of the following is true concerning the 1A safety injection tank? The safety injection tank can inject water into:
A. Loop 1A only.
B. Loop’s 1A and 2A.
C. Loop’s 1A and 1B.
D. Loop’s 1A, 1B, 2A and 2B.
Answer: A
Which one of the following describes why the safety injection tanks are considered a passive system? (Assume the plant is at 100% power.)
A. Outlet valves automatically open on an actuation signal.
B. Tanks require minimal maintenance.
C. Injection from the tanks involves single manual action.
D. They require no electrical power to perform their function.
Answer: D
Which of the following parameter values would exceed the allowable ECCS design criteria per 10CFR50.46 ?
A. 2% sump water Iodine 131 concentration.
B. 2150°F peak clad temperature.
C. 20% through wall clad degradation due to oxidation.
D. .75% hydrogen generation due to the zirc water reaction.
Answer: C
Which one of the following will automatically occur when a recirculation actuation signal (RAS) is received?
A. Containment spray header isolation valve will open.
B. Refueling water tank outlet valve will close.
C. Low Pressure Safety Injection pumps will stop.
D. High Pressure Safety Injection pump discharge valve will close.
Answer: C
Which of the following statements correctly identifies when a HPSI pump is to be used for Emergency Boration per 40AO-9ZZ01, “Emergency Boration”?
A. Anytime RCS pressure is less than HPSI shutoff head.
B. Anytime a SIAS/CIAS occurs.
C. Only if Charging pumps are unavailable.
D. Only if Reactor Coolant System Tcold is less than 350 degrees F.
Answer: C
Which one of the following describes the signal that would have been generated when the reactor coolant system pressure lowers to 1800 psia?
A. Safety injection actuation signal
B. Main steam isolation signal
C. Recirculation actuation signal
D. Containment spray actuation signal
Answer: A
Which one of the following describes the signal that will be generated when the pressurizer reaches 1837 psia?
A. Main Steam Isolation Signal (MSIS)
B. Safety Injection Actuation Signal (SIAS)
C. Recirculation Actuation Signal (RAS)
D. Containment Spray Actuation Signal (CSAS)
Answer: B
Which of the following describes why the safety injection tanks do not dump their contents into the reactor coolant system during normal operation?
A. RCS pressure is less than SIT pressure and the force (D/P) upon the RCS check valves keep them closed.
B. The safety injection tanks are normally isolated until a SIAS signal is generated.
C. The safety injection tank injection valves are normally closed with their power supply breakers open.
D. RCS pressure is greater than SIT pressure and the force (D/P) upon the SIT check valves keep them closed.
Answer: D
Which one of the following is an important reason to locate and stop a leak in the safety injection piping outside of containment during a large LOCA?
A. Reduces the amount of fixed contamination that will remain in the containment after repair of the leak.
B. Prevent safety injection pump runout during the injection phase following a LOCA.
C. A LOCA outside of containment could result in inadequate containment sump inventory to allow recirculation.
D. Prevent short circuit of the auxiliary building electrical systems with resultant possibility of electric shock.
Answer: C
When filling a safety injection tank (NOP/NOT), which of the following is one possible consequence of stopping the HPSI pump and not closing the SIT fill/drain valve?
A. The SIT will flow into the RCS.
B. The SIT will flow into the RWT.
C. The RWT will flow into the SIT.
D. The RCS will flow into the SIT.
Answer: B
Shutdown cooling is used to cool the Reactor Coolant System from a maximum of _____ to the temperature required for refueling.
A. 350°F
B. 250°F.
C. 410°F
D. 500°F
Answer: A
A large break LOCA has occurred on Unit 2. Containment pressure is presently 13 psig. RWT level has dropped to approximately 6%. Which one of the following would you expect to occur based on this?
A. Safety injection suction valves from the RWT close.
B. Both HPSI pumps trip.
C. Containment spray valves close.
D. All safety injection pump recirculation valves close.
Answer: D
Which one of the following is a reason for Containment Spray flow following a LOCA?
A. To prevent the containment sump pH from exceeding 7.0.
B. To minimize the containment sump oxygen levels.
C. To reduce containment pressure during a loss of coolant accident (LOCA).
D. To minimize the possibility of corrosion cracking of metallic components inside containment.
Answer: C
Pressurizer pressure is 1250 psia. Pressurizer level is 45%. HPSI injection is 330 gpm/cold leg (acceptable flow). Reactor coolant system is 28°F subcooled. Reactor vessel level monitoring system indicates 100% in plenum and upper head. No reactor coolant pumps are running. Containment temperature and pressure are 195°F and 11 psig, respectively. SIAS, CIAS, MSIS, and CSAS have actuated. A cooldown is in progress using steam generators, both WR levels are 50%. WHICH ONE of the following identifies the action the Control Room Supervisor is to direct concerning high pressure safety injection use?
A. HPSI flow may be throttled until HPSI flow is the same as break flow.
B. Continue maximum injection flow until subcooling is at least 24°F.
C. HPSI flow may be throttled to restore pressurizer level 10 to 70%.
D. Continue maximum injection flow until subcooling is at least 44°F.
Answer: D